Environmental Tectonics Corp. v. United States

72 Fed. Cl. 290, 2006 U.S. Claims LEXIS 222, 2006 WL 2130527
CourtUnited States Court of Federal Claims
DecidedJuly 31, 2006
DocketNo. 05-746C
StatusPublished
Cited by3 cases

This text of 72 Fed. Cl. 290 (Environmental Tectonics Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Environmental Tectonics Corp. v. United States, 72 Fed. Cl. 290, 2006 U.S. Claims LEXIS 222, 2006 WL 2130527 (uscfc 2006).

Opinion

MEMORANDUM OPINION AND ORDER

BRADEN, Judge.

RELEVANT FACTS1

A. Contract No. N47408-98-C-2103.

On September 25, 1998, the United States Navy (“the Government”) awarded Environmental Tectonics Corporation (“ETC”) Contract No. N47408-98-C-2103 (“the Con[292]*292tract”), for the design and fabrication of two Submarine Decompression Chamber (“SDC”) Segments. See Am. Compl. ¶ 5; see generally Compl. Ex. A (the Contract and Amendments to the Contract). Although the initial completion date was April, 8, 1999, this subsequently was changed on four occasions, with a final completion date of August 31, 2003. See Compl. Ex. A at 112-13, 118-19, 122-23 126-27. In addition, the contract value was changed from $3,278,634.58 to $3,354,486.58. Id. at 116-17.

Shortly after award of the Contract, the Government informed ETC of an error in the Government’s solicitation package, concerning the maximum allowable weight of the SDC Segments. See Am. Compl. ¶ 59; see also Am. Ans. ¶ 59. In an April 6, 1999 Amendment to the Contract, the Government changed the SDC Segment maximum allowable weight from 17,706 kilograms to 16,581 kilograms, a 6.35% decrease in weight. See Compl. Ex. A at 109. This change required ETC to redesign the SDC segments, incur additional unanticipated engineering and manufacturing costs, and delay performance. See Am. Compl. ¶¶ 60, 87-88, 91-93, 106-07, 114,121-22,131-33.

Sometime after award of the Contract, ETC also recognized that the Contract required two separate design packages for the SDC segments. Id. ¶¶ 145-46 (“Under the Contract, ETC found it was necessary to simultaneously prepare and submit separate design packages for SDC Segment 1 and SDC Segment 2 ... essentially doubling] ETC’s work effort.”). To comply with the Contract’s requirements, ETC doubled the work effort budgeted in its proposal, resulting in additional cost and delay. Id. ¶¶ 146, 160-61.

In addition, ETC discovered that the Government’s solicitation package contained numerous instances where the amount and size of components were underestimated. Id. ¶ 166. Again, this situation resulted in an unanticipated increase in engineering and material costs. Id. ¶¶ 167-68.

ETC also incurred other unanticipated material, labor costs, and delays, because the Government allegedly required that ETC perform work that was outside the scope of the Contract and failed to specify that a component for the pressure gauges was only available from one supplier. Id. ¶¶ 222-325, 330-33, 337.

The confluence of these events caused ETC to incur cash flow problems due to the Government’s late payment of ETC invoices, as well as lost profits, net unabsorbed overhead, contract financing costs, and rental costs for manufacturing floor space. Id. ¶¶ 347, 349, 353, 366, 376.

B. The May 6, 2003 Certified Claim.

On November 7, 2002, ETC submitted a Request to the Contracting Officer for reimbursement of the costs listed above. See Gov’t Mot. at 2. The Government characterized this as a “draft claim.” Id. On May 6, 2003, ETC converted the November 7, 2002 Request into a “Certified Claim.” Id. ETC amended the Certified Claim on August 7, 2003, January 6, 2004, and April 28, 2004. Id. On July 22, 2004, the Contracting Officer issued a Final Decision denying all of the claims ETC asserted. Id.

PROCEDURAL BACKGROUND

On July 11, 2005, ETC filed a Complaint in the United States Court of Federal Claims appealing the Contracting Officer’s July 22, 2004 Final Decision. See Compl. at 1. Counts One and Two allege a mutual mistake concerning the type of contract that the parties entered and the weight requirement for the SDC segments, seeking reformation and an equitable adjustment. Id. ¶¶ 378-402. Counts Three and Four allege that the misrepresented specifications were unilateral mistakes and seeks the costs that were incurred. Id. ¶¶ 403-27. Counts Five and Six allege that the Government breached the Contract through “constructive and cardinal changes” and seek costs incurred. Id. ¶¶ 428-53. Count Seven alleges that the Government breached the Duty of Good Faith and Fair Dealing and seeks additional engineering and manufacturing costs incurred. Id. ¶¶ 454-60. Count Eight2 alleg[293]*293es that the Government breached the Duty of Disclosure of Superior Knowledge and seeks additional costs over the contract price for the Government’s failure to disclose certain information to ETC. Id. ¶¶ 461-74. Count Nine alleges that the Government materially breached the Contract and seeks restitution of: “additional, unanticipated labor and material costs ...; extended project management costs ...; loss of efficiency costs; loss [sic] profits; unabsorbed/unrecovered overhead costs; contract financing costs; rental costs; ... [and] claim preparation costs.” Id. ¶¶ 475-77. Count Ten alleges that the Government breached the Contract by delaying commencement of the work subject to the Contract and seeks additional costs. Id. ¶¶ 478-81. Count Eleven alleges that the Government has “materially and fundamentally” breached the Contract and seeks costs incurred by ETC due to the Government’s breach. Id. ¶¶ 482-84.

On November 7, 2005, the Government filed an Answer. On April 21, 2006, the Government filed a Motion to Dismiss Count Nine “to the extent it seeks interest and claim preparation costs.” Gov’t. Mot. at 1. On May 16, 2006, ETC filed an Amended Complaint deleting the claim for liquidated damages from Count Nine and reducing the amount of restitution sought from $9,109,617.50 to $7,995,398.00. Compare Compl. ¶477, with Am. Compl. ¶477. On May 16, 2006, the Government filed an Answer to the Amended Complaint. On May 19, 2006, ETC filed an Opposition to the Government’s Motion. On July 7, 2006, the Government filed a Reply.

DISCUSSION

A. Jurisdiction.

1. Tucker Act.

The Tucker Act provides the United States Court of Federal Claims with “jurisdiction to render judgment upon any claim against the United States founded either upon the Constitution, or any Act of Congress or any regulation of an executive department, or upon any express or implied contract with the United States, or for liquidated or unliquidated damages in cases not sounding in tort.” 28 U.S.C. § 1491(a)(1). The Tucker Act, however, is “only a jurisdictional statute; it does not create any substantive right enforceable against the United States for money damages.” United States v. Mitchell, 445 U.S. 535, 538,100 S.Ct. 1349, 63 L.Ed.2d 607 (1980) (quoting United States v. Testan, 424 U.S. 392, 398, 96 S.Ct. 948, 47 L.Ed.2d 114 (1976)). Therefore, in order to come within the jurisdictional reach of the Tucker Act, a plaintiff must identify and plead a constitutional provision, federal statute, independent contractual relationship, and/or the United States executive agency regulation that provides a substantive right to money damages. See Wopsock v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
72 Fed. Cl. 290, 2006 U.S. Claims LEXIS 222, 2006 WL 2130527, Counsel Stack Legal Research, https://law.counselstack.com/opinion/environmental-tectonics-corp-v-united-states-uscfc-2006.