P & D Contractors, Inc. v. United States

37 Cont. Cas. Fed. 76,263, 25 Cl. Ct. 237, 1992 U.S. Claims LEXIS 73, 1992 WL 32704
CourtUnited States Court of Claims
DecidedFebruary 24, 1992
DocketNo. 90-798C
StatusPublished
Cited by7 cases

This text of 37 Cont. Cas. Fed. 76,263 (P & D Contractors, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
P & D Contractors, Inc. v. United States, 37 Cont. Cas. Fed. 76,263, 25 Cl. Ct. 237, 1992 U.S. Claims LEXIS 73, 1992 WL 32704 (cc 1992).

Opinion

ORDER

MOODY R. TIDWELL, III, Judge:

This case is before the court on the parties’ cross-motions for summary judgment on plaintiff’s claim for the balance of the contract price under a firm-fixed price construction contract. For the reasons set forth below, the court grants defendant’s cross-motion for summary judgment and denies plaintiff’s cross-motion.

FACTS

On July 13,1988, P & D Contractors, Inc. entered into a firm-fixed price construction contract with the Department of the Navy for “Additions to Enlisted Club, Building 112, Naval Air Station, South Weymouth, Massachusetts.” The contract required P & D to remove an existing outdoor dining area, located adjacent to the Enlisted Men’s club at the South Weymouth Naval Air Station, and to replace it with a recreation room and necessary electric, heating, and cooling components. The contract price was $140,998, and the date of completion was set for March 27, 1989. P & D did not complete work until September 13, 1989, 170 days after the contract completion date.

The contract provided for liquidated damages, as follows in pertinent part:

Liquidated Damages: If the Contractor fails to complete the work within the time specified in the contract, or any extension, the contractor shall pay to the Government as liquidated damages, the sum of $100 for each day of delay.

Specifications, sec. 01010, page 01010-3, par. 5. Defendant calculated 170 days of delay, and withheld $17,000 in liquidated damages. Defendant also withheld $5,000 from P & D for its failure to provide the defendant with the following: (1) payroll data for a subcontractor, American Heating; (2) operation and maintenance (O & M) manuals for the mechanical heating and cooling (HVAC) system; and (3) testing of the HVAC system and testing and balancing (T & B) reports for the HVAC system. All of the preceding were required [239]*239under the contract.1 Defendant based the withholding on paragraph 32 of the contract’s general provisions and Section 01011, paragraph 9(b) of the contract. Paragraph 32 of the general provisions stated in pertinent part:

(c) ... When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for the protection of the Government and shall release to the Contractor all the remaining amount.

Section 01011, paragraph 9(b) of the specifications provided:

The obligation of the Government to make any of the payments required under ... this contract shall, in the discretion of the OICC [officer in charge of construction], be subject to: (1) reasonable deductions on account of defects ..., and (2) any claims which the Government may have against the Contractor under or in connection with this contract.

On April 19, 1990, P & D submitted a claim to the contracting officer, pursuant to the Contract Disputes Act (CDA) of 1978, 41 U.S.C. § 601, et seq. P & D sought to recover the $17,000 withheld as liquidated damages for the 170-day delay, and the $5,000 withheld by the Navy for the missing manuals, tests, reports and payrolls. The contracting officer issued a final decision denying P & D’s claim on August 22, 1990.

In its motion before this court, P & D did not deny that it executed a contract which expressly provided for liquidated damages or the Navy’s concomitant right to withhold payment from P & D. Nor did P & D dispute that construction was not completed until 170 days after the contract deadline. P & D’s arguments focused on the validity of the liquidated damages clause and the reasonableness of the damages assessed under the liquidated damages and withholding clauses. As these are contentions of law, and there are no genuine issues of material fact, the court agrees with the parities that the case is ripe for disposition by summary judgment.

DISCUSSION

Summary judgment is appropriate when there is “no genuine issue as to any material fact” so that the moving party “is entitled to judgment as a matter of law.” RUSCC 56(c) (1991). A genuine issue of material fact is one that would change the outcome of the litigation. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247-48, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986); Chevron U.S.A., et al. v. United States, 17 Cl.Ct. 537, 540 (1989), rev’d on other grounds, 923 F.2d 830 (Fed.Cir.1991). In order to show that a material fact is genuinely at issue, the non-movant must do more than present “some” evidence on the disputed issue. Liberty Lobby, Inc., 477 U.S. at 248-50, 106 S.Ct. at 2510-11. As the Supreme Court stated, “[T]here is no issue for trial unless there is sufficient evidence favoring the non-moving party for a [court] to return a verdict for that party. If the evidence [of the non-movant] is merely colorable, or is not significantly probative, summary judgment may be granted.” Id. at 249-50, 106 S.Ct. at 2511 (citations omitted); See also Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 1356, 89 L.Ed.2d 538 (1986), which held that “[w]here the record taken as a whole could not lead a rational trier of fact to find for the non-moving party, there is no ‘genuine issue for trial.’ ” P & D must do more than merely raise some doubt as to the existence of a fact; it must furnish some credible evidence suffi[240]*240dent to require trial on the merits. Avia Group Int’l, Inc. v. L.A. Gear California, Inc., 853 F.2d 1557, 1560 (Fed.Cir.1988).

I. The Liquidated Damages Claim

P & D argued that the liquidated damages provision was unenforceable because it was not based on a reasonable estimate of the type of damages defendant might suffer from late completion of the project. In response, defendant maintained that the liquidated damages were reasonable because they were based on figures from Navy Contracting Manual NAVFAC P-68, recently held by this court to provide a reasonable basis for fixing liquidated damages in government contracts. Fred A. Arnold, Inc. v. United States, 18 Cl.Ct. 1 (1989).

Liquidated damages clauses are valid when they serve as “fair and reasonable attempts to fix just compensation for anticipated loss caused by breach of contract,” and not merely as an “added spur to performance.” Priebe & Sons, Inc. v. United States, 332 U.S. 407, 413, 68 S.Ct. 123, 126-27, 92 L.Ed. 32 (1947). P & D argued that Arnold addressed liquidated damages in a contract for the construction of military housing and the circumstances here, for an addition to an enlisted men’s club, were different enough to warrant lesser liquidated damages. P & D argued that the Arnold

Free access — add to your briefcase to read the full text and ask questions with AI

Related

K-Con Building Systems, Inc. v. United States
107 Fed. Cl. 571 (Federal Claims, 2012)
M. Maropakis Carpentry, Inc. v. United States
84 Fed. Cl. 182 (Federal Claims, 2008)
Safeco Credit & Fraley Associates, Inc. v. United States
44 Fed. Cl. 406 (Federal Claims, 1999)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Harris v. Office of Personnel Management
985 F.2d 549 (Federal Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,263, 25 Cl. Ct. 237, 1992 U.S. Claims LEXIS 73, 1992 WL 32704, Counsel Stack Legal Research, https://law.counselstack.com/opinion/p-d-contractors-inc-v-united-states-cc-1992.