John R. Glenn v. The United States

858 F.2d 1577, 35 Cont. Cas. Fed. 75,568, 1988 U.S. App. LEXIS 13932, 1988 WL 105460
CourtCourt of Appeals for the Federal Circuit
DecidedOctober 13, 1988
Docket88-1230
StatusPublished
Cited by15 cases

This text of 858 F.2d 1577 (John R. Glenn v. The United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John R. Glenn v. The United States, 858 F.2d 1577, 35 Cont. Cas. Fed. 75,568, 1988 U.S. App. LEXIS 13932, 1988 WL 105460 (Fed. Cir. 1988).

Opinion

DECISION

MARKEY, Chief Judge.

The order of the United States Claims Court, 13 Cl.Ct. 784 (December 10, 1987), dismissing John R. Glenn’s (Glenn’s) claim for lack of jurisdiction and denying his motion to transfer, is vacated and the case is remanded with instructions to transfer.

BACKGROUND

The Facts

Though the record is sparse, the parties agree on the facts. Glenn filed a claim with the Contracting Officer (CO) to recover $31,500 alleged to have been wrongfully withheld from him in connection with construction contract number 244-83-0074. The Government had withheld those funds to cover reprocurement costs and liquidated damages arising out of Glenn’s asserted failure to perform the work correctly. Glenn’s claim for the withheld $31,500 was not required to be and was not certified because it was for less than $50,000. See 41 U.S.C. § 605(c)(1) (1982).

On March 29, 1985, the contracting officer issued a final decision denying Glenn’s claim (“the liability decision”). That decision also stated:

[A]s indicated above, the Government has incurred costs in excess of the estimates ... to complete the contract and to correct your [Glenn’s] defective work. Therefore the Government will continue to withhold payment of this amount from the progress payment #7 in order to protect the Government’s interests.
In addition, ... you will be held liable for the excess costs referred to above and any other damages which the Government has incurred. The extent of your liability will be the subject of another Final Decision letter.

The letter concluded with a paragraph detailing Glenn’s avenue of appeal:

This decision may be appealed to the Armed Services Board of Contract Ap *1579 peals.... If you decide to make such an appeal, you must mail or otherwise furnish written notices thereof to the Board of Contract Appeals within 90 days from the date you receive this decision.... Instead of appealing to the Board of Contract Appeals, you may bring an action directly to the U.S. Court of Claims [sic] within twelve months of the date you receive this decision.

Glenn timely appealed the liability decision to the Armed Services Board of Contract Appeals (board) (Appeal No. 31260). That appeal is pending.

On June 10,1986, the CO issued a second final decision (“the quantum decision”) quantifying the total amount owed by Glenn at $88,398.05 — -$66,648.05 for the government’s reprocurement costs and $21,750 for liquidated damages. Subtracting the $31,500 previously withheld and an additional $35,070.32 owed Glenn on an unrelated contract, the quantum decision stated that Glenn “should submit a check in the amount of $21,827.73” ($88,398.05 less $66,570.32).

In the board proceeding on Glenn’s appeal of the liability decision, Administrative Judge Lane prepared a December 24, 1986 memorandum detailing a telephone conference he held with the parties on December 19, 1986. The memorandum indicated that Glenn had brought the quantum decision to the board’s attention, but did so more than 90 days after the final date of that quantum decision, causing “some doubt” about the board’s jurisdiction over the quantum decision. Intending “to save the time and expense of further argument and decision by the Board on the jurisdictional question,” Administrative Judge Lane suggested that Glenn “consider filing an appeal from the [CO’s] June 1986 final [quantum] decision to the U.S. Claims Court with a simultaneous request for transfer of the case to this Board under section 10(d) of the Contract Disputes Act, 41 U.S.C. 609(d).” “The purpose of doing so would be to cure any possible jurisdictional defect from the appellant’s failure to appeal the June final [quantum] decision to this Board within the 90-day deadline.”

Glenn’s Appeal to the Claims Court

On June 4, 1987, Glenn timely appealed the quantum decision to the Claims Court. His complaint noted the quantum decision “withholding payment from [Glenn] ... in the amount of $66,570.32 (the setoff)” and “claiming damages against [him] in the amount of $21,827.73.” Glenn sought: (1) recovery of the $66,570.32 withheld plus interest; (2) declaration that “all claims of the United States against [him] be declared null and void;” (3) recovery of “damages, interest, penalties and costs” to which he is entitled; and (4) “such other and further relief as may be appropriate under the circumstances.” On October 30, 1987, Glenn moved for transfer from the Claims Court to the board. See 41 U.S.C. § 609(d) (1982). 1 That motion was unopposed.

Characterizing Glenn’s claim as one for $66,570.32, and noting that the Contract Disputes Act requires the contractor to certify claims for more than $50,000, the Claims Court sua sponte held that it was without jurisdiction over Glenn’s complaint. The court denied Glenn’s motion to transfer because “[w]hen there has been a failure to appeal the final decision within the 90-day deadline, it would distort the appeal procedure to permit the failure to be cured by an appeal to this court for the express purpose of a transfer to the agency board.”

ISSUE

(1) Whether the Claims Court erred in dismissing Glenn’s complaint for failure to certify his claim.

(2) Whether Glenn’s motion to transfer should have been granted.

*1580 OPINION

Introduction

Administrative Judge Lane’s hope of saving time and expense, by declining to decide whether the board had jurisdiction over the quantum decision, has obviously been frustrated by subsequent events. Experience with the circuitous route suggested here would argue against its repetition.

(1) Claims Court Jurisdiction

In characterizing Glenn’s claim, the Claims Court wrongly focused on the $66,-570.32 prayed for in the complaint, rather than on the original claim for $31,500 made to the CO. 2 As this court made clear in Tecom, Inc. v. United States, 732 F.2d 935, 937 (Fed.Cir.1984), “[b]y the statutory terms [of 41 U.S.C. § 605(c) (1982)], the certification requirement applies to submission of claims to the contracting officer; certification at that time, if required, is all important.” (Emphasis in original.) “It would be most disruptive of normal litigation procedure if any increase in the amount of a claim based on matters developed in litigation before the court [or board] had to be submitted to the contracting officer before the court [or board] could continue to final resolution on the claim.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monbo v. United States
Federal Claims, 2024
Nova group/tutor-saliba v. United States
127 Fed. Cl. 591 (Federal Claims, 2016)
Woodruff v. United States
122 Fed. Cl. 761 (Federal Claims, 2015)
Palafox Street Associates, L.P. v. United States
122 Fed. Cl. 18 (Federal Claims, 2015)
BRC Lease Co. v. United States
93 Fed. Cl. 67 (Federal Claims, 2010)
J. Cooper & Associates, Inc. v. United States
47 Fed. Cl. 280 (Federal Claims, 2000)
Hawkins & Powers Aviation, Inc. v. United States
46 Fed. Cl. 238 (Federal Claims, 2000)
Croman Corp. v. United States
44 Fed. Cl. 796 (Federal Claims, 1999)
Metric Constructors, Inc. v. United States
44 Fed. Cl. 513 (Federal Claims, 1999)
AAI Corp. v. United States
37 Cont. Cas. Fed. 76,038 (Court of Claims, 1991)
Transtechnology Corp. v. United States
36 Cont. Cas. Fed. 75,953 (Court of Claims, 1990)
SMS Data Products Group, Inc. v. United States
36 Cont. Cas. Fed. 75,820 (Court of Claims, 1990)
25 New Chardon Street Ltd. Partnership v. United States
36 Cont. Cas. Fed. 75,779 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
858 F.2d 1577, 35 Cont. Cas. Fed. 75,568, 1988 U.S. App. LEXIS 13932, 1988 WL 105460, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-r-glenn-v-the-united-states-cafc-1988.