Johnson Controls World Services, Inc. v. United States

43 Cont. Cas. Fed. 77,463, 43 Fed. Cl. 506, 1999 U.S. Claims LEXIS 86, 1999 WL 270072
CourtUnited States Court of Federal Claims
DecidedApril 28, 1999
DocketNo. 98-612C
StatusPublished
Cited by4 cases

This text of 43 Cont. Cas. Fed. 77,463 (Johnson Controls World Services, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Johnson Controls World Services, Inc. v. United States, 43 Cont. Cas. Fed. 77,463, 43 Fed. Cl. 506, 1999 U.S. Claims LEXIS 86, 1999 WL 270072 (uscfc 1999).

Opinion

OPINION

MILLER, Judge.

This contract case is before the court after argument and supplemental briefing on plaintiffs motion to dismiss the complaint pursuant to RCFC12(b)(l). The sole issue under consideration is whether the court may retain concurrently jurisdiction over two government claims that request the same underlying quantum based on the same triggering events, distinguished only by the different clauses under which interest due is calculated.

FACTS

The two contracts involved are among a longstanding series of contracts awarded by the Department of the Air Force (the “Air Force”) for the performance of services on the Eastern Test Range (the “ETR”) dating back to 1953. After numerous business reorganizations, name changes, and asset transfers, Johnson Control World Services, Inc. (“plaintiff’), succeeded Pan American World Airways, Inc. (“Airways”); Pan Am World Services, Inc. (“PAWS”); and Pan Am Corporation under Contract No. F08606-78-C-0004, (the “1978 ETR contract”) and Contract No. F08606-84-C-0001 (the “1984 ETR Contract”).1

Special provision J.33 of the 1978 ETR contract stated:

a. It is recognized that the contractor’s pension plan is not presently fully funded. The unfunded liability is being amortized consistent with the provisions of the Employee Retirement Income Security Act of 1974, applicable Internal Revenue Service Regulation, and the contractor’s usual practices for funding such liabilities. The estimated cost of this contract does not include any amount for the unfunded liability for other than the period under contract.
b. If as a result of final close-out of this contract or any follow-on contracts, whieh-[508]*508ever occurs later, the contractor’s segment is closed, the contractor shall submit to the Contracting Officer a statement of this segment’s actuarially determined liability and plan assets as computed in accordance with the provisions of [Cost Accounting Standard] 413.
e. Pension fund adjustments will be determined in accordance with DAR Section 15, Part 2. Upon receipt of such statement and supporting documentation, the Contracting Officer, after audit review, shall negotiate with the contractor the amount considered as the fund deficit or excess. The difference between the market value of the assets and the actuarial liability for the segment will be considered as an adjustment to previously determined pension costs.
d. Any adjustment due to a deficit shall be treated as an allowable reimbursable (out-of-target) cost under General Provision 3 and General Provision 4. In such event, an adjustment to the estimated cost of this contract shall be negotiated. That portion of any excess applicable to this contract shall be applied in reduction of any payment to be made by the Government under this contract or will otherwise be credited or paid by such other means as the Contracting Officer may direct.
e. Failure to agree upon the amount of payment or repayment shall be treated as a dispute within the meaning of the clause entitled “Disputes” of the General Provisions.

The 1978 ETR contract incorporated by reference the pertinent clauses of the Armed Service Procurement Regulations (“ASPR”) requiring the contractor’s compliance with all applicable Cost Accounting Standards (“CAS”). Among these clauses ASPR 7-104.83(a)(5), Cost Accounting Standards, stated that the contractor shall

[a]gree to an adjustment of the contract price or cost allowance, as appropriate, if he or a subcontractor fails to comply with an applicable Cost Accounting Standard ... and such failure results in any increased costs paid by the United States. Such adjustment shall provide for recovery of the increased costs to the United States together with interest thereon computed at a rate determined by the Secretary of the Treasury pursuant to Public Law 92-41, 85 STAT. 97, or seven percent (7%) per an-num, whichever is less, from the time payment by the United States was made to the time the adjustment is effected.

The 1978 ETR contract also incorporated by reference ASPR 7-104.39, Interest. This clause permitted interest to accrue from “the date of the first written demand for payment” on “all amounts that become payable by the Contractor to the Government under this contract,” unless paid within 30 days from the date due. As a “follow-on” contract to the 1978 ETR contract, the 1984 ETR contract continued subject to the J.33 clause and the requirements of the CAS.2 The 1984 ETR contract also incorporated by reference updated versions of ASPR 7-104.83(a)(5) and ASPR 7-104.39, in a form virtually identical to their predecessors.

Performance under the ETR contracts was completed on September 30, 1988. Between November 1991 and November 1992, plaintiff terminated and cashed out its pension plan under the ETR contracts, receiving a gross reversion of $49,618,599.00. In addition, plaintiff received approximately $2,037,683.00 in mortality credits under participating insurance contracts retained by plaintiffs predecessor in interest. By letter dated June 28, 1993, plaintiff submitted to the Divisional Administrative Contracting Officer (“DACO”) its request for a final decision regarding alleged noneompliance with CAS 413.3

[509]*509In its claim plaintiff (1) recounted a series of communications and negotiations initiated by plaintiff in 1991 in which plaintiff, in good faith, attempted, but failed to conclude, settlement discussions with the Air Force regarding plaintiffs alleged noncompliance with CAS 413; (2) asserted that, in the course of these communications and negotiations, plaintiff had complied with CAS 413 by providing the required determination of the difference between the actuarial liability and the market value of the subject pension find assets as of the alleged segment closure corresponding to the conclusion of the ETR contracts in September 1988; and (3) advised the DACO that, despite the delegation of authority over CAS issues to the Air Force contracting officer on August 24, 1991, under federal regulation the DACO has exclusive authority over CAS noncompliance determinations and that such authority cannot be retained by or delegated back to the agency contracting officer.

On March 5, 1997, the Air Force contracting officer issued her final decision and demand for payment “for noncompliance with contractual and regulatory requirements to identify and refund the pension plan surplus [on the 1978 ETR contract and the 1984 ETR contract] and provide credits for known overbilling of pension costs.” The contracting officer based her decision on the occurrence of a “segment closure” upon the completion of the ETR contracts in September 1988 and plaintiffs subsequent failure to conduct an “asset versus liability” assessment required by provision J.33 in the 1978 ETR contract and provision H.871 in 1984 ETR contract. The contracting officer’s final decision explained that, because plaintiff was unwilling to recognize its liability under these clauses, an overbilling and overfunding of the pension plan in the amount of $56,115,322.00 resulted. The decision noted that, if plaintiff failed to remit this amount to the Government within 30 days, interest would accrue from the date of demand at a rate established in the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dodson Livestock Co. v. United States
48 Fed. Cl. 551 (Federal Claims, 2001)
Johnson Controls World Services, Inc. v. United States
48 Fed. Cl. 182 (Federal Claims, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
43 Cont. Cas. Fed. 77,463, 43 Fed. Cl. 506, 1999 U.S. Claims LEXIS 86, 1999 WL 270072, Counsel Stack Legal Research, https://law.counselstack.com/opinion/johnson-controls-world-services-inc-v-united-states-uscfc-1999.