Curtiss-Wright Corp. v. General Electric Co.

446 U.S. 1, 100 S. Ct. 1460, 64 L. Ed. 2d 1, 1980 U.S. LEXIS 119, 29 Fed. R. Serv. 2d 221
CourtSupreme Court of the United States
DecidedApril 22, 1980
Docket79-105
StatusPublished
Cited by1,516 cases

This text of 446 U.S. 1 (Curtiss-Wright Corp. v. General Electric Co.) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Curtiss-Wright Corp. v. General Electric Co., 446 U.S. 1, 100 S. Ct. 1460, 64 L. Ed. 2d 1, 1980 U.S. LEXIS 119, 29 Fed. R. Serv. 2d 221 (1980).

Opinion

Mb. Chief Justice BubgeR

delivered the opinion of the Court.

Federal Rule of Civil Procedure 54 (b) allows a district court dealing with multiple claims or multiple parties to direct the entry of final judgment as to fewer than all of the claims or parties; to do so, the court must make an express determination that there is no just reason for delay. We granted certiorari in order to examine the use of this procedural device. 444 U. S. 823 (1979).

I

From 1968 to 1972, respondent General Electric Co. entered into a series of 21 contracts with petitioner Curtiss-Wright Corp. for the manufacture of components designed for use in nuclear powered naval vessels. These contracts had a total value of $215 million.

In 1976, Curtiss-Wright brought a diversity action in the United States District Court for the District of New Jersey, seeking damages and reformation with regard to the 21 contracts. The complaint asserted claims based on alleged fraud, *4 misrepresentation, and breach of contract by General Electric. It also sought $19 million from General Electric on the outstanding balance due on the contracts already performed.

General Electric counterclaimed for $1.9 million in costs allegedly incurred as the result of “extraordinary efforts” provided to Curtiss-Wright during performance of the contracts which enabled Curtiss-Wright to avoid a contract default. General Electric also sought, by way of counterclaim, to recover $52 million by which Curtiss-Wright was allegedly unjustly enriched as a result of these “extraordinary efforts.”

The facts underlying most of these claims and counterclaims are in dispute. As to Curtiss-Wright’s claims for the $19 million balance due, however, the sole dispute concerns the application of a release clause contained in each of the 21 agreements, which states that “Seller . . . agree [s] as a condition precedent to final payment, that the Buyer and the Government . . . are released from all liabilities, obligations and claims arising under or by virtue of this order.” App. 103a. When Curtiss-Wright moved for summary judgment on the balance due, General Electric contended that so long as Curtiss-Wright’s other claims remained pending, this provision constituted a bar to recovery of the undisputed balance.

The District Court rejected this contention and granted summary judgment for Curtiss-Wright on this otherwise undisputed claim. Applying New York law by which the parties had agreed to be bound, the District Court held that Curtiss-Wright was entitled to payment of the balance due notwithstanding the release clause. The court also ruled that Curtiss-Wright was entitled to prejudgment interest at the New York statutory rate of 6% per annum.

Curtiss-Wright then moved for a certification of the District Court’s orders as final judgments under Federal Rule of Civil Procedure 54 (b), 1 which provides:.

“When more than one claim for relief is presented in an *5 action, whether as a claim, counterclaim, cross-claim, or third-party claim, or when multiple parties are involved, the court may direct the entry of a final judgment as to one or more but fewer than all of the claims or parties only upon an express determination that there is no just reason for delay and upon an express direction for the entry of judgment. In the absence of such determination and direction, any order or other form of decision, however designated, which adjudicates fewer than all the claims or the rights and liabilities of fewer than all the parties shall not terminate the action as to any of the claims or parties, and the order or other form of decision is subject to revision at any time before the entry of judgment adjudicating all the claims and the rights and liabilities of all the parties.”

The court expressly directed entry of final judgment for Curtiss-Wright and made the determination that there was “no just reason for delay” pursuant to Rule 54 (b).

The District Court also provided a written statement of reasons supporting its decision to certify the judgment as final. It acknowledged that Rule 54 (b) certification was not to be granted as a matter of course, and that this remedy should be reserved for the infrequent harsh case because of the overload in appellate courts which would otherwise result from appeals of an interlocutory nature. The essential inquiry was stated to be “whether, after balancing the competing factors, finality of judgment should be ordered to advance the interests of sound judicial administration and justice to the litigants.”

The District Court then went on to identify the relevant factors in the case before it. It found that certification would not result in unnecessary appellate review; that the claims *6 finally adjudicated were separate, distinct, and independent of any of the other claims or counterclaims involved; that review of these adjudicated claims would not be mooted by any future developments in the case; and that the nature of the claims was such that no appellate court would have to decide the same issues more than once even if there were subsequent appeals.

Turning to considerations of justice to the litigants, the District Court found that Curtiss-Wright would suffer severe daily financial loss from nonpayment of the $19 million judgment because current interest rates were higher than the statutory prejudgment rate, a situation compounded by the large amount of money involved. The court observed that the complex nature of the remaining claims could, without certification, mean a delay that “would span many months, if not years.”

The court found that solvency of the parties was not a significant factor, since each appeared to be financially sound. Although the. presence of General Electric’s counterclaims and the consequent possibility of a setoff recovery were factors which weighed against certification, the court, in balancing these factors, determined that they were outweighed by the other factors in the case. Accordingly, it granted Rule 54 (b) certification. It also granted General Electric’s motion for a stay without bond pending appeal.

A divided panel of the United States Court of Appeals for the Third Circuit held that the case was controlled by its decision in Allis-Chalmers Corp. v. Philadelphia Electric Co., 521 F. 2d 360 (1975), where the court had stated:

“In the absence of unusual or harsh circumstances, we believe that the presence of a counterclaim, which could result in a set-off against any amounts due and owing to the plaintiff, weighs heavily against the grant of 54 (b) certification.” Id., at 366 (footnote omitted).

In Allis-Chalmers, the court defined unusual or harsh cir *7 cumstances as those factors “involving considerations of solvency, economic duress, etc.” Id., at 366, n. 14.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

King v. Skolness
N.D. Georgia, 2020
Seana Barnett v. Sara MacArthur
Eleventh Circuit, 2017
Marilyn Newsome v. David Shoemake
Mississippi Supreme Court, 2017
Roberts v. Bennaceur
658 F. App'x 611 (Second Circuit, 2016)
NYSA Series Trust v. Dessein
631 F. App'x 54 (Second Circuit, 2015)
Nippon Yusen Kaisha v. Fil Lines USA Inc.
977 F. Supp. 2d 343 (S.D. New York, 2013)
L-7 Designs, Inc. v. Old Navy, LLC
964 F. Supp. 2d 299 (S.D. New York, 2013)
Miller Investment Trust v. Xiangchi Chen
967 F. Supp. 2d 686 (S.D. New York, 2013)
United States v. Apple, Inc.
889 F. Supp. 2d 623 (S.D. New York, 2012)
SkinMedica, Inc. v. Histogen Inc.
869 F. Supp. 2d 1176 (S.D. California, 2012)
Farrow v. J. CREW GROUP INC.
12 A.3d 28 (District of Columbia Court of Appeals, 2011)
Ben-Rafael v. Islamic Republic of Iran
718 F. Supp. 2d 25 (District of Columbia, 2010)
Clark v. Baka
593 F.3d 712 (Eighth Circuit, 2010)
Torres v. City of Madera
655 F. Supp. 2d 1109 (E.D. California, 2009)
Bayird v. Floyd
2009 Ark. 455 (Supreme Court of Arkansas, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
446 U.S. 1, 100 S. Ct. 1460, 64 L. Ed. 2d 1, 1980 U.S. LEXIS 119, 29 Fed. R. Serv. 2d 221, Counsel Stack Legal Research, https://law.counselstack.com/opinion/curtiss-wright-corp-v-general-electric-co-scotus-1980.