Meltech Corporation, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedFebruary 13, 2023
Docket21-1532
StatusUnpublished

This text of Meltech Corporation, Inc. v. United States (Meltech Corporation, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meltech Corporation, Inc. v. United States, (uscfc 2023).

Opinion

In the United States Court of Federal Claims NOT FOR PUBLICATION

No. 21-1532C (Filed: February 13, 2023)

) MELTECH CORPORATION, INC., ) ) Plaintiff, ) ) v. ) ) UNITED STATES, ) Defendant. ) )

Leonard A. Sacks, Leonard A. Sacks & Associates, P.C., Rockville, MD, for plaintiff. Fred A. Mendicino, Faughnan Mendicino PLLC, Dulles, VA, Of Counsel.

Matthew J. Carhart, Trial Attorney, Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington DC, for defendant, with whom on the briefs were Brian M. Boynton, Principal Deputy Assistant Attorney General, Patricia M. McCarthy, Director, Deborah A. Bynum, Assistant Director, Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington DC. Adam J. Kwiatkowski, Assistant District Counsel, U.S. Army Corps of Engineers, Baltimore, MD, Of Counsel.

TRANSFER ORDER

On or about September 29, 2014, the United States Army Corps of Engineers (USACE) awarded plaintiff Meltech Corporation, Inc. a $10.5 million design-build contract to renovate military barracks located in Fort Meade, Maryland. In the course of contract performance, Meltech submitted three certified claims dated August 31, 2017, April 9, 2020, and June 9, 2021. The contracting officer denied the certified claims on July 6, 2018, July 2, 2020, and July 12, 2021, respectively. Meltech appealed the denials of the first and third certified claims to the Armed Services Board of Contract Appeals (ASBCA or Board). Meltech appealed the denial of the second certified claim to this Court. On January 27, 2023, the Court directed the parties to show cause why this case should not be transferred to the ASBCA pursuant to 41 U.S.C. § 7107(d). 1 See ECF No. 17. Both parties timely responded on February 9, 2023. See ECF Nos. 17–18. For the reasons set forth below, transfer of this action is in the interest of justice.

Relevant here, the first certified claim seeks reimbursement of $350,978 and a 150-day contract extension for an alleged differing site condition involving the structural integrity of the military barracks’ existing concrete. Through discovery in the ASBCA proceedings, Meltech claims to have uncovered evidence demonstrating the USACE possessed–but failed to disclose–superior knowledge regarding the structural condition of the subject site. Accordingly, on January 10, 2020, Meltech sought to amend its ASBCA complaint to add claims of superior knowledge and breach of good faith and fair dealing. On June 11, 2020, the Board denied Meltech’s motion to pursue the additional causes of action citing Meltech’s failure to present them in the August 31, 2017 certified claim to the contracting officer.

In the interim, on April 9, 2020, Meltech filed the second certified claim with the contracting officer based on the USACE’s alleged withholding of superior knowledge. Although the phrase “good faith and fair dealing” does not appear in Meltech’s second certified claim, in describing its “simple claim” (notably singular), Meltech explains the contractor “suffered damages based on the USACE[’s] failure to disclose its superior knowledge or to allow Meltech to perform destructive testing for many months without good cause.” See ECF No. 1-2 at 1 (emphasis added). In the April 9, 2020 certified claim, Meltech claimed entitlement to the same amount of increased costs included in the first certified claim (i.e., $350,978), but extended the claimed government-caused delay from 150 days to 283 days. See id. As noted above, the contracting officer denied the second certified claim on July 2, 2020.

Rather than appeal the contracting officer’s July 2, 2020 decision to the ASBCA within the agency board’s 90-day statutory deadline, see 41 U.S.C. § 7104(a), Meltech filed the instant suit on July 1, 2021, i.e., one day shy of the Court’s one-year statutory deadline. See id. § 7104(b)(3). In the complaint filed in this Court, Meltech asserts alternative theories of recovery based on USACE’s alleged withholding superior knowledge and the agency’s alleged breach of good faith and fair dealing. Meltech seeks $2.4 million in damages–an amount not included in either of Meltech’s certified claims.

Shortly after the complaint was filed in this Court, the parties jointly requested a nearly year-long stay to allow the ASBCA to resolve Meltech’s appeals, representing: “In light of the factual overlap between the case before the [ASBCA] and the case before this Court, the parties expect that the board’s decision will likely narrow the factual issues that this Court must decide, if the board’s decision does not dispose of the case entirely.” See ECF No. 5 at 3; accord ECF No. 7 at 1 (“As the parties previously explained, Meltech is currently pursuing claims before

1This case was transferred to the undersigned for adjudication on January 4, 2023, pursuant to Rule 40.1(b) of the Rules of the United States Court of Federal Claims. See ECF Nos. 14–15.

2 the Armed Services Board of Contract Appeals that overlap with the claims it brought before this Court.”). The stay remained in effect until June 14, 2022; the following day, the Court granted the parties’ joint request for a briefing schedule on defendant’s motion to dismiss. See ECF Nos. 9–10.

On September 15, 2022, defendant moved to dismiss Meltech’s complaint or, in the alternative, to stay this case pending final disposition of the ASBCA appeals. See ECF No. 11. Defendant argues Meltech’s allegations constitute impermissible claim splitting. At a minimum, defendant seeks to dismiss Meltech’s claims insofar as they allege a breach of good faith and fair dealing and request damages in excess of $350,978 due to Meltech’s failure to present the issues to the contracting officer. Defendant alternatively requests that the Court stay this matter until the Board proceedings conclude and then dismiss the complaint based on issue preclusion. See id. at 46 (“It is unnecessary to expend resources litigating this case when the case may be substantially narrowed, if not entirely dispose of, by the board’s final judgment.”). Although disagreeing with defendant’s position regarding issue preclusion, Meltech does not oppose a stay and “agrees that a final decision by the Board would limit the scope of disputed facts and shorten the overall duration of any future proceedings before this Court.” See ECF No. 12 at 36.

Title 41, United States Code, Section 7107(d) provides:

If 2 or more actions arising from one contract are filed in the United States Court of Federal Claims and one or more agency boards, for the convenience of parties or witnesses or in the interest of justice, the United States Court of Federal Claims may order the consolidation of the actions in that court or transfer any actions to or among the agency boards involved.

41 U.S.C. § 7107(d). Although not conclusively decided, the weight of authority strongly suggests Meltech’s timely appeal to this Court vests derivative jurisdiction in the ASBCA to adjudicate the merits of Meltech’s April 9, 2020 certified claim following a § 7107(d) transfer. See Glenn v. United States, 858 F.2d 1577, 1580–81 (Fed. Cir. 1988); Southwest Marine, Inc. v. United States, 680 F. Supp. 327, 329–30 (N.D. Ca. 1988); see, e.g., also Suffolk Constr. Co., Inc. v. Gen. Servs. Admin., CBCA 4377, 16-1 BCA ¶ 36,476; but see Nova Grp./Tutor-Saliba v. United States, 127 Fed. Cl. 591, 595–96 (2016).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

John R. Glenn v. The United States
858 F.2d 1577 (Federal Circuit, 1988)
Nova group/tutor-saliba v. United States
127 Fed. Cl. 591 (Federal Claims, 2016)
Avant Assessment, LLC v. United States
134 Fed. Cl. 323 (Federal Claims, 2017)
Morse Diesel International, Inc. v. United States
66 Fed. Cl. 801 (Federal Claims, 2005)
Giuliani Contracting Co. v. United States
36 Cont. Cas. Fed. 75,882 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
Meltech Corporation, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meltech-corporation-inc-v-united-states-uscfc-2023.