Fred A. Arnold, Inc. v. United States

35 Cont. Cas. Fed. 75,707, 18 Cl. Ct. 1, 1989 U.S. Claims LEXIS 165, 1989 WL 91827
CourtUnited States Court of Claims
DecidedAugust 15, 1989
DocketNo. 578-86 C
StatusPublished
Cited by5 cases

This text of 35 Cont. Cas. Fed. 75,707 (Fred A. Arnold, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fred A. Arnold, Inc. v. United States, 35 Cont. Cas. Fed. 75,707, 18 Cl. Ct. 1, 1989 U.S. Claims LEXIS 165, 1989 WL 91827 (cc 1989).

Opinion

OPINION

WIESE, Judge.

I

At issue in this case is the finality, under Wunderlich Act standards, 41 U.S.C. §§ 321-322 (1982), of a decision of the Armed Services Board of Contract Appeals denying claims of both contracting parties: Arnold’s demand for equitable adjustments in contract price and time based on various claims of Government-caused delay, disruption, and extra work, and the Government’s demand for liquidated damages based on a 13-month delay in the completion of construction.1

[3]*3On the basis of the parties’ briefs and the oral argument, the court concludes that, with respect to the contractor’s claims, the Board’s decision is neither erroneous in fact nor law and hence is entitled to finality. However, as to the Government’s claim, the court concludes that the , denial of liquidated damages was incorrect as a matter of law; hence we reverse.

II

The contract claims in question grew out of the performance of a competitively-bid construction contract which the United States Navy awarded to Fred A. Arnold, Inc., a small business building company, on May 21, 1975. The contract called for construction of a three-story, 300 foot-long reinforced concrete bachelor enlisted quarters (“BEQ”) at Camp Pendleton, California. The contract price was $1.9 million. Work was to begin on June 17, 1975 and the completion date, as adjusted during performance of the work, was set for October 18, 1976. Though construction was timely accomplished, the building’s balconies required substantial structural modification (liability for which is one of the issues raised here) that delayed the Government’s use and occupancy of the building for approximately 13 months beyond the planned finish date.

In the course of the work various claims arose which, despite efforts to resolve them at the contracting officer level, eventually came before the Board for resolution. Following three weeks of trial, the Board issued a comprehensive decision rejecting virtually all of the contractor’s claims (there were 10 claims consolidated under 8 appeal dockets). Also denied by the Board was a Government demand for liquidated damages. Upon rejection of its claims, the contractor brought suit in this court to reverse the Board’s decision. The appeal covers all of the claims originally raised before the Board except the “Hollow Metal Doors and Window Frames” claim. The Government, in turn, has filed a counterclaim reasserting its demand for liquidated damages.

Ill

Before turning to the specific claims in issue, we deal first with a contention which the contractor raises concerning a claimed lack of impartiality on the part of the Board member to whom the trial and decision of this case had been assigned. The contention is that immediately prior to assuming his judicial duties with the Board, the member in question had served as assistant general counsel in the same Navy office charged with the responsibility of defending the Government’s interests in this litigation before the Board. It is claimed that the first of the contractor’s claims (the “Catch Basins” claim) arose during the Board member’s tenure as assistant general counsel and that “more than eight months before [the board member] left the Navy General Counsel’s office, either he or persons working with him or under his supervision were actively involved in resisting the Plaintiff’s claims which were already before the ASBCA____” Based on these allegations of conflict of interest and the infraction of ethical standards they point to, it is urged that we proceed in our review of the Board’s decision uninhibited by the deference otherwise due administrative factual determinations under the Wunderlich Act, 41 U.S.C. § 321.

Despite their seeming seriousness, we give these contentions short shrift. There is absolutely no proof of the contractor’s contentions—they are no more than rash speculation. Nor are we given any explanation as to why these contentions were not raised in the proceedings below, as well they might have been. It is no answer to say that the bias was not confirmed until the decision was issued. This was, after all, a panel decision; hence the interests of the concurring Board members in the integrity of their action would certainly have [4]*4counseled a request for reconsideration before bringing the matter to this court’s attention. Finally, and most importantly, based on our review of the conduct of the trial proceedings, and the substantiality of the evidence on which the Board based its findings, we can discern no ground for saying that the decision in question was the product of other than careful judgment, fairly and honestly applied.

This, then, is not a case where the evidence suggests that the Board member had “the kind and degree of personal involvement in the case and hostility to the plaintiff that would warrant disqualification of a judge for bias and prejudice.” Gulf & Western Industries, Inc. v. United States, 230 Ct.Cl. 1, 7, 671 F.2d 1322, 1326 (1982). Accordingly, the case presents no occasion for departing from the substantial evidence standard in the evaluation of the Board’s factual determinations. That standard directs a reviewing court to accept as final factual determinations drawn from “such relevant evidence as a reasonable mind might accept as adequate to support a conclusion.” Consolidated Edison Company v. National Labor Relations Board, 305 U.S. 197, 229, 59 S.Ct. 206, 217, 83 L.Ed. 126 (1938). We proceed on that basis.

Global Settlement Claim

On December 7, 1976, (a date by which all construction except balcony repair had been completed), plaintiff’s president met with the contracting officer to discuss the contractor’s pending claims. Both parties were represented by counsel. After unsuccessfully attempting to resolve each claim separately, the parties agreed to a “bottom line” settlement of all but four of the contractor’s claims. By the terms of this “global” settlement, the Government agreed to pay the contractor an additional $30,000 and to extend the contract completion date by 22 days (from September 26, 1976 to October 18, 1976) in exchange for the release of all of the contractor’s claims, except those relating to the catch basins, the pilings, the balcony correction, and the door and window frames. The Government also promised to provide security for the construction site; to relieve the contractor from having to provide a construction quality control (CQC) representative during the balcony corrective work; to release all previously withheld liquidated damages; and to suspend any further withholding of liquidated damages pending completion of the balcony corrective work and a determination of liability for that work.

As a follow-up to the December 7 meeting, the parties’ attorneys met again on December 9 to draft a contract modification formalizing the terms of the settlement previously agreed to. Thereafter, by letter to the Government dated December 16, 1976, the contractor’s attorney confirmed the contractor’s understanding and acceptance of the global settlement. In turn, the Government forwarded a signed modification to the contractor, Modification No.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M. Maropakis Carpentry, Inc. v. United States
84 Fed. Cl. 182 (Federal Claims, 2008)
Precision Pine & Timber, Inc. v. United States
75 Fed. Cl. 80 (Federal Claims, 2006)
Thomas Creek Lumber & Log Co. v. United States
41 Cont. Cas. Fed. 76,971 (Federal Claims, 1996)
P & D Contractors, Inc. v. United States
37 Cont. Cas. Fed. 76,263 (Court of Claims, 1992)
Fred A. Arnold, Inc. v. United States
37 Cont. Cas. Fed. 76,146 (Court of Claims, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,707, 18 Cl. Ct. 1, 1989 U.S. Claims LEXIS 165, 1989 WL 91827, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fred-a-arnold-inc-v-united-states-cc-1989.