Ingersoll-Rand Co. v. United States

37 Cont. Cas. Fed. 76,248, 24 Cl. Ct. 692, 1991 U.S. Claims LEXIS 602, 1991 WL 279399
CourtUnited States Court of Claims
DecidedDecember 23, 1991
DocketNo. 90-3849C
StatusPublished
Cited by2 cases

This text of 37 Cont. Cas. Fed. 76,248 (Ingersoll-Rand Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ingersoll-Rand Co. v. United States, 37 Cont. Cas. Fed. 76,248, 24 Cl. Ct. 692, 1991 U.S. Claims LEXIS 602, 1991 WL 279399 (cc 1991).

Opinion

FACTS

MARGOLIS, Judge.

On January 30,1989, in connection with a contract with the United States Air Force (Air Force), plaintiff Ingersoll-Rand (Ingersoll) submitted to the contracting officer a claim of $1,659,898, resulting from alleged delay on the part of the defendant.1 The contracting officer issued a final decision on August 11, 1989, denying Ingersoll’s [693]*693claim. Believing the decision to be legally insufficient because it failed to state adequately the reasons for denial of the claim, Ingersoll communicated this view to the Air Force, which agreed on October 3,1989 to have the contracting officer issue a new final decision.

Sometime after October 3, 1989, Ingersoll became concerned that R. Gregory Holley might not have been the proper person to certify the claim and, as a result, submitted a new certification to the contracting officer on January 9, 1990, signed by John Arzbach whose title was “Vice-President and General Manager Portable Compressor Division.”2 This certification was substantially similar to the certification of January 30, 1989.

The contracting officer’s new final decision was not forthcoming, and on October 11, 1990, Ingersoll filed suit in this court, alleging direct access on the ground that its claim had been constructively denied by the contracting officer. Defendant has filed a motion to dismiss, asserting that Ingersoll’s certification does not satisfy the requirements of the Contract Disputes Act of 1978 (CDA), 41 U.S.C. § 601 et seq. Defendant specifically questions whether Ingersoll’s certifications to the contracting officer were “unequivocal as to the completeness and accuracy of the supporting data” because Ingersoll refused to certify such up to the date of execution of the certification. See supra notes 1-2.

DISCUSSION

For this court to assert jurisdiction over a CDA case, the contractor must have certified the claim to the contracting officer in accordance with 41 U.S.C. § 605(c)(1). United States v. Grumman Aerospace Corp., 927 F.2d 575, 579 (Fed.Cir.1991); Tecom, Inc. v. United States, 732 F.2d 935, 937 (Fed.Cir.1984). This “certification requirement assures that the plaintiff is submitting a claim in an amount it then honestly believes is due and that the data furnished at the time of certification are accurate and complete to the best of plaintiff’s knowledge and belief.” J.F. Shea Co., Inc. v. United States, 4 Cl.Ct. 46, 54 (1983) (emphasis in original). Section 605(c)(1) demands the following attestations by the contractor in a certification:

1) that the claim is made in good faith;
2) that the supporting data are accurate and complete to the best of the contractor’s knowledge and belief, and
3) that the amount requested accurately reflects the contract adjustment for which the contractor believes the government is liable.

To satisfy the statute, the contractor “must simultaneously state all three elements of the required certification” and must do so “clearly and unequivocally____” Aeronetics Div., AAR Brooks & Perkins Corp. v. United States, 12 Cl.Ct. 132, 135 (1987). “[N]o less than substantial compliance may be enough to satisfy the certification requirements of 41 U.S.C. § 605(c)(1).” Cupey Bajo Nursing Home, Inc. v. United States, 23 Cl.Ct. 406, 414 (1991).

[694]*694Both of Ingersoll’s certifications to the contracting officer simultaneously state the elements of § 605(c)(1). See supra notes 1-2. However, although they practically “parrot the words of the statute,” Aeronetics Div., AAR Brooks & Perkins Corp., 12 Cl.Ct. at 135, the certifications are not unequivocal because they certify the accuracy and completeness of the supporting data only as of January 18, 1989. Neither certification actually attests to the accuracy and completeness of the supporting data up to the date of certification—in one case, January 30,1989 and in the other case, January 9, 1990. J.F. Shea Co., 4 Cl.Ct. at 54.

This court has no reason to doubt Ingersoll’s assertion that it had identified all costs associated with the claim in question by January 18, 1989. Nevertheless, to permit a contractor to restrict its attestations to a date before execution of the certification and submission of the claim possibly could allow the contractor to escape false claim liability if it should submit with its claim incomplete and/or inaccurate data dated after the date to which the attestation was restricted. This court is hesitant to create precedent allowing contractors to qualify certifications and possibly evade false claim liability, especially in light of the strict approach the Federal Circuit is taking towards certification requirements. See United States v. Grumman Aerospace Corp., 927 F.2d 575.

Because Ingersoll’s certifications were equivocal as to completeness and accuracy of supporting data, this court finds that they do not satisfy the requirements of § 605(c)(1), and therefore defendant’s motion to dismiss is granted.3 The clerk shall dismiss the complaint without prejudice. No costs.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scan-Tech Security, L.P. v. United States
46 Fed. Cl. 326 (Federal Claims, 2000)
United Sales, Inc. v. United States
40 Cont. Cas. Fed. 76,842 (Federal Claims, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,248, 24 Cl. Ct. 692, 1991 U.S. Claims LEXIS 602, 1991 WL 279399, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ingersoll-rand-co-v-united-states-cc-1991.