Project Map, Inc. v. United States

486 F.2d 1375, 203 Ct. Cl. 52, 1973 U.S. Ct. Cl. LEXIS 152
CourtUnited States Court of Claims
DecidedNovember 14, 1973
DocketNo. 31-73
StatusPublished
Cited by16 cases

This text of 486 F.2d 1375 (Project Map, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Project Map, Inc. v. United States, 486 F.2d 1375, 203 Ct. Cl. 52, 1973 U.S. Ct. Cl. LEXIS 152 (cc 1973).

Opinion

Per Curiam :

This case implicates three contracts plaintiff Project Map, Inc. has had with the Department of Labor. The contractor sues to recover $26,166.42 admittedly due it under Contract 0424. The defendant has withheld that sum from the amount concededly owing under that agreement because, on the other two contracts (Contracts 0401 and 0430), the contracting officer determined that plaintiff had been overpaid by at least that figure. In each instance this determination of overpayment was appealed to the Department’s Board of Contract Appeals, and both disputes are still pending before that tribunal. The contractor says that there is no dispute as to Contract 0424, on which it is suing, and therefore it should now be paid the full sum due under that agreement. The Government admits that there is no controversy as to 0424 but asserts a right to set off, on that agreement, amounts it claims owing to it under the other two contracts. Both sides have moved for summary judgment.

Part III of Dale Ingram, Inc. v. United States, 201 Ct. Cl. 56, 76, 475 F. 2d 1177, 1188 (March 1973), dealt with [54]*54precisely the same problem. In that instance, too, the defendant withheld payment of a sum awarded by the Board of Contract Appeals on one contract because there was then pending before the Board a dispute as to another of the contractor’s agreements under which the contracting officer had held the contractor indebted to the Government in a larger sum. That plaintiff, just like Project Map, Inc., argued that the failure to pay the conceded sum was a breach of contract entitling the claimant to immediate judgment. The court squarely rejected this contention “because the Government has a right of off-set with respect to the decision of the contracting officer [on the other contract] now pending before the Board in which he held that the plaintiff is indebted to the Government in the sum of [a figure greater than that withheld]. The decision of the contracting officer in this regard is final and binding until and unless it is reversed or changed by the Board or by this court should the case be appealed here from the Board. Consequently, the Government has the right to withhold the [sum withheld] awarded to the plaintiff in this case until [the other appeal] has been finally decided.” 201 Ct. Cl. at 76, 475 F. 2d at 1188.

Dale Ingram, Inc. is dispositive here. We do not agree with plaintiff that that holding was counter to 31 U.S.C. § 227,1 a provision which is limited to prescribing the procedure for offsets against court judgments obtained against the Federal Government. The section does not deal with the federal right of set-off prior to the entry of a court judgment, nor does it suggest in any way that the set-off rights of the Federal Government, unlike those of other creditors, are confined to the single remedy of set-off after a judgment has been obtained. On the contrary, in United States v. Munsey Trust Co., 332 U.S. 234, 239 (1947), the Supreme Court said that “the gov[55]*55ernment has the same right ‘which belongs to every creditor, to apply the unappropriated moneys of his debtor, in his hands, in extinguishment of the debts due him.’ ” See, also, Madden v. United States, 178 Ct. Cl. 121, 122-23, 371 F. 2d 469, 470 (1967). There is no intimation that this right is restricted solely to a debt which is admitted by the debtor, and that has not been the practice either of the Government or of the private commercial world.

If 31 U.S.C. § 227 has any bearing at all, its underlying policy serves to support the ruling in Dale Ingram, Inc. The section declares that, in the circumstances to which it applies, the Comptroller General, once the alleged debtor disputes his obligation, shall cause legal proceedings to be begun to try out the issue — 'but only “if such debt is not already in suit.” The premise is simply that there should be an impartial determination of the disputed debt. But that is exactly what is happening in Dale Ingram, Ine., as well as in the present case. In both instances, the controversial debt is “already in suit” in the sense that the Board of Contract Appeals (and perhaps ultimately a court) will decide whether the money is properly owing by the contractor. There is thus bound to be an impartial determination, and the process of securing it had already been started before this action was begun. Cf. Eastport S.S. v. United States, 131 Ct. Cl. 210, 214, 130 F. Supp. 333, 335 (1955).

Plaintiff also contends that Dale Ingram, Inc. is contrary to the rationale of Eastport S.S. v. United States, supra, 131 Ct. Cl. at 213-14, 130 F. Supp. at 335, and id., 135 Ct. Cl. 175, 140 F. Supp. 773 (1956). We perceive no inconsistency. East-port Steamship I involved a disputed debt set off by the Comptroller General against a prior judgment obtained by the steamship company against the United States; instead of waiting for the Comptroller General to cause a suit to be instituted, the plaintiff brought suit here for the portion of the prior judgment which had not been paid. The court held that 31 U.S.C. § 227, supra, did not prevent the claimant from taking the initiative by itself instituting the first action. Eastport Steamship II carried out that reasoning to allow [56]*56interest if the withholding turned out to be improper. Nothing in either opinion suggests, even remotely, that the procedure under §227, after judgment is entered, is the only right of set-off ever possessed by the Government. Nor do the opinions imply that, where, as here, a proceeding to resolve the dispute is already in existence, the claimant has a right to commence a second, independent proceeding.

We shall therefore follow Bale Ingram, Inc. in granting judgment for the amount withheld under Contract 0424, subject to the Government’s right of set-off. At the oral argument we were informed, and both parties agreed, that in August 1973 the contracting officer revised his determinations to find that the plaintiff is due $31,275.67 under Contract 0424 and that the defendant’s claims under Contracts 0401 and 0430 are reduced to $15,973.60. This leaves a balance of $15,302.07 admittedly due plaintiff, without dispute. We see no reason why this sum should not be paid promptly to plaintiff once its tax problems are finally disposed of.2 The remaining amount represents the alleged debt, still in controversy, which is now before the Board of Contract Appeals for determination. Disposition of that portion of the amount in suit will have to await the final outcome of those administrative proceedings and of any court review which may follow.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

NCLN20, Inc. v. United States
99 Fed. Cl. 734 (Federal Claims, 2011)
Telex Communications, Inc. v. United States
42 Cont. Cas. Fed. 77,281 (Federal Claims, 1998)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Gardner Zemke Co. v. Dunham Bush, Inc.
850 P.2d 319 (New Mexico Supreme Court, 1993)
P & D Contractors, Inc. v. United States
37 Cont. Cas. Fed. 76,263 (Court of Claims, 1992)
Placeway Construction Corp. v. United States
35 Cont. Cas. Fed. 75,709 (Court of Claims, 1989)
Cord Moving & Storage Co. v. United States
35 Cont. Cas. Fed. 75,699 (Court of Claims, 1989)
Swager Tower Corp. v. United States
34 Cont. Cas. Fed. 75,320 (Court of Claims, 1987)
Tatelbaum ex rel. Creditors of A. Hoen & Co. v. United States
33 Cont. Cas. Fed. 74,502 (Court of Claims, 1986)
Cascade Pacific International v. The United States
773 F.2d 287 (Federal Circuit, 1985)
Mazama Timber Products, Inc. v. United States
32 Cont. Cas. Fed. 72,759 (Court of Claims, 1984)
Grad Partnership v. United States
31 Cont. Cas. Fed. 72,051 (Court of Claims, 1984)
District of Columbia v. Aetna Insurance
31 Cont. Cas. Fed. 71,231 (District of Columbia Court of Appeals, 1983)
Centron Corp. v. United States
585 F.2d 982 (Court of Claims, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
486 F.2d 1375, 203 Ct. Cl. 52, 1973 U.S. Ct. Cl. LEXIS 152, Counsel Stack Legal Research, https://law.counselstack.com/opinion/project-map-inc-v-united-states-cc-1973.