Safeco Credit & Fraley Associates, Inc. v. United States

44 Fed. Cl. 406, 1999 U.S. Claims LEXIS 178, 1999 WL 545257
CourtUnited States Court of Federal Claims
DecidedJuly 27, 1999
DocketNo. 93-314 C
StatusPublished
Cited by17 cases

This text of 44 Fed. Cl. 406 (Safeco Credit & Fraley Associates, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Safeco Credit & Fraley Associates, Inc. v. United States, 44 Fed. Cl. 406, 1999 U.S. Claims LEXIS 178, 1999 WL 545257 (uscfc 1999).

Opinion

OPINION AND ORDER

HEWITT, Judge.

This dispute arises out of a 1985 contract for berthing improvements to a naval dock at the Mayport, Florida Naval Station.1 The case is before the court on the parties’2 motions for summary judgment and their respective oppositions thereto.

The dispute focuses on two issues. The first issue involves a liquidated- damages provision in the contract. Safeco contends that the provisions governing the rate and the calculation of damages, if enforced according to the government’s interpretation, would be illegal as a penalty. The second issue is whether or not home office overhead expenses were owed to plaintiff on account of delays and extensions of the project. Safeco contends that it has met the requirements to recover damages under the Eichleay formula. Safeco has moved and the government has cross-moved for summary judgment on both issues. After considering the submissions of both parties, the terms of the contract, and applicable law, the court finds that the government is entitled to summary judgment on both issues.

I. Background

The facts upon which the court relies are based on plaintiffs and defendant’s proposed [409]*409findings of uncontroverted facts, each viewed in the light of the allegations made in the other party’s statement of genuine issues. See Rules of the Court of Federal Claims (“RCFC”), Rule 56(d). In accordance with the standard of review articulated below and, after an examination of the submissions of the parties in this case, as well as the parties’ oral arguments, the court finds there are no material facts in dispute.3

The contract was divided into seven construction phases identified as 1A, IB, 2A, 2B, 3A, 3B, and 3C, and a mobilization phase. The mobilization phase and construction phases 1A, IB, 2A, and 2B ran consecutively. With the exception of phase IB, which was to begin before the completion of phase 1A, each of phases 1A, IB, 2A, and 2B had to be completed before work on the next phase could commence. Phases 3A, 3B and 3C ran consecutively to each other, but phase 3A began concurrently with phase 1A. Mobilization activities included preparations for construction including “[fjield verifications, contract submittals, ordering] equipment and materials, [and] stockpiling] equipment and materials ____” Defendant’s Appendix, Vol. I at 13. Each construction phase was for construction on one berth. Id. at 13-14.

The Navy added or changed work on the project by 53 modifications to the contract. Many of the modifications extended the time period for completion of phases 1A, IB, 2A, and 2B — those phases of the project which (with the exception of phase IB, which was to begin before the completion of phase 1A) were to run consecutively. The parties disagree about the effect of these modifications on the contract completion dates and, in turn, on Safeco’s possible liability for failure to complete the project on time. The government calculated damages based on the dates of completion set forth in the contract and the modifications.4 If a phase of the project was not completed by the date in the contract, the government assessed liquidated damages for each day of delay beyond the contract completion date for that phase of the project. Plaintiff subtracted the number of days it took to complete a particular phase from the number of days allotted under the contract and the modifications, without regard to completion dates, in arriving at the amount it claims should have been assessed.5 [410]*410Plaintiff refers only to the number of days by which the contract was extended in each modification, without reference to the actual changed completion date.6 It interpreted the modifications to extend both the project completion and subsequent commencement dates. If a phase of the project was extended, in plaintiffs view, that extension altered the commencement date for the subsequent phase so that it would begin after the completion date of the previous phase. Plaintiffs Response at 17.

By focusing on the number of days it took plaintiff to complete a particular phase of the project, without reference to the actual completion dates, plaintiff asserts that damages should have been assessed for 66 days for phase IB, 0 days for phase 2A, and 148 days for phase 2B. Plaintiffs Response at 7.

Defendant calculated damages by reference to the commencement and completion dates of each phase. Where more than one phase was late, defendant assessed damages concurrently. Moreover, with the exception of modification nos. P00014, P00023, P00027, P00052, and P000537, all of the modifications contained accord and satisfaction language which purported to release the Navy from liability on any related claims for equitable adjustment. The government believes that these provisions provide a complet.e defense to claims arising under most of the modifications. Defendant’s Motion at 17.

The Navy Construction Manual (1985) (“NAVFAC P-68”) § 4-212 directs the inclusion of liquidated damages clauses in construction contracts. The government asserts that the damage provisions in the contract for this project contained a rate that was based upon the standard rate for a project of comparable cost plus an upward adjustment based upon the anticipated damages which would be incurred by the Navy in the event of a delay. Safeco asserts that “[t]he upward adjustment was an arbitrary increase lacking any proper justification.”8

Plaintiff is seeking payment of monies plaintiff believes it is owed under the contract. For phase IB, the government assessed liquidated damages for 65 days at a rate of $675 per day for a total of $43,875. Safeco asserts that the government should have assessed damages for 66 days at $450 per day for a total of $29,700 and seeks an adjustment of $14,175 from the government for phase IB. For phase 2A the government assessed liquidated damages for 48 days for a total of $32,400. Safeco asserts that the government should not have assessed any damages for phase 2A because the number of original contract days plus time added by the modifications to complete phase 2A was 277 [411]*411days while plaintiff completed phase 2A in 258 days. Finally, the government assessed damages for phase 2B for 197 days at $1,050 per day for a total of $144,795. During phase 2B the government had taken partial possession and therefore reduced the damage rate by one-half to $735 per day during the period of time of possession.9 Plaintiff believes it is entitled to a reimbursement of $75,679 for phase 2B. Plaintiff contends that damages for phase 2B should only have been assessed for 148 days at $467 per day. Again, the discrepancy between the view of the government and the plaintiff stems from their differing views as to whether the modifications affected the dates by which — or the number of days within which — performance was to be completed.

In addition to a refund of liquidated damages which Safeco believes was improperly assessed, Safeco asserts an entitlement to home office overhead expenses. The government claims that it paid Safeco $308,028 for extended home office overhead. However, plaintiff asserts that only $15,258.23 was reimbursed, and that the difference lies in the government’s erroneous characterization of “indirect cost reimbursement” as equivalent to home office overhead.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pontchartrain Partners, LLC
Armed Services Board of Contract Appeals, 2025
KUNJ Construction Corporation
Armed Services Board of Contract Appeals, 2024
Laboratory Corp. of America v. United States
108 Fed. Cl. 549 (Federal Claims, 2013)
M. Maropakis Carpentry, Inc. v. United States
84 Fed. Cl. 182 (Federal Claims, 2008)
Jaynes v. United States
75 Fed. Cl. 218 (Federal Claims, 2007)
Ahrens v. United States
62 Fed. Cl. 664 (Federal Claims, 2004)
Cuyahoga Metropolitan Housing Authority v. United States
57 Fed. Cl. 751 (Federal Claims, 2003)
Bechtel National, Inc. v. Roche
65 F. App'x 277 (Federal Circuit, 2003)
Ryco Construction, Inc. v. United States
55 Fed. Cl. 184 (Federal Claims, 2002)
Smelser v. United States
53 Fed. Cl. 530 (Federal Claims, 2002)
Kanag'Iq Construction Co. v. United States
51 Fed. Cl. 38 (Federal Claims, 2001)
R.P. Richards Construction Co. v. United States
51 Fed. Cl. 116 (Federal Claims, 2001)
O'Connor v. United States
50 Fed. Cl. 285 (Federal Claims, 2001)
National Steel & Shipbuilding Co. v. United States
49 Fed. Cl. 579 (Federal Claims, 2001)
Starflight Boats v. United States
48 Fed. Cl. 592 (Federal Claims, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
44 Fed. Cl. 406, 1999 U.S. Claims LEXIS 178, 1999 WL 545257, Counsel Stack Legal Research, https://law.counselstack.com/opinion/safeco-credit-fraley-associates-inc-v-united-states-uscfc-1999.