Donald M. Drake Company v. The United States

439 F.2d 169, 194 Ct. Cl. 549, 1971 U.S. Ct. Cl. LEXIS 116
CourtUnited States Court of Claims
DecidedMarch 19, 1971
Docket90-68
StatusPublished
Cited by10 cases

This text of 439 F.2d 169 (Donald M. Drake Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Donald M. Drake Company v. The United States, 439 F.2d 169, 194 Ct. Cl. 549, 1971 U.S. Ct. Cl. LEXIS 116 (cc 1971).

Opinion

ON PLAINTIFF’S MOTION AND DEFENDANT’S. CROSS-MOTION FOR SUMMARY JUDGMENT

PER CURIAM:

This case was referred to Trial Commissioner David Schwartz with directions to prepare and file his opinion on the issues of plaintiff’s motion and defendant’s cross-motion for summary judgment under the order of reference and Rule 166(c). The commissioner has done so in an opinion and report filed on November 20, 1970, wherein such facts as are necessary to the opinion are set forth. Plaintiff filed a request for review by the court of the commissioner’s recommendation for dismissal and the case has been submitted to the court on oral argument of counsel and the prior briefs and papers of the parties before the commissioner.

With respect to claim for the stop order in the area of spillage from above, the court points out that, under the sustainable findings of the Corps of Engineers Board of Contract Appeals, it was practically certain at the time of the bid that plaintiff would encounter such spillage, and plaintiff should have known this. The court does not have before it in this case any issue as to the application of the Suspension of Work clause where the contractor merely knows or should know, at the time the contract is made, that a suspension may possibly occur, or may not.

Since the court agrees with the opinion and recommended conclusion of the trial commissioner, as hereinafter set forth, it hereby adopts the same, together with the foregoing paragraph, as the basis for its judgment in this case. Therefore, plaintiff is not entitled to recover. Plaintiff’s motion for summary judgment is denied, defendant’s cross-motion is granted and plaintiff’s petition is dismissed.

OPINION OF COMMISSIONER

SCHWARTZ, Commissioner:

Plaintiff’s claim arises out of a contract dated March 26, 1962 with the *171 Corps of Engineers for the relocation of several miles of railroad line and highway as part of the John Day Dam project on the Columbia River between Washington and Oregon. Claim is made for an equitable adjustment for increased costs allegedly occasioned by government disruption of plaintiff’s work schedule. The claim, made under a standard Disputes clause in the contract, has been denied by the Army Corps of Engineers Board of Contract Appeals, ENG BCA No. 2725, 67-1 BCA |j 6230, on rehearing, 67-2 BCA j[ 6550. In this court plaintiff contends that the Board committed reversible errors in its findings of fact and conclusions of law. The applicable standards for the determination of the issues, presented by cross-motions for summary judgment, are those of the Wunderlich Act. The Board’s findings of fact are final if supported by substantial evidence, and its decisions of questions of law are open to independent judicial consideration. 41 U.S.C. §§ 321, 322 (1964).

The facts applicable to all three claims are few. The lake to be created by the John Day Dam required the relocation of 7 miles of Washington State highway and of the same number of miles of the line of the Spokane, Portland and Seattle Railway Co. The new highway was to be approximately 200 feet north and 50 feet above the relocated railroad line. The relocation was the subject of contracts involving the Corps of Engineers, the Washington State Highway Commission, and the railway company.

In accordance with its contract with the Corps, the Highway Commission on June 19, 1961 awarded a contract for relocation of 3% miles of highway to a firm called Erland & Blickle, herein “Erland.” Work was to be completed within 200 working days, or by approximately April 30, 1962. On March 26, 1962 the Corps of Engineers awarded a contract to plaintiff — the contract under which the dispute arises — for the entire 7 miles of railroad relocation and the western 3% miles of highway relocation. On the same day, plaintiff was given notice to proceed.

Plaintiff complains of three separate work restrictions or stop orders which, it claims, required that it use its equipment in a less efficient manner than contemplated in its approved progress schedule. Additional work by plaintiff, connected with two of the three claims made, has been paid for. The claims now in suit are for delay or “impact” costs.

Relying upon both the Changes and the Suspension of Work clauses in its contract, plaintiff contends that each of the three stop orders constituted a constructive change or a delay or suspension of the work for an unreasonable period, for the convenience of the Government. The Board denied all parts of the claim, holding that none of the delays was unreasonable.

The Board was correct in the decisions of law here brought into question. As to the challenged findings of fact, in seeking to overturn decisions of fact, a plaintiff assumes a heavy burden of showing that there is no evidence of substance to support the Board’s findings and that the evidence of substance compellingly supports a contrary finding. Koppers Co. v. United States, 405 F.2d 554, 558-559, 186 Ct.Cl. 142, 147-151 (1968); Rice v. United States, 428 F.2d 1311, 1314-1315, 192 Ct.Cl. 903, 909 (1970). Plaintiff has failed to meet its burden. The three claims will be discussed separately.

1. The stop order in the area of spillage from above. Erland’s work on the highway, above the railway line which plaintiff was to relocate, required the blasting of rock. Blasted rock and earth were pushed over the side of the road and fell on plaintiff’s work site. On May 25, 1962, therefore, the contracting officer instructed plaintiff not to excavate in the area until a survey was made to determine pay quantities of material to be excavated. Photogrammetric measurements of the area were then made by the Corps, and on their *172 completion on August 22, 1962 plaintiff was permitted to begin work in the spillage area.

Plaintiff contends it did not have and could not reasonably have had notice that there would be such spillage in May from the Erland work as might delay its work. Substantial evidence supports the Board’s conclusion to the contrary.

Work by Erland was in progress during the period of bidding for plaintiff’s contract, January 26, 1962 to March 13, 1962. Franklin Drake, president of plaintiff, visited the site during that time, in February 1962, observed the status of the work going on, and saw that it would involve excavation by drilling and blasting rock. He even saw, in his words, “evidence of a minor amount of spillage of common materials” over the Erland cut.

The Board may have misread the transcript, in its finding that the witness then knew that Erland’s modified completion was mid-May 1962 (and thus had actual notice of the possible effects on plaintiff’s work of Erland’s blasting). The transcript shows only that the witness testified that “I know what it [the modified completion date] is now.” The seeming error does not vitiate the ultimate finding that plaintiff had sufficient notice of possible spillage in May, for complete information was available to plaintiff for the asking or the looking.

Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Utley-James, Inc. v. United States
34 Cont. Cas. Fed. 75,478 (Court of Claims, 1988)
Tatelbaum ex rel. Creditors of A. Hoen & Co. v. United States
33 Cont. Cas. Fed. 74,502 (Court of Claims, 1986)
Sperry Corp. v. United States
33 Cont. Cas. Fed. 74,234 (Court of Claims, 1986)
Johnson Controls, Inc. v. United States
671 F.2d 1312 (Court of Claims, 1982)
Dravo Corp. v. United States
594 F.2d 842 (Court of Claims, 1979)
Wickham Contracting Co. v. United States
546 F.2d 395 (Court of Claims, 1976)
Atlantic Gulf & Pacific Co. of Manila
21 Cont. Cas. Fed. 84,079 (Court of Claims, 1975)
Arundel Corp. v. United States
515 F.2d 1116 (Court of Claims, 1975)
Aerojet-General Corp. v. United States
467 F.2d 1293 (Court of Claims, 1972)
Teitelbaum v. United States
458 F.2d 72 (Court of Claims, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
439 F.2d 169, 194 Ct. Cl. 549, 1971 U.S. Ct. Cl. LEXIS 116, Counsel Stack Legal Research, https://law.counselstack.com/opinion/donald-m-drake-company-v-the-united-states-cc-1971.