Mazama Timber Products, Inc. v. United States

32 Cont. Cas. Fed. 72,759, 6 Cl. Ct. 87, 1984 U.S. Claims LEXIS 1325
CourtUnited States Court of Claims
DecidedAugust 24, 1984
DocketNo. 444-81C
StatusPublished
Cited by7 cases

This text of 32 Cont. Cas. Fed. 72,759 (Mazama Timber Products, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mazama Timber Products, Inc. v. United States, 32 Cont. Cas. Fed. 72,759, 6 Cl. Ct. 87, 1984 U.S. Claims LEXIS 1325 (cc 1984).

Opinion

OPINION

MEROW, Judge:

This case comes before the court on motions for summary judgment. Jurisdiction is based on 41 U.S.C. §§ 601-13.

[88]*88 Factual Background

On August 20, 1974 Mazama Timber Products, Inc. (Mazama) was awarded the Rush Creek timber sale contract in the Willamette National Forest, Blue River District, by the United States Forest Service. The contract provided that, in connection with the timber sale, plaintiff would construct roads according to Forest Service specifications. Shortly after construction began, plaintiff encountered difficulties regarding subsurface conditions. On June 18, 1979, pursuant to the Contract Disputes Act of 1978, 41 U.S.C. §§ 601-13, Mazama submitted a claim for $661,622.93 to the Forest Service for breach of contract. On January 25, 1980 the Forest Service issued a final decision denying the claim, and on December 18, 1980 Mazama filed suit in this court seeking relief on this road construction claim.1 Mazama continued contract performance pending resolution of the dispute.

In early April 1981, while its road construction suit was pending, Mazama received a bill for $166,051.97 from the Forest Service for timber removal. On April 24, 1981 Mazama advised the Forest Service that, in light of the existing $661,-622.93 construction claim, plaintiff would withhold any amounts due the Forest Service for the timber as a setoff. On May 12, 1981 defendant sent Mazama another timber bill for $44,468.32. On June 2,1981 the Forest Service issued plaintiff a final assessment for $188,707.29.

Upon Mazama’s initial refusal to make payments, the Forest Service requested payment from plaintiffs surety, United Surety (United). Defendant made a second request to United when it issued its final assessment on June 2, 1981. United refused payment, claiming it had no obligation under the contract. The Forest Service advised it would recommend United’s removal from the Department of Treasury’s list of approved sureties if payment were not forthcoming. On July 17,1981 plaintiff sought a temporary restraining order and a preliminary and permanent injunction in the United States District Court for the District of Columbia to prevent the Forest Service from initiating procedures revoking United’s Certificate of Authority. Upon denial of the claim, plaintiff paid defendant, under protest, $188,707.29 for timber and $2,041.63 in interest. Mazama subsequently requested return of the payments from the Forest Service. Upon receipt of the final decision refusing payment, Mazama filed this second suit for reimbursement of the $188,707.29 and $2,041.63 it paid the Forest Service and for $16,251.20 it incurred in attorneys’ fees seeking the temporary restraining order. Plaintiff (1) seeks review of the contracting officer’s final decision, and (2) alleges breach of contract because of defendant’s failure to cooperate and its wrongful pursuit of collection remedies.

During the pendency of this suit, plaintiff filed a petition for reorganization under Chapter 10 of the Bankruptcy Act, 11 U.S.C. §§ 501-676. On March 7, 1984 plaintiff’s payment bond was cancelled.

Cross motions for summary judgment have been filed and oral argument has been heard. For the reasons stated below, plaintiff’s motion for summary judgment is granted and plaintiff is awarded $188,-707.29 for the timber and $2,041.63 for the interest amounts it paid under protest as well as interest allowed in accordance with 41 U.S.C. § 611. Plaintiff’s prayer for attorneys’ fees is denied.

Discussion

1. Timber Claim

A. Common Law Setoff

Plaintiff correctly argues that its refusal to pay defendant was an exercise of its common law setoff right and that requiring payment was a breach of contract. The setoff right belongs “to every creditor, to apply the appropriated moneys of his debtor, in his hands, in extinguishment of the debts due him.” United States v. Munsey Trust, 332 U.S. 234, 239, 67 S.Ct. [89]*891599, 1602, 91 L.Ed. 2022 (1947). (Emphasis added.) Offsets are available to any debtor/contractor who also acts as a creditor. This includes the government, a private contractor, and a public contractor.

Contrary to defendant’s assertions, Mazama’s claim is sufficiently certain for a setoff. It is the subject of judicial proceedings. To exercise the right of setoff, pending resolution of the controversy, the claim need not be reduced to judgment. I.M.L. Freight, Inc. v. United States, 225 Ct.Cl. 393, 395, 639 F.2d 676, 678 (1980); Burlington Northern, Inc. v. United States, 199 Ct.Cl. 143, 147, 462 F.2d 526, 529 (1972); Project Map, Inc. v. United States, 203 Ct.Cl. 52, 55, 486 F.2d 1375, 1376 (1973). Defendant does not dispute that Mazama’s claims were made in good faith. Instead, defendant argues that a right to offset should not be recognized because of the potentially devastating effect it would have on future timber sale contracts. The Forest Service argues that recognizing a setoff right would encourage the submission of frivolous claims and would needlessly delay timber payment. However, this argument must await an appropriate case for its resolution since, in the instant matter, the setoff is based on a good faith claim asserted by plaintiff. Absent such a claim, a setoff right may well not be available.

Defendant also contends that, even if a right to setoff were recognized, it must be predicated upon a contracting officer’s final decision quantifying the claim. See Appeal of Transport Tire Co., 80-2 BCA ¶ 14,586 (1980). However, plaintiff has pleaded its $661,622.93 claim in this court. This pleading, together with RUSCC 11 and statutory provisions dealing with the submission of false claims (18 U.S.C. § 1001; 31 U.S.C. §§ 231-35; 28 U.S.C. § 2514), provide a guarantee of plaintiff’s good faith quantification of its claim. This is fully equivalent to the guarantee obtained from a contracting officer’s decision required as a predicate to a government set-off on a claim against a contractor.

Defendant also argues that a setoff is inappropriate in this case because plaintiff is insolvent. Defendant contends that if the construction claims plaintiff asserts as a basis for the setoff are denied, defendant may not be fully compensated for the timber. Rather, defendant would be required “to stand in line” with plaintiff’s other creditors.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Local Oklahoma Bank, N.A. v. United States
59 Fed. Cl. 713 (Federal Claims, 2004)
Cienega Gardens v. United States
38 Fed. Cl. 64 (Federal Claims, 1997)
Applied Companies v. United States
41 Cont. Cas. Fed. 77,122 (Federal Claims, 1997)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
C.B.C. Enterprises, Inc. v. United States
24 Cl. Ct. 1 (Court of Claims, 1991)
Transamerica Insurance v. United States
37 Cont. Cas. Fed. 76,037 (Court of Claims, 1991)
Dependable Insurance v. United States
34 Cont. Cas. Fed. 75,347 (Court of Claims, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
32 Cont. Cas. Fed. 72,759, 6 Cl. Ct. 87, 1984 U.S. Claims LEXIS 1325, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mazama-timber-products-inc-v-united-states-cc-1984.