FRASSON LODOVICO S.r.l.

CourtArmed Services Board of Contract Appeals
DecidedFebruary 10, 2014
DocketASBCA No. 58645
StatusPublished

This text of FRASSON LODOVICO S.r.l. (FRASSON LODOVICO S.r.l.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
FRASSON LODOVICO S.r.l., (asbca 2014).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of-- ) ) FRASSON LODOVICO S.r.l. ) ASBCA No. 58645 ) Under Contract No. W912PF-10-C-0028 )

APPEARANCE FOR THE APPELLANT: Mr. Mauro Frasson Owner

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney MAJ Nancy J. Lewis, JA Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE SHACKLEFORD ON THE GOVERNMENT'S MOTION TO DISMISS FOR LACK OF JURISDICTION

The government moves to dismiss this appeal for lack of jurisdiction asserting that because the appeal was filed more than 90 days after the contracting officer's (CO's) final decision was emailed to a person assisting appellant, it is untimely. Appellant opposed the motion, arguing its appeal was timely filed within 90 days of receipt of the CO's final decision sent to appellant by registered mail. We conclude the appeal was timely filed. The motion is denied.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTION

1. On 27 September 2010, the 409th Contracting Support Brigade, Regional Contracting Office, Vicenza, Italy (government) awarded Contract No. W912PF-10-C-0028 (contract), a design-build construction contract in the amount ofEUR 369.688,20 ($477,818.54), to FRASSON LODOVICO S.r.l. (Frasson or appellant) (R4, tab 1).

2. In unilateral Modification No. P00005, dated 17 February 2012, the government deleted work it alleged Frasson had failed to perform, and reduced the contract amount by EUR 7.800,00. The government also assessed liquidated damages in the amount ofEUR 28.557,80. (R4, tab 20)

3. Appellant, in a 22 March 2012 letter, contested the government's assessment of liquidated damages and requested an equitable adjustment for its installation of two heat recovery units, along with additional work performed on the heating, ventilation, and air conditioning system (R4, tab 22). 4. In a 26 April2012letter, appellant submitted a certified claim for 1 EUR 56.363,44 seeking an equitable adjustment for the purchase and installation of the two heat-recovery units and the repair of the existing heating, ventilation and air conditioning system (R4, tab 24).

5. Frasson filed a petition with the Board on 3 December 2012, seeking an order under Board Rule 1(e) compelling the CO to issue a final decision (R4, tab 27). The Board docketed the request on 4 December 2012 (gov't mot., ex. G-1) and thereafter was advised by the government a final decision would be forthcoming by 25 January 2013. Deeming this date reasonable, on 8 January 2013, the Board issued an Order directing the CO to make a final decision no later than 25 January 2013. The Order also stated that if the CO failed to comply with the Order, such failure would be deemed a decision denying the claim and the contractor could appeal it as such. (Gov't mot., ex. G-2)

6. The CO, Mr. Jeffrey Neill, issued a final decision in a letter dated 22 January 2013, addressed to appellant to the attention of Mr. Frasson (R4, tab 32). It was sent via email on 25 January 2013, to Mr. Rodolfo Prischich (gov't mot., ex. G-3, encl. 8). Mr. Neill stated in a declaration that he believed Mr. Prischich was representing Mr. Frasson, appellant's owner. Mr. Prischich was a former employee of the Regional Contracting Office-Italy (RCO) and was a consultant/advisor to companies doing business with the RCO. He and Mr. Neill had had conversations about the project in question and Mr. Prischich had attended meetings between Mr. Frasson and Mr. Neill, translating for Mr. Frasson. (Gov't mot., ex. G-3)

7. Mr. Neill also had a copy of the final decision sent by certified mail to appellant (gov't mot., ex. G-.3, encl. 8). The decision, addressed to "Frasson Lodovico S.R.L.[,] ATTN: Mr. Frasson," was received by appellant 5 February 2013 (app. resp. at 7, encls. 3, 7). The decision stated, inter alia: "If you decide to appeal, you must, within 90 days from the date you receive this decision, mail or otherwise furnish written notice to the agency board of contract appeals" (R4, tab 32 at 8).

8. Mr. Neill issued a correction to his final decision in a letter dated 25 February 20 13, stating:

The Contracting Officer's Decision letter dated 22 Jan 20 13 contains some errors that might cause some confusion. This letter will clarify the decision. The contract number and dates of actions contained in paragraphs 2, 9, 13a, 13b were erroneous as they were referenced as occurring in calendar year 2012, when they occurred in a different calendar year.

1 The amount claimed in Euros, when converted to dollars, is almost $73,000, well below the threshold of$100,000 requiring certification. 41 U.S.C. § 7103(b). 2 These paragraphs have been corrected to reflect the correct dates (only the year was erroneous).

In addition, in paragraph 29, the decision contained therein is confusing as it says that the "claim is hereby denied in its entirety" when it was approved in part and denied in part in paragraphs 1 and 28a-c.

The letter indicated it contained an enclosure titled "Corrected Contracting Officer's Decision." (R4, tab 33)

9. By correspondence received at the Board 1 May 2013, Mr. Frasson filed an appeal. The notice of appeal stated appellant was appealing "the attached final decision ofthe contracting officer dated 22 January 2013, received on 5 February 2013 via registered mail" and included the CO's 25 February 2013 letter indicating there were corrections to the 22 January 2013 final decision, and a copy of the final decision incorporating the corrections. The appeal was docketed 2 May 20 13.

10. The government filed a motion to dismiss for lack of jurisdiction on 8 August 2013, asserting appellant's appeal was untimely as it was filed 97 days after appellant received the CO's final decision. According to the government, the 90-day appeal period began on 25 January 2013 when the final decision was emailed to Mr. Prischich and the appeal was not filed "with the Board until2 May 2013." (Gov't mot. at 1) The government contends Mr. Prischich was acting as appellant's representative and had actual or apparent authority to do so, thus starting the 90-day time period (gov't mot. at 4, 5). The government also argues that irrespective of Mr. Prischich's authority to receive the CO's final decision, the Board must still find that 25 January 2013 is the date to be used in determining timeliness of the appeal because the Board had ordered the CO to make a final decision no later than 25 January 2013, and if he had not, the claim would be deemed denied and appealable (gov't mot. at 5-6).

11. Appellant contests the motion and denies Mr. Prischich was its representative or had any legal authority to make decisions for the company. According to appellant, Mr. Prischich was only acting as a consultant and translator, was not an employee of the company and had never been delegated authority to represent the company. (App. resp., encl. 2)

12. Appellant's president also submitted an affidavit attesting that he had never requested the government send the CO's final decision via email and none of his "employees or key personnel received notice [of the final decision] prior to my receipt of the original, certified letter which our records show was received on February 5, 2013" (app. resp., encl. 3). Appellant has provided a copy of the envelope and the post office

3 receipt indicating a 5 February 2013 delivery date and receipt by appellant (app. resp., encl. 7).

DECISION

The Contract Disputes Act of 1978 (CDA), 41 U.S.C. § 7103

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cosmic Construction Co. v. The United States
697 F.2d 1389 (Federal Circuit, 1982)
Pathman Construction Company, Inc. v. The United States
817 F.2d 1573 (Federal Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
FRASSON LODOVICO S.r.l., Counsel Stack Legal Research, https://law.counselstack.com/opinion/frasson-lodovico-srl-asbca-2014.