Tatelbaum ex rel. Creditors of A. Hoen & Co. v. United States

33 Cont. Cas. Fed. 74,502, 10 Cl. Ct. 207, 1986 U.S. Claims LEXIS 841
CourtUnited States Court of Claims
DecidedJuly 10, 1986
DocketNo. 29-85C
StatusPublished
Cited by8 cases

This text of 33 Cont. Cas. Fed. 74,502 (Tatelbaum ex rel. Creditors of A. Hoen & Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Tatelbaum ex rel. Creditors of A. Hoen & Co. v. United States, 33 Cont. Cas. Fed. 74,502, 10 Cl. Ct. 207, 1986 U.S. Claims LEXIS 841 (cc 1986).

Opinion

OPINION

YOCK, Judge.

This contract case involves an appeal from a decision of the Government Printing Office (“GPO”), Board of Contract Appeals (hereinafter the Board)1 sustaining the Government Printing Office’s setoff of amounts owed by the insolvent contractor to GPO on two defaulted contracts against amounts which GPO owed the debtor on two unrelated contracts. On cross-motions for summary judgment, the parties seek review of the Board’s decision in accordance with the standards of the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1982).

For reasons outlined herein, the Board’s decision is affirmed.

Facts

Plaintiff Charles M. Tatelbaum is As-signee for the Benefit of the Creditors of A. Hoen & Company, Inc. (“Hoen”), an insolvent Maryland corporation. The GPO awarded Hoen five contracts during 1979 and 1980, four of which are relevant here. In all of these contracts, GPO reserved the right to assess Hoen for any excess costs of reprocurement in the event of Hoen’s termination for default.

Hoen had completed work on two of the contracts and had partially completed work on the other two when it ceased its business operations on April 10, 1981. Five days later, Hoen executed an assignment for the benefit of its creditors, and on April 16, 1981, the Circuit Court of Baltimore City declared Hoen insolvent and assumed jurisdiction over the Hoen estate, appointing plaintiff Charles M. Tatelbaum and Edward F. Shea, Jr., as assignees.2

In accordance with the Default Clause of each contract, and upon learning that Hoen had ceased business operations, GPO terminated Hoen’s contracts identified as Programs B 312-S, B 321-S, and B 365-M, for default, due to Hoen’s inability to complete performance. GPO notified Hoen of its termination for default by letter dated April 15, 1981. The letter also informed Hoen that, pursuant to contract provision, the company would be responsible for any excess costs that arose due to reprocurement on these contracts because of the default.

[209]*209Of the four contracts at issue, two (B 315-S and B-365-M) had been completed by the termination date and the GPO then owed Hoen some $24,393.31 and $9,637.48, respectively, on the contracts. Of the two partially completed contracts (B 312-S and B 321-S), GPO then owed Hoen some $53,-304.57 and $11,125.09 respectively.

On April 1, 1982, the GPO assessed against Hoen $122,702.38 in excess repro-curement costs relating to contracts B 312-S and B 321-S. The GPO assessed $77,061.86 in reprocurement costs against the B 312-S contract, and $45,640.52 against the B 321-S contract. GPO did not assess any reprocurement costs against contract B 365-M. Hoen was advised that GPO was setting off these costs against $98,460.45 due and owing Hoen for performance under all four contracts.

Plaintiff sought review of the setoff with the contracting officer, which was denied on September 20, 1982. Subsequently, the plaintiff appealed the contracting officer’s decision to the GPO Board of Contract Appeals, arguing that the GPO could not set off against monies due and owing Hoen under Programs B 315-S and B 365-M debts arising from Programs B 312-S and B 321-S. Plaintiff conceded that GPO could recoup reprocurement costs of each defaulted contract from amounts that the company was owed on each defaulted contract, but argued that it was improper for GPO to extend this setoff right to separate, completed contracts that were not in default. Plaintiff claimed it was owed $34,-030.79 under Programs B 315-S and B 365-M, the two contracts that had been completed and that were not in default.

Plaintiff’s complaint, filed February 14, 1985, seeks this Court’s review of the October 21, 1983, decision of the Board which denied plaintiff’s claim. Plaintiff initially sought to obtain review of the Board’s decision before the United States Court of Appeals for the Federal Circuit. By decision dated December 11, 1984, Tatelbaum v. United States, 749 F.2d 729 (Fed.Cir. 1984), the United States Court of Appeals for the Federal Circuit ruled that, since the GPO was not part of the Executive Branch, the Contract Disputes Act of 1978, 41 U.S.C. § 601 et seq. (1982), did not apply to decisions by the GPO Board of Contract Appeals, and that the court of appeals, therefore, lacked jurisdiction over Mr. Ta-telbaum’s attempted appeal. The case was ordered transferred to this Court. Mr. Ta-telbaum’s complaint invokes the jurisdiction of this Court pursuant to 28 U.S.C. § 1491 and the Wunderlich Act, 41 U.S.C. §§ 321-22. Both parties have filed motions for summary judgment.

Discussion

It is the duty of this Court, in reviewing a decision under the standards of the Wun-derlich Act, to determine whether the Board’s findings of fact and conclusions of law are supported by substantial evidence and are correct as a matter of law. Dravo Corp. v. United States, 219 Ct.Cl. 416, 423, 594 F.2d 842, 845 (1979); Entwistle Co. v. United States, 6 Cl.Ct. 281, 286 (1984).

Before responding to the plaintiff’s contentions, it is important to point out that judicial review of administrative factual determinations under Wunderlich standards is narrow and limited. Roflan Co. v. United States, 7 Cl.Ct. 242, 248 (1985); Iconco v. United States, 6 Cl.Ct. 149, 151 (1984), aff'd mem., 770 F.2d 179 (Fed.Cir.1985); Koppers Co. v. United States, 186 Ct.Cl. 142, 148, 405 F.2d 554, 557 (1968). The Board’s findings of fact are presumptively correct. Arundel Corp. v. United States, 207 Ct.Cl. 84, 99, 515 F.2d 1116, 1124 (1975). Plaintiff carries a heavy burden in seeking to set aside factual determinations made by a Board. Donald M. Drake Co. v. United States, 194 Ct.Cl. 549, 553, 439 F.2d 169, 171 (1971). Questions of law decided by the Board, on the other hand, are not binding on this Court nor entitled to finality. Astro-Space Laboratories, Inc. v. United States, 200 Ct.Cl. 282, 293, 470 F.2d 1003, 1008-09 (1972).

The plaintiff argues that the decision of the GPO Board of Contract Appeals is wrong as a matter of law. Specifically, the plaintiff states the issue in the case to be [210]*210whether the United States may recover re-procurement costs for contracts terminated for default from an insolvent contractor by offsetting those reprocurement costs from amounts due the contractor under unrelated contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stiles v. United States
47 Fed. Cl. 1 (Federal Claims, 2000)
Amoco Production Co. v. Fry
908 F. Supp. 991 (District of Columbia, 1995)
Dependable Insurance v. United States
34 Cont. Cas. Fed. 75,347 (Court of Claims, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
33 Cont. Cas. Fed. 74,502, 10 Cl. Ct. 207, 1986 U.S. Claims LEXIS 841, Counsel Stack Legal Research, https://law.counselstack.com/opinion/tatelbaum-ex-rel-creditors-of-a-hoen-co-v-united-states-cc-1986.