DODS, Inc.

CourtArmed Services Board of Contract Appeals
DecidedMarch 12, 2015
DocketASBCA No. 59510
StatusPublished

This text of DODS, Inc. (DODS, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DODS, Inc., (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) DODS, Inc. ) ASBCA No. 59510 ) Under Contract No. SPM4A 7-09-M-8426 )

APPEARANCE FOR THE APPELLANT: Mr. David Storey President

APPEARANCES FOR THE GOVERNMENT: E. Michael Chiaparas, Esq. DCMA Chief Trial Attorney Douglas R. Jacobson, Esq. Trial Attorney Defense Contract Management Agency Bloomington, MN

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL PURSUANT TO BOARD RULE 12.3

INTRODUCTION

Appellant, DODS, Inc. (DODS), seeks $18,470.53 in termination settlement costs, appealing from the deemed denial of its I May 2014 certified claim for that sum certain. DODS has elected to proceed pursuant to Board Rule 12.3, and the parties have elected to proceed without a hearing, pursuant to Board Rule 11. We sustain the appeal in part and award $2,792.55, plus interest.

SUMMARY FINDINGS OF FACTS

In July 2009, DODS and the Defense Supply Center, Richmond, Virginia (government), entered into Contract No. SPM4A 7-09-M-B426 for DODS to supply "aircraft formers,'' including a first article for testing, for a total contract award of $6,400 (R4, tab I at L 4 ). The first article was priced at $1,800 (id. at 9), and each of the four aircraft formers that the contract contemplated DODS would deliver subsequent to first article testing was priced at $ L 150 (id. at 8). DODS never submitted a first article for approval (see app. supp. R4, tab A 184 ).

On 13 June 2011, the government terminated the contract for default (R4, tab 2 at 16). On 11 June 2012, we converted the termination for default to a termination for convenience ofthe government. DODS, Inc., ASBCA 57667, 12-2 BCA ~ 35,078 at 172,281. On 18 December 2012, we denied the government's motion to reconsider our decision to convert the termination. DODS, Inc., ASBCA 57667, 13 BCA ~ 35,203 at 172, 716.

On 11 March 2013, DODS submitted to the contracting officer a termination settlement proposal (Standard Form 1435) requesting $18,470.53 (R4, tab 8). After over a year of correspondence including regarding whether DODS had provided the government sufficient information to support that request (R4, tabs 9, 11-17), on 1 May 2014, DODS submitted to the contracting officer a certified claim for $18,470.53 (R4, tab 18; gov't br. at 16, ~ 56), the same amount set forth in the 11 March 2013 settlement proposal. Although the contracting officer never issued a decision on the 1 May 2014 claim, the parties agree that they are at an impasse (Bd. corr. file, 8 October 2014 memorandum of telephonic conference). We find that by 1 May 2014, when DODS submitted its certified claim to the contracting officer, the parties had reached an impasse, establishing the Board's jurisdiction to entertain this appeal. Cf Central Environmental, Inc., ASBCA No. 51086, 98-2 BCA ~ 29,912 at 148,080 (impasse including where 14 months had passed since appellant submitted settlement proposal, and where appellant had requested contracting officer's final decision 4 months after submitting proposal).

The contract includes Federal Acquisition Regulation (FAR) clause 52.249-1, TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED-PRICE) (SHORT FORM) (APR 1984) (R4, tab 1 at 15), which provides:

The Contracting Officer, by written notice, may terminate this contract, in whole or in part, when it is in the Government's interest. If this contract is terminated, the rights, duties, and obligations of the parties, including compensation to the Contractor, shall be in accordance with Part 49 of the Federal Acquisition Regulation in effect on the date of this contract.

DECISION

DODS bears the burden to prove by a preponderance of the evidence that it is entitled to a greater termination settlement amount than that determined by the contracting officer. See General Dynamics Land Systems, Inc., ASBCA No. 52283, 02-1 BCA ~ 31,659 at 156,411. Here, having not issued any decision, the contracting officer did not determine a settlement amount; therefore, DODS bears the burden of proving entitlement to any amount. A convenience termination converts a fixed-price

2 contract into a cost-reimbursement contract, entitling the contractor to recover its allowable costs in accordance with the standards of reasonableness, allocability, and regulatory cost principles, as applicable, plus profit. Id. Pursuant to FAR 49.207, Limitation on settlements, "[t]he total amount payable to the contractor for a settlement, before deducting disposal or other credits and exclusive of settlement costs, must not exceed the contract price less payments otherwise made or to be made under the contract."

Claimed Termination/or Convenience Settlement Costs

DODS seeks the following (R4, tab 8 at 41 ):

Metals: $880.00 Work-in-Progress: $2,679.25 Other Costs: $154.64 General & Administrative Expenses (G&A) $9,147.27 Profit: $1,905.98 Settlement Expenses: $3,791.39 Subtotal: $18,558.53 Less Disposal and Other Credits ($88.00) Total: $18,470.53

Metals and "Other Costs"

DODS seeks $880 for four sheets of metal ($220 per sheet) paid for by TTF, L.L.C. (TTF), (minus a 10%, $88.00 credit), as well as $154.64 in "Other Costs"; namely, the cost of delivery of those sheets to TTF by FedEx (R4, tab 8 at 41-50, 128). We have found that "there is no practical distinction between TTF and DODS." DODS, 13 BCA ~ 35,203 at 172, 711. We further find that one of the sheets "was consumed in the manufacturing process of the First Article" (app. supp. R4, tab A210), leaving three sheets of residual equipment with a value of $660. The government invokes the limitation in FAR 3 l.205-42(a), "Common items," that "[t]he costs of items reasonably usable on the contractor's other work shall not be allowable unless the contractor submits evidence that the items could not be retained at cost without sustaining a loss." The burden is on a contractor to demonstrate that it could not retain the residual equipment at cost for use on other work without sustaining a loss. FAR 31.205-42(a), Termination costs; see Essex Electro Engineers, Inc., DOT CAB Nos. 1025, 1119, 81-1 BCA ~ 14,838 at 73,250 (citing former FPR 1-15.205-42(a) which was essentially identical to FAR 3 l.205-42(a)), ajf'd on recon., 81-1BCA~15,109, ajf'd, 702 F.2d 998 (Fed. Cir. 1983). DODS makes no such showing. We award only the $220 cost of the

3 sheet that was consumed related to first article testing, as well as the $154.64 FedEx delivery cost. 1

Work-in-Progress

DODS seeks $2,679.25 for "Work-in-Progress," consisting of direct labor costs (R4, tab 8 at 41-42). The government does not dispute that those costs were incurred performing work on the contract, but contends that they are not reasonable, including because DODS did not even produce the first article, which was priced only at $1,800. Indeed, the government invokes FAR 49 .207, Limitation on settlements, which provides that "[t]he total amount payable to the contractor for a settlement, before deducting disposal or other credits and exclusive of settlement costs, must not exceed the contract price less payments otherwise made or to be made under the contract." However, $1,800 was not the price of the contract (the contract price was $6,400) but the price of one of the contract's line items; namely, first article testing (R4, tab 1 at 1, 9). See Concord Electric Co., ASBCA No. 31012, 85-3 BCA ~ 18,484 at 92,844-45.

Nevertheless, we agree that $2,679.25 in direct labor costs, given the circumstances, is not reasonable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Essex Electro Engineers, Inc. v. The United States
702 F.2d 998 (Federal Circuit, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
DODS, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/dods-inc-asbca-2015.