SGW, Inc. v. United States

36 Cont. Cas. Fed. 75,848, 20 Cl. Ct. 174, 1990 U.S. Claims LEXIS 139, 1990 WL 47673
CourtUnited States Court of Claims
DecidedApril 19, 1990
DocketNo. 29-89C
StatusPublished
Cited by18 cases

This text of 36 Cont. Cas. Fed. 75,848 (SGW, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
SGW, Inc. v. United States, 36 Cont. Cas. Fed. 75,848, 20 Cl. Ct. 174, 1990 U.S. Claims LEXIS 139, 1990 WL 47673 (cc 1990).

Opinion

[175]*175ORDER

MOODY R. TIDWELL, III, Judge:

This action is before the court on defendant’s motion to dismiss plaintiff’s claims not certified nor presented to the contracting officer for final decision. Plaintiff opposed defendant’s motion and also moved for dismissal of defendant’s counterclaims and special plea in fraud.

FACTS

On February 10, 1981, plaintiff SGW Corporation (SGW) contracted with defendant, through the United States Army, to furnish 1,759 rifle barrels at a total cost of $243,621.50. The barrels were to meet strict government specifications and technical requirements. During performance, plaintiff requested and defendant subsequently approved a contract modification which allowed plaintiff to substitute an equivalent grade of steel so long as it satisfied certain physical tests. By May 17, 1983, plaintiff had produced and delivered 966 rifle barrels and had requested and received payments totalling $168,396.42.

On September 29, 1983, a rifle barrel manufactured by plaintiff malfunctioned. An investigation by the Department of the Army concluded that the malfunction was caused by the rifle barrel not having been manufactured pursuant to contract specifications. The Army then tested a representative sample of all the rifle barrels supplied by plaintiff and found the representative sample defective. As a result, defendant removed the remaining barrels from active service and instigated a more detailed investigation of plaintiff. That investigation led to the indictment of Mr. Robert C. Schuetz, part-owner, corporate secretary and plant manager of plaintiff, on eight counts of mail fraud arising out of the alleged knowing delivery of nonspecifi-[176]*176cation rifle barrels to the Amy. Mr. Schuetz was later acquitted on six of the eight counts and the remaining two counts were dismissed.

Defendant terminated the contract for default in 1985 for plaintiff's failure to meet the delivery schedule and, on March 7, 1986, suspended plaintiff and its officers from contracting with the United States. On January 22, 1988, some three years after the termination for default, defendant demanded repayment of unliquidated progress payments from plaintiff in the amount of $34,743.92. Plaintiff then brought suit in this court.

Plaintiff claimed that the contract tolerance of .001 inch for the radius of the rifle barrel was commercially impracticable and impossible to perform in a normal manufacturing environment. Similarly, it was commercially impracticable and impossible to inspect the barrels to see if they met this minuscule degree of contract tolerance. These factors, plaintiff concluded, entitled plaintiff to compensation of the costs incurred in attempting to perform as well as an equitable time extension. Plaintiff also claimed that the contract was wrongfully terminated for default because the termination was based, at least in part, on Mr. Schuetz’ alleged criminal misconduct, notwithstanding that Mr. Schuetz was never convicted. Plaintiff also claimed that defendant breached its good faith duty to cooperate by withholding “superior knowledge” of a problem with the rifle barrels. Due to this lack of notification, plaintiff continued to perform under the contract and produced 500 finished but undelivered barrels and 293 barrels that were approximately seventy-five percent complete when defendant terminated the contract for default. Plaintiff alleged that it incurred uncompensated costs plus lost profit of $219,-581. Plaintiff argued that the termination for default was improper on three grounds. First, when defendant furnished defective specifications to plaintiff; second, when defendant provided defective government property to be used during inspection; and third, when the contracting officer demanded supplementary tests in addition to and more exacting than the tests specified in the contract. Plaintiff argued that the costs it incurred in attempting to perform these alleged constructive changes were compensable and sought to have this court convert the termination for default into a termination for the convenience of the government, allow recovery of plaintiff's lost costs and profit, and bar defendant from demanding repayment of unliquidated progress payments by allowing a time extension to negate the termination for default.

Defendant responded with counterclaims of fraud. Under the False Claims Act (FCA), 31 U.S.C. §§ 3729-3733 (1982 & Supp. V 1987), defendant alleged that plaintiff knew that its rifle barrels did not conform to the specifications but nonetheless presented the non-conforming barrels to defendant for approval and payment. Specifically, defendant alleged that the rifle barrels did not conform to the contract specifications as to dimensions, heat treatment and surface finish. The barrels were therefore unfit for their intended use. Defendant sought FCA penalties of $10,000 for plaintiff’s claims for payment, treble damages amounting to $137,115, and costs of this action. Defendant also counterclaimed under the fraud provisions of the Contract Disputes Act (CDA), 41 U.S.C. § 604 (1982) in that the barrels did not conform to the specifications. Under the CDA, plaintiff would be liable to defendant for $133,652.50, the unsupported amount of its claims, and for all costs attributable to reviewing those claims. Finally, defendant made a special plea in fraud. Defendant argued that because plaintiff practiced or attempted to practice a fraud against the government in the proof, statement, establishment or allowance of its claims under the contract, defendant was entitled to entry of judgment of forfeiture.

Plaintiff responded that defendant had failed to state a legal cause of action upon which relief could be granted, that defendant’s counterclaims under the CDA and the Special Plea in Fraud were time-barred by applicable statutes of limitation, that the latest provisions of the FCA which trebled penalties could not be applied retroactively [177]*177to events that occurred in the years 1981 through 1983 and, finally, that defendant was collaterally estopped from attempting to prove liability under the FCA because the civil penalties of the FCA constituted a punishment and therefore represented a double jeopardy to plaintiff due to Mr. Schuetz’ acquittal of criminal charges.

DISCUSSION

In examining these cross motions to dismiss, the court will accept the facts as alleged by the non-moving party as true, i.e., when assessing defendant’s motion to dismiss, the facts will be viewed in the light most favorable to plaintiff and when assessing plaintiff’s motion to dismiss, the facts will be viewed in the light most favorable to defendant. Scheuer v. Rhodes, 416 U.S. 232, 236, 94 S.Ct. 1683, 1686, 40 L.Ed.2d 90 (1974); Pope v. United States, 15 Cl.Ct. 218, 222 (1988).

The fundamental issues for the court are whether defendant properly terminated plaintiff’s contract for default and demanded repayment of $34,743.92 in unliquidated progress payments. The parties concede that these issues are properly before this court and the court agrees that it has subject matter jurisdiction over these issues. See 41 U.S.C. § 605(a), (c)(1) (1982).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shell Oil Company v. United States
123 Fed. Cl. 707 (Federal Claims, 2015)
Hernandez, Kroone and Associates, Inc. v. United States
110 Fed. Cl. 496 (Federal Claims, 2013)
American Heritage Bancorp v. United States
56 Fed. Cl. 596 (Federal Claims, 2003)
First Federal Savings Bank v. United States
52 Fed. Cl. 774 (Federal Claims, 2002)
UMC Electronics Co. v. United States
45 Fed. Cl. 507 (Federal Claims, 1999)
TS Infosystems, Inc. v. United States
41 Cont. Cas. Fed. 77,007 (Federal Claims, 1996)
Jana, Inc. v. United States
40 Cont. Cas. Fed. 76,862 (Federal Claims, 1995)
Mega Construction Co. v. United States
39 Cont. Cas. Fed. 76,564 (Federal Claims, 1993)
Tyger Construction Co. v. United States
38 Cont. Cas. Fed. 76,499 (Federal Claims, 1993)
Boeing Co. v. United States
38 Cont. Cas. Fed. 76,332 (Court of Claims, 1992)
AAI Corp. v. United States
37 Cont. Cas. Fed. 76,038 (Court of Claims, 1991)
Summit Contractors v. United States
36 Cont. Cas. Fed. 75,964 (Court of Claims, 1990)
Continental Heller Construction v. United States
36 Cont. Cas. Fed. 75,944 (Court of Claims, 1990)
Scott Aviation v. United States
36 Cont. Cas. Fed. 75,901 (Court of Claims, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
36 Cont. Cas. Fed. 75,848, 20 Cl. Ct. 174, 1990 U.S. Claims LEXIS 139, 1990 WL 47673, Counsel Stack Legal Research, https://law.counselstack.com/opinion/sgw-inc-v-united-states-cc-1990.