BRC Lease Co. v. United States

93 Fed. Cl. 67, 2010 U.S. Claims LEXIS 273, 2010 WL 2245862
CourtUnited States Court of Federal Claims
DecidedMay 25, 2010
DocketNo. 09-111C
StatusPublished
Cited by8 cases

This text of 93 Fed. Cl. 67 (BRC Lease Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
BRC Lease Co. v. United States, 93 Fed. Cl. 67, 2010 U.S. Claims LEXIS 273, 2010 WL 2245862 (uscfc 2010).

Opinion

ORDER GRANTING DISMISSAL

FIRESTONE, Judge.

Pending before the court in this contract dispute action brought pursuant to the Contract Disputes Act (“CDA”), 41 U.S.C. §§ 601-613 (2006), is the defendant’s (“government’s”) motion to dismiss for lack of jurisdiction under Rule 12(b)(1) of the Rules of the Court of Federal Claims (“RCFC”).1 For the reasons set forth below, the government’s motion to dismiss is GRANTED.

BACKGROUND FACTS

A. The Contract Dispute

The relevant facts are taken from the complaint and may be summarized as follows: This case arises from a dispute between the National Institutes of Health (“NIH”) and BRC Lease Company, LLC (“plaintiff” or “BRC”) concerning the construction and leasing of the NIH Biomedical Research Center (“project”) at the Johns Hopkins Bayview Medical Campus in Baltimore. The project is designed under a “build-to-lease” arrangement, whereby BRC has secured the funding for the project and is paid through NIH’s monthly rental payments.2 BRC is the successor in interest to FSK Land Corporation (“FSK”), the original party to a June 15, 2001 lease with NIH.3 Pursuant to that lease, FSK entered into a Development Management Services Agreement with Smith Management and Construction, Inc. (“Smith”) for the design and construction of the project that is at issue in this case.4 The project involved the design and construction of new laboratory and clinical space for NIH. As Development Manager, Smith entered into an Agreement for Construction Services (“Construction Agreement”) with contractor Skanska USA Buildings, Inc. (“Skanska”).

The Construction Agreement required Skanska, the contractor, to substantially complete the project on or before January 18, 2007. Skanska did not achieve substantial completion until October 27, 2007, whereupon NIH took possession and was to begin payment. The lease included a Lease Rider:

The Government and Lessor [ (BRC) ] agree as follows with regard to the Government’s remedies against the Lessor for the acts and omissions of the Lessor that arise from acts or omissions of the Development Manager [ (Smith) ] or other subcontractors [ (Skanska) ] of Lessor .... In the event the Government is damaged as a result of the breach of contract by the [69]*69Development Manager or any of its subcontractors, or any other subcontractor of the Lessor, or as a result of the negligence or intentional misconduct of the Development Manager, its subcontractors, or any other subcontractor of Lessor, the Government will pursue its claim either directly, or through the Lessor, against the Development Manager, its subcontractors, or other subcontractor of Lessor, as the case may be, and the Government will be limited in its recovery to the amount the Government recovers from the Development Manager, its subcontractors, or other subcontractors of Lessor, as the case may be.

(Compl. ¶ 16 (emphasis added).) The NIH Contracting Officer (“CO”) stated in a December 18, 2007 letter to BRC that because Skanska did not achieve substantial performance of the project until October 27, 2007, BRC was to instruct Skanska to pay liquidated damages of $50,000 per day for the period of January 18 through October 27, 2007.

Thereafter, Skanska failed to achieve final completion of the project and by letter dated March 24, 2008, NIH advised BRC that Skanska had “not demonstrated diligence or promptness to correct the failure, default[,] nor neglect in accordance with the contract documents.” (PL’s Opp. to Def.’s Mot. to Dismiss Ex. 1.) The letter further advised BRC that the government would proceed to complete Skanska’s work at a then-estimated cost of $1,789,204. In the March 24, 2008, letter the CO further stated:

[T]he Government effective immediately elects to contract or otherwise perform the requirements and deduct from any payment or payments under this lease, then or thereafter due, the resulting cost to the Government, including all administrative costs. [Smith] provided a reasonable detailed list of incomplete contract requirements with an estimated value of $1,789,204.00. The Government reserves the right to comet the deficiencies and seek additional damages as required under the lease or allowed by law. The Government will provide acttial contract pivposals along udth invoices to BRC for your records and deduct cost to correct deficiencies through the lease payments beginning with March rents.
This is the final decision of the Contracting Officer. You may appeal this decision to the [CBCA].... Instead of appealing to the agency board of contract appeals, you may bring an action directly in the United States Court of Federal Claims....

(Id. (emphasis added).)

NIH did not withhold any rent payments in March or April of 2008. However, on May 2, 2008, NIH notified BRC that NIH intended to withhold May 2008 rent and future rent equal to the amount of the cost of cure. (Id. Ex. 6.) NIH followed up this email with a letter to BRC dated May 15, 2008 which enclosed a copy of Cure Proposals “pursuant to the Default Letter dated March 24, 2008.” (Id. Ex. 7.) This letter stated:

[NIH] has contracted directly with [Smith] to cure the deficiencies as stated in the Cure Notice dated February 22, 2007[sie]. These cure proposals do not represent the total cure and the NIH reserves the right to continue to contract directly and seek damages as warranted. The total amount of these cure proposals] is $232,290.00[,] which will be offset by May rents.

(Id.) The Cure Proposals documented the amount NIH was to spend to cure various aspects of the project that were incomplete or defective. Thereafter, NIH began withholding additional portions of rent due to BRC as an offset to the cost of curing Skans-ka’s defaults, sending Cure Proposals to BRC each month showing the amount to be withheld.5 (See id. Ex. 10.)

On June 19, 2008, the surety and escrow agency, Bank of New York (“BONY’), at the direction of Ambac Assurance Corp., the bond insurer, wrote to NIH stating that NIH was in default of its obligations under the lease because of NIH’s failure to pay rent in the full amount due. (Id. Ex. 8.) BONY [70]*70stated that withholding rent was prohibited by the Lease Rider. In response, NIH wrote to BONY on July 15, 2008, stating:

The NIH has the authority to withhold rent payments and disagrees with the position that a withholding of rent constitutes a default under the Lease. The Federal Acquisition Regulation General Clauses are included in the lease. These clauses include the Mutuality of Obligation clause, which states in relevant part, “The obligations and covenants of the Lessor, and the Government’s obligation to pay rent under this Lease, are interdependent....

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wade v. United States
Federal Claims, 2018
Ogunniyi v. United States
124 Fed. Cl. 525 (Federal Claims, 2015)
Woodruff v. United States
122 Fed. Cl. 761 (Federal Claims, 2015)
Bowers Investment Co. v. United States
104 Fed. Cl. 246 (Federal Claims, 2011)
Environmental Safety Consultants, Inc. v. United States
95 Fed. Cl. 77 (Federal Claims, 2010)

Cite This Page — Counsel Stack

Bluebook (online)
93 Fed. Cl. 67, 2010 U.S. Claims LEXIS 273, 2010 WL 2245862, Counsel Stack Legal Research, https://law.counselstack.com/opinion/brc-lease-co-v-united-states-uscfc-2010.