Kurz & Root Co. v. United States

652 F.2d 69, 28 Cont. Cas. Fed. 81,142, 227 Ct. Cl. 522, 1981 U.S. Ct. Cl. LEXIS 127
CourtUnited States Court of Claims
DecidedMarch 3, 1981
DocketNo. 505-79C
StatusPublished
Cited by11 cases

This text of 652 F.2d 69 (Kurz & Root Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kurz & Root Co. v. United States, 652 F.2d 69, 28 Cont. Cas. Fed. 81,142, 227 Ct. Cl. 522, 1981 U.S. Ct. Cl. LEXIS 127 (cc 1981).

Opinion

This action for breach of contract is before the court on defendant’s motion for summary judgment. Without oral argument, and on the basis of the submissions of the parties, we grant the motion and dismiss plaintiffs petition.

H-1

Plaintiff is, and has for some years, engaged in the manufacture and sale of electrical generator equipment. On March 14, 1966, the United States Marine Corps, Department of the Navy, awarded to plaintiff contract NOm-73511, a fixed-price contract for the manufacture and delivery of production quantities of 30 kw generator sets and related items. The contract price, as amended by various modifications, was $1,414,841. On September 8, 1969, pursuant to the Government-furnished property clause and the changes clause of the contract, plaintiff submitted a claim to the Government’s contracting officer for an equitable adjustment of $950,727 in the stated fixed price. The gravamen of the claim was that performance of the contract had been made more difficult and costly by defective or inappropriate Government-furnished property. The claim was later increased to $1,034,326.1

During 1969 and 1970, the parties engaged in numerous discussions with a view toward a negotiated settlement of plaintiffs claim. Mr, Dan Elmore, who was at the time a Marine Corps contracting officer, was the principal negotiator for the Government. Plaintiffs principal negotiator was Mr. Daniel Ross, a lawyer in private practice. On December 14, 1970, the Government, acting through Elmore, and [524]*524plaintiff reached an oral agreement to settle the entire claim for $623,500. The agreement was based on and included a promise by the Government to make prompt, expeditious payment of the settlement amount to plaintiff.2 According to plaintiffs petition in this action,

[t]he promise by the government to make prompt payment was a highly significant factor in [plaintiffs] decision to settle its $1,034,326 claim for $623,500, and the promise actively induced [plaintiff] to agree to the reduced amount and relinquish the balance of its claim. The importance to [plaintiff] of prompt payment was that it was experiencing severe financial difficulties as a result of having its operating capital invested in the government contract work [which was the subject of its claim]. This fact was made known to the contracting officer during negotiations and regularly thereafter.

Elmore (the Government’s contracting officer) presented the settlement agreement, for post-negotiation clearance, to Mr. W. H. Underwood, who was director of procurement for the Marine Corps. In early January 1971, Underwood approved the agreement. At the time, Underwood considered it "a good deal.”

After approving the agreement, Underwood forwarded a request for settlement funds to the Navy Department. By March 3, 1971, funds for the settlement had been received by Elmore. On that date, Elmore informed Ross that a written supplemental agreement embodying the settlement would be ready for signature on March 5,1971.

This written supplemental agreement was never executed.

On 5 March 1971, before Mr. Ross and Mr. Brownell [plaintiffs president] arrived at Marine Corps Headquarters [to sign this agreement], events occurred that thwarted the actual execution of the Supplemental Agreement. Mr. Underwood received a call from the Deputy Quartermaster General of the Marine Corps. He was informed of certain information that the Marine Corps had been provided by the staff investigators of a House of Representatives Armed Services Subcommittee. It was allega[525]*525tions the staff investigators had developed and provided to the Marine Corps in connection with, among others, Mr. Elmore and Mr. Neuman [who was at the time assistant counsel to the Commandant of the Marine Corps and who had been involved in the negotiation of the settlement of plaintiffs claim], * * *.* * *
* * * * *
When Mr. Underwood received the information he became concerned about the integrity of the negotiation that he had approved in connection with the claim. He went down to Mr. Elmore’s office and directed that a settlement agreement not be executed. * * *3

At that point, Elmore became aware of a Navy procurement directive which appeared to require that the settlement, because it involved an amount over $600,000, be submitted to the Chief of Naval Material (CNM) for review and approval. Elmore apprised Underwood of the existence of this naval procurement directive. Thereafter, plaintiff was informed that the written supplemental agreement would not be executed on March 5, 1971, because the settlement had to be reviewed by CNM.

The settlement was then submitted by the Marine Corps to CNM for review and clearance. On April 20, 1971, CNM returned the clearance, disapproved, with a request for further information. No additional information was ever submitted to CNM by the Marine Corps.

In April 1971, the Marine Corps advised plaintiff that new personnel would have to review plaintiffs claim. Thereafter, the Marine Corps requested plaintiff to resubmit its claim. Without relinquishing its rights to the settlement agreement, plaintiff agreed to make a revised [526]*526submission of its claim. "On 10 September 1971 * * * [plaintiff] resubmitted its claim in the amount of $1,062,728, without prejudice to its position that the $623,500 was a final and binding settlement agreement.”4

On February 4, 1972, plaintiff requested a contracting officer’s final decision in writing. On February 9, 1972, a successor contracting officer issued a final decision which denied plaintiffs claim in its entirety. Plaintiff filed a timely appeal to the Armed Services Board of Contract Appeals ( asbca ).

The asbca held a hearing on the appeal and, at plaintiffs request, the issue was confined to the question:5

"Was there a binding and enforceable [oral settlement] agreement between the appellant and the Marine Corps Contracting Officer [Elmore] to pay the appellant $623,500 as a result of defective [Government-furnished equipment] * * *?”

On March 18, 1974, the asbca held that the oral settlement agreement was binding and enforceable between plaintiff and the Government. It therefore sustained plaintiffs appeal in the amount of $623,500 and otherwise denied the appeal.

On April 5, 1974, the Government issued a written modification to contract NOm-73511 whereby it paid plaintiff the sum of $623,500 and whereby plaintiff agreed as follows: * * * In consideration of such increase in contract price, the Contractor hereby waives all right, title and interest, if any, to any claims against Government arising under Contract NOm-73511, including, but not limited to, claims in regard to the Government-Furnished governor and the hump test.

On November 6,1979, plaintiff commenced this action. In its petition, it sets forth two counts for relief. Count I alleges that the Government breached the "(i) prompt payment requirement of the December 14,1970, settlement agreement and/or * * * (ii) its obligations under the Disputes Clause of Contract NOm 73511 to render a prompt, equitable, and impartial decision on Contractor’s [527]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AR Sales Co. v. United States
49 Fed. Cl. 621 (Federal Claims, 2001)
Doe v. United States
37 Fed. Cl. 74 (Federal Claims, 1996)
New Valley Corp. v. United States
34 Fed. Cl. 703 (Federal Claims, 1996)
CCM Corp. v. United States
35 Cont. Cas. Fed. 75,590 (Court of Claims, 1988)
Bowen v. Massachusetts
487 U.S. 879 (Supreme Court, 1988)
H.H.O., Inc. v. United States
32 Cont. Cas. Fed. 73,393 (Court of Claims, 1985)
Mazama Timber Products, Inc. v. United States
32 Cont. Cas. Fed. 72,759 (Court of Claims, 1984)
Brookfield Construction Co. v. United States
661 F.2d 159 (Court of Claims, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
652 F.2d 69, 28 Cont. Cas. Fed. 81,142, 227 Ct. Cl. 522, 1981 U.S. Ct. Cl. LEXIS 127, Counsel Stack Legal Research, https://law.counselstack.com/opinion/kurz-root-co-v-united-states-cc-1981.