Dravo Corp. v. United States

594 F.2d 842, 25 Cont. Cas. Fed. 82,542, 219 Ct. Cl. 416, 1979 U.S. Ct. Cl. LEXIS 62
CourtUnited States Court of Claims
DecidedFebruary 21, 1979
DocketNo. 315-77
StatusPublished
Cited by27 cases

This text of 594 F.2d 842 (Dravo Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dravo Corp. v. United States, 594 F.2d 842, 25 Cont. Cas. Fed. 82,542, 219 Ct. Cl. 416, 1979 U.S. Ct. Cl. LEXIS 62 (cc 1979).

Opinion

PEE CURIAM;

This case comes before the court on plaintiffs request, filed August 28, 1978, for review by the court of the recommended decision of Trial Judge Robert J. Yock, filed August 3, 1978, pursuant to Rule 166(c), on plaintiffs motion and defendant’s cross-motion for summary judgment, having been submitted to the court on the briefs and oral argument of counsel. Upon consideration thereof, since the court agrees with the trial judge’s [419]*419recommended decision, as hereinafter set forth, it hereby affirms and adopts the decision as the basis for its judgment in this case. With respect to the issue discussed in Part III of the trial judge’s opinion, the panel points out that, under the uniform practice of the court, this panel is bound by the recent decision by another panel in Framlau Corp. v. United States, 215 Ct. Cl. 185, 196-99, 568 F.2d 687, 693-95 (1977), and could not overrule or disregard it, even if we had the disposition to do so; only the court en banc can do that. Accordingly, plaintiffs motion for summary judgment is denied, defendant’s cross-motion for summary judgment is granted and the petition is dismissed.

OPINION OP TRIAL JUDGE

YOCK, Trial Judge:

This contract case involves an appeal from a decision of the Department of the Army, Corps of Engineers Board of Contract Appeals (hereinafter the Board).1 That decision affirmed the contracting officer’s denial of plaintiffs interest claim in the sum of $377,488.81. On cross-motions for summary judgment, the parties seek review of the Board’s decision in accordance with the standards of the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1970).

For reasons outlined herein, the Board’s decision is affirmed.

Facts

Plaintiff is a corporation with general offices at Pittsburgh, Pennsylvania. It describes itself as a diversified enterprise with worldwide operations. It is involved with markets including power generation, water management, water transportation, rapid transit, pollution control, urban development, bulk materials handling, minerals and metals processing, and mining. The company’s activities are organized into four operating groups within which are more than 25 separate business divisions. This contract claim concerns a project which was under the control of the Western Construction Division of the Heavy Construction Group of plaintiff corporation.

[420]*420On August 1, 1969, plaintiff entered into contract No. DACW67-70-C-0005 with the United States Army Corps of Engineers for the purpose of constructing, the Wynoochee Dam, Facilities for Upstream Fish Passage and Roads on the Wynoochee River in the State of Washington. The contract work was completed and accepted on October 20, 1972. During contract performance, between May 1970 and June 1972, Dravo performed the following work:

A). Case No. 32b - Revision of height of lift differentials between monoliths of the Dam Modification No. 37
B). Case No. 14b - Removal of unsafe rock on the right abutment . of the Dam Modification No. 37
C). Case No. 20 - Change in aggregate specifications to specify allowable amounts of wood particles in the aggregate Modification No. 38
D). Case No. 20 - Spillway Choke wall revision Modification No. 33
E). Case No. 11 - Pourback Cave Area-Impact Modification No. 34
F). Case No. 14 - Right Bank Layback-Direct Cost Modification No. 35

Plaintiff presented claims for the above items founded upon the "Changes” and "Suspension of work” clauses of the contract. After several months of negotiating, the Government recognized the validity of these claims. On September 20, 1972, a firm settlement agreement was reached on all of the above items in the total amount of $1,371,624, later corrected for minor errors to $1,371,960. A profit allowance of 10 percent was included in the settlement.

As of December 4, 1972, Modifications 33, 34 and 35 covering items D, E, and F above, had been issued and accepted in the combined total of $123,754. This left a balance of $1,248,206 due plaintiff for the first three items (A, B, and C). There then followed a prolonged period of [421]*421time during which technical difficulties and inactivity delayed plaintiffs receipt of the remaining agreed amount of $1,248,206.

On October 29, 1974, Modification 37 was tendered to plaintiff in the amount of $968,000 for items A and B, followed by Modification 38 on December 20, 1974, in the amount of $280,206 for item C, which made a combined total of $1,248,206. After signing and accepting those modifications, plaintiff transmitted them to the contracting officer by letter of December 23,1974. That letter made the following specific reservation:

By our signatures on Modifications No. P00037 and No. P00038 and Consent of our Sureties thereto, we do not waive, but expressly reserve, the right to claim and receive interest incurred and paid upon the amounts of additional cost and expense occasioned by the recognized "directed changes and suspension of work” from the inception of such directed changes and suspension of work until the date of receipt by us of Modification No. P00037 and Modification No. P00038 recognizing our right to payment for such additional costs and expenses and for which these Modifications are tendered in payment. A separate claim for such interest will be presented in the immediate future.

Plaintiff received payment of the $1,248,206 in accordance with Modifications 37 and 38 on December 24, 1974. That concluded the equitable adjustment settlement with the exception of plaintiffs claim for interest.

Plaintiff calculated its claim for interest in the amount of $377,488.81 in the following manner. Plaintiff began by estimating the costs incurred each month on the Wynoochee Dam project, beginning in August 1970, which were attributable to the changed additional work performed under the contract, and later recognized as valid by contract Modifications 37 and 38. This cost "deficiency” was cumulated to yield a monthly cost "deficiency to date.” By June 1972, the last work on the change order had been performed, and the monthly cost deficiency to date, which had reached $1,068,221, remained static until May 1973. At that time, plaintiff added a profit and bond figure of $129,742 to the cost deficiency to date to yield $1,197,963 which was the total remaining deficiency each month until payment was finally received in December 1974. Plaintiff [422]*422then calculated a monthly "effective rate” of interest on corporate borrowings during the pertinent periods of time, and applied the effective rate to the cost deficiency to date each month to determine the total interest costs.

On January 14, 1975, plaintiff submitted its claim for interest to the contracting officer. This submittal did not mention a claim for imputed interest or additional profit for the use of equity capital but was restricted to an application at the average rate of interest on corporate borrowings to the estimated monthly costs incurred for Modifications 37 and 38 work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

System Fuels, Inc. v. United States
92 Fed. Cl. 101 (Federal Claims, 2010)
Energy Northwest v. United States
91 Fed. Cl. 531 (Federal Claims, 2010)
Wisconsin Electric Power Co. v. United States
90 Fed. Cl. 714 (Federal Claims, 2009)
Southern Nuclear Operating Co. v. United States
77 Fed. Cl. 396 (Federal Claims, 2007)
Parker v. United States
77 Fed. Cl. 279 (Federal Claims, 2007)
Environmental Tectonics Corp. v. United States
72 Fed. Cl. 290 (Federal Claims, 2006)
Gulf Contracting, Inc. v. United States
37 Cont. Cas. Fed. 76,128 (Court of Claims, 1991)
District of Columbia v. C.J. Langenfelder & Son, Inc.
558 A.2d 1155 (District of Columbia Court of Appeals, 1989)
Gevyn Construction Corp. v. The United States
827 F.2d 752 (Federal Circuit, 1987)
Gevyn Construction Corp. v. United States
33 Cont. Cas. Fed. 74,851 (Court of Claims, 1986)
Tatelbaum ex rel. Creditors of A. Hoen & Co. v. United States
33 Cont. Cas. Fed. 74,502 (Court of Claims, 1986)
Nebraska Public Power District v. Austin Power, Inc.
773 F.2d 960 (Eighth Circuit, 1985)
Havens Steel Co. v. Randolph Engineering Co.
613 F. Supp. 514 (W.D. Missouri, 1985)
Entwistle Co. v. United States
32 Cont. Cas. Fed. 72,807 (Court of Claims, 1984)
G.M. Shupe, Inc. v. United States
32 Cont. Cas. Fed. 72,712 (Court of Claims, 1984)
L'Enfant Plaza Properties, Inc. v. United States
31 Cont. Cas. Fed. 71,681 (Court of Claims, 1983)
Rawlins v. United States
686 F.2d 903 (Court of Claims, 1982)
Landram v. United States
229 Ct. Cl. 855 (Court of Claims, 1982)
Maryland Port Administration v. C. J. Langenfelder & Son, Inc.
438 A.2d 1374 (Court of Special Appeals of Maryland, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
594 F.2d 842, 25 Cont. Cas. Fed. 82,542, 219 Ct. Cl. 416, 1979 U.S. Ct. Cl. LEXIS 62, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dravo-corp-v-united-states-cc-1979.