Fred A. Arnold, Inc. v. United States

37 Cont. Cas. Fed. 76,146, 24 Cl. Ct. 6, 1991 U.S. Claims LEXIS 353, 1991 WL 150168
Procedural entryThis page is a short order in Fred A. Arnold, Inc. v. United States. Read the opinion of the Court — 35 Cont. Cas. Fed. 75,707
United States Court of Claims·Decided August 6, 1991·No. No. 578-86 C·Published

Opinion

OPINION

WIESE, Judge.

I

In an earlier opinion in this case, this court examined the correctness, under the standards of review prescribed by the Wunderlich Act, 41 U.S.C. §§ 321-322 (1988), of a decision of the Armed Services Board of Contract Appeals. The decision in question had denied substantially all of the contractor’s (plaintiff’s) claims for equitable adjustments in contract price and time as well as the Government’s claim for liquidated damages. We affirmed the board’s denial of the contractor’s claims and reversed its denial of the Government’s claim. Fred A. Arnold, Inc. v. United States, 18 Cl.Ct. 1 (1989), aff'd in part and rev’d in part, 86-1 B.C.A. (CCH) 1118,701. The case was then returned to the board for a determination of the amount due the Government on its counterclaim.

The board’s task, however, has not yet been accomplished. It appears that the board read the court's remand order more narrowly than was intended and therefore confined the decision on quantum to the two remaining claims (both minor in amount) that had not been quantified in its earlier decision. The larger issue—the netting of accounts and ascertainment of the amount ultimately due the Government on its claim for liquidated damages—was left unaddressed. (The board’s decision on quantum was issued as an unpublished opinion on November 15, 1990).

It is in this incomplete state of resolution that the case is once again brought here by plaintiff. Aided now by new counsel, plaintiff asks that we reconsider that part of our earlier decision reversing the board’s disallowance of the Government’s claim for liquidated damages. Specifically, plaintiff contends that the liquidated damages issue (introduced in these proceedings by way of a Government counterclaim) involves ques: tions independent of those presented in the claims appealed by the contractor. Therefore, the argument continues, under the rule established by S & E Contractors, Inc. v. United States, 406 U.S. 1, 92 S.Ct. 1411, 31 L.Ed.2d 658 (1972), the Government’s counterclaim represents an impermissible enlargement of the scope of the contractor’s suit. Accordingly, plaintiff asks us to dismiss the Government’s counterclaim for lack of a contractual right to contest the board’s decision. The Government opposes plaintiff’s motion and urges that we dismiss the motion, either for lack of timeliness or for lack of merit. In addition, the Government, by separate motion, asks that we enter judgment in its favor for the amount claimed due on its counterclaim.

The issues have been briefed by the parties and oral argument was heard on July 23, 1991. At the conclusion of the argument, the court announced its decision in defendant’s favor. We restate here the reasons for that decision.

II

In S & E Contractors, Inc. v. United States, 406 U.S. 1, 92 S.Ct. 1411, 31 L.Ed.2d 658 (1972), the Supreme Court ruled that the Government could not appeal a decision on a “disputes clause” claim that had been resolved by a contract appeals board (or other final deciding authority) in a contractor’s favor. Both the language of the disputes clause and settled administrative practice were held to render such board decisions final and binding on the Government, absent the contractor’s fraud [8] or overreaching. 406 U.S. at 9-10, 20, 92 S.Ct. at 1416-17, 1422.

Subsequently, in Roscoe-Ajax Constr. Co. v. United States, 204 Ct.Cl. 726, 499 F.2d 639 (1974), a case involving a contractor’s request for judicial review of part of a contract board decision, the Court of Claims decided that the rationale of S & E Contractors, Inc. barred the Government from challenging any aspect of a contract board’s decision that fell outside the scope of the contractor’s own appeal. The essence of S&E, explained the court, lay in its emphasis upon the finality accorded to a settled contract "dispute." Hence, an appeal by the Government would lie only where it concerned the same dispute that formed the basis of the contractor’s appeal.

The concept of the “ ‘same dispute’ as distinguished from a ‘separate dispute,”’ the court went on to explain, “encompasses, in general, those aspects of a controversy which are so related to one another that they form parts of a whole and ought to be decided together.” 204 Ct.Cl. at 742, 499 F.2d at 646. The contractor in Roscoe-Ajax was challenging only the board’s overall method of calculating the amount due for a series of change orders and not the root issue of entitlement or even the amount due for any single change order. Therefore, the Government could not contest the quantum of the equitable adjustments which the board had allowed for the individual changes. As the court saw it, the claim and counterclaim were not so connected as to constitute elements of the same dispute; they did not share the same facts or implicate the same legal rules and principles. “The only controversy plaintiff stirs here is an isolated and separable dispute, involving computation and the total-ling of the individual sums, and only as to that separate question can the Government present its own counter-demand.” 204 Ct. Cl. at 747, 499 F.2d at 649.

Plaintiff contends that the analysis which shaped the result in Roscoe-Ajax is equally applicable to this case. The argument is that the Government’s entitlement to liquidated damages rests on facts and legal principles distinct from those governing the merits of the appeals presented by the contractor. Therefore, plaintiff asserts that the Government’s counterclaim constitutes a separate dispute which may not be reexamined here. As indicated, the Government sees this argument as being both untimely and without merit. We agree on both counts.

Free access — add to your briefcase to read the full text and ask questions with AI

Fred A. Arnold, Inc. v. United States, 37 Cont. Cas. Fed. 76,146, 24 Cl. Ct. 6, 1991 U.S. Claims LEXIS 353, 1991 WL 150168 (cc 1991).

37 Cont. Cas. Fed. 76,146 (Fred A. Arnold, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

New Colonial Ice Co. v. Helvering
292 U.S. 435 (Supreme Court, 1934)
S&E Contractors, Inc. v. United States
406 U.S. 1 (Supreme Court, 1972)
Janet L. Wallace v. Department of the Air Force
879 F.2d 829 (Federal Circuit, 1989)
Fred A. Arnold, Inc. v. United States
35 Cont. Cas. Fed. 75,707 (Court of Claims, 1989)
Stein Bros. Mfg. Co. v. United States
337 F.2d 861 (Court of Claims, 1963)
Keco Industries, Inc.
199 Ct. Cl. 1020 (Court of Claims, 1972)
Roscoe-Ajax Construction Co. v. United States
499 F.2d 639 (Court of Claims, 1974)
Northland Camps, Inc. v. United States
499 F.2d 658 (Court of Claims, 1974)
Hunt v. Jaglowski
926 F.2d 689 (Seventh Circuit, 1991)