Cold Metal Process Co. v. United Engineering & Foundry Co.

351 U.S. 445, 76 S. Ct. 904, 100 L. Ed. 2d 1311, 100 L. Ed. 1311, 1956 U.S. LEXIS 1802
CourtSupreme Court of the United States
DecidedJune 11, 1956
Docket76
StatusPublished
Cited by224 cases

This text of 351 U.S. 445 (Cold Metal Process Co. v. United Engineering & Foundry Co.) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Cold Metal Process Co. v. United Engineering & Foundry Co., 351 U.S. 445, 76 S. Ct. 904, 100 L. Ed. 2d 1311, 100 L. Ed. 1311, 1956 U.S. LEXIS 1802 (1956).

Opinion

*446 Mr. Justice Burton

delivered the opinion of the Court.

This is a multiple claims action in which the District Court entered a judgment disposing of but one claim. Pursuant to Rule 54 (b) of the Federal Rules of Civil Procedure, as amended in 1946, 1 that court expressly determined that there was no just reason for delay and expressly directed the entry of judgment. Thereupon, an appeal was taken to the Court of Appeals, and the issue before us is whether the latter court has jurisdiction to entertain that appeal under 28 U. S. C. § 1291, 2 although an unadjudicated counterclaim awaits disposition in the District Court. The issue is comparable to that decided in Sears, Roebuck & Co. v. Mackey, ante, at 427, except that here the unadjudicated claim is a counterclaim arising in part out of the same transactions and occurrences as the adjudicated claim. By applying the reasoning used in the Sears case, we reach a like conclusion here and uphold the jurisdiction of the Court of Appeals.

While the counterclaim arises in part out of the same transactions as does the adjudicated claim, it was filed long after the principal proceeding was begun, and is in the nature of an action ancillary to the principal proceeding and bears a separate case number. Upon request of both parties, the District Court has removed the counterclaim from the trial calendar, without prejudice to either party, leaving it subject to reinstatement for trial at any time by order of the court upon its own initiative, or upon request of either party after reasonable notice. A brief review of the entire proceedings and a disclosure of its subject matter throws light on the relationship between the adjudicated claim and the counterclaim.

*447 In 1927, petitioner, The Cold Metal Process Company, an Ohio corporation, and United Engineering & Foundry Company, a Pennsylvania corporation, entered into a contract for the purpose of securing a patent in the name of Cold Metal relating to a certain type of steel rolling mill and of granting to United an exclusive license to make, use and sell mills under such patent. To that end, the parties contributed claims under their respective patent applications and it was agreed that the license should be granted when the patent was issued. The parties also agreed to try, by negotiation, to determine the amount of the payment by United for the license. If the parties could not agree on that point, the subject was to be submitted to arbitration in a manner specified in the contract. 3

In 1930, the patent was issued but Cold Metal refused to treat the 1927 contract as conferring an exclusive license on United. Cold Metal maintained that United was not a licensee until the amount due Cold Metal had been determined and paid. United, on the other hand, treated the contract as an enforceable exclusive license under which the license fee was to be determined later.

After litigation not now material, 4 Cold Metal, in 1934, instituted the present proceeding, Equity No. 2991, against United in the United States District Court for the Western District of Pennsylvania. Cold Metal asked (1) for an injunction restraining United from prosecuting certain suits, pending in Ohio and elsewhere, founded upon United's claim of exclusive rights under the patent, and (2) for determination of the amount to be paid by United under the 1927 contract. The court declined to issue a preliminary injunction, 9 F. Supp. 994, but Cold Metal appealed from such denial and, in 1935, obtained *448 a reversal directing the injunction to be issued, 79 F. 2d 666.

In 1936, Cold Metal, in line with the foregoing results, filed a supplemental complaint asking that the 1927 contract be “cancelled, revoked and annulled” and that United be enjoined from further operations under the patent. However, in 1938, the District Court, after trial, held the contract valid and enforceable, and directed an accounting before a master. 83 F. Supp. 914.

Cold Metal appealed but, in 1939, the Court of Appeals reversed its 1935 decision and largely sustained United’s position. It ordered that the injunction against United’s infringement suits be dissolved and held that the 1927 contract created a valid and enforceable exclusive license in favor of United. It also stated that the master could determine, from an “understanding” between the parties as shown by the record, the amount due from United under the 1927 contract. 107 F. 2d 27.

In 1941, United asked leave to file an amended answer and counterclaim, complaining that Cold Metal’s recent acts were inconsistent with the 1939 judgment of the Court of Appeals. In 1942, the District Court denied that motion on the ground that it could carry out only the existing mandate of the Court of Appeals. 43 F. Supp. 375. It suggested, however, that the injunction sought by United in its counterclaim should be the subject matter of another action, and that United could assert, before the master, Cold Metal’s breaches of the 1927 contract. In 1943, the District Court modified its 1938 decree to make it conform to the Court of Appeals’ order of 1939. It also appointed a master to determine not only the amount due Cold Metal from United for its past operations, but the payments to be made on licensed mills in the future.

In 1949, United refiled its claims as an “Ancillary Cross Complaint” in Civil Action No. 7744. United sought, *449 inter alia, (1) to enjoin the prosecution of infringement suits by Cold Metal against parties using mills under licenses granted by United, (2) to require Cold Metal to account for any funds it had collected for the use of such mills within the field of United’s exclusive license, and (3) to set off those funds from any payment or royalty that might be due from United to Cold Metal under the 1927 contract. In 1950, the District Court dismissed the cross complaint on the ground that it was not ancillary to Equity No. 2991. 92 F. Supp. 596. However, in 1951, the Court of Appeals reversed the District Court. It held that United’s cross complaint was, in reality, a counterclaim, ancillary to Equity No. 2991, and, therefore, within the jurisdiction of the District Court. 190 F. 2d 217. The Court of Appeals reviewed the previous course of the proceedings and pointed out that the claims now made by United in this counterclaim are entirely dependent upon the 1939 decision of that court, 107 F. 2d 27, which upheld the validity of United’s exclusive license.

Into this situation, in 1954, came the master’s report on the accounting in Equity No. 2991. It listed the licensed mills, fixed the compensation payable under the 1927 contract, and found that United’s license had existed from 1930 to 1947 and that United’s customers were duly licensed to use the patented mills.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chantal Attias v. CareFirst, Inc.
969 F.3d 412 (D.C. Circuit, 2020)
Joseph Pakootas v. Teck Cominco Metals, Ltd.
905 F.3d 565 (Ninth Circuit, 2018)
Marilyn Newsome v. David Shoemake
Mississippi Supreme Court, 2017
Tetra Technologies, Inc. v. Continental Insurance
755 F.3d 222 (Fifth Circuit, 2014)
Jackson v. Volvo Trucks North America, Inc.
462 F.3d 1234 (Tenth Circuit, 2006)
Myers v. Medical Center of Delaware, Inc.
28 F. App'x 163 (Third Circuit, 2002)
Berckeley Investment Group, Ltd. v. Colkitt
259 F.3d 135 (Third Circuit, 2001)
Russoli v. Salisbury Township
126 F. Supp. 2d 821 (E.D. Pennsylvania, 2000)
E.I. DuPont De Nemours & Co. v. Phillips Petroleum Co.
720 F. Supp. 373 (D. Delaware, 1989)
Avondale Industries, Inc. v. Travelers Indemnity Co.
123 F.R.D. 80 (S.D. New York, 1988)
Coca-Cola Bottling Co. v. Coca-Cola Co.
654 F. Supp. 1419 (D. Delaware, 1987)
Cullen v. Margiotta
811 F.2d 698 (Second Circuit, 1987)
TBS Pacific, Inc. v. Tamura
686 P.2d 37 (Hawaii Intermediate Court of Appeals, 1984)
Holliday v. Xerox Corp.
555 F. Supp. 51 (E.D. Michigan, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
351 U.S. 445, 76 S. Ct. 904, 100 L. Ed. 2d 1311, 100 L. Ed. 1311, 1956 U.S. LEXIS 1802, Counsel Stack Legal Research, https://law.counselstack.com/opinion/cold-metal-process-co-v-united-engineering-foundry-co-scotus-1956.