Lodge Construction, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedApril 14, 2021
Docket13-499
StatusPublished

This text of Lodge Construction, Inc. v. United States (Lodge Construction, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lodge Construction, Inc. v. United States, (uscfc 2021).

Opinion

In the United States Court of Federal Claims No. 13-499; 13-800 Filed: April 14, 2021

LODGE CONSTRUCTION, INC.,

Plaintiff,

v.

THE UNITED STATES,

Defendant.

Michael H. Payne, Cohen Seglias Pallas Greenhall & Furman, Philadelphia, PA, for Plaintiffs.

John H. Roberson, Senior Trial Counsel, with whom were Deborah A. Bynum, Assistant Director, Robert E. Kirschman, Director, Commercial Litigation Branch, and Brian M. Boynton, Acting Assistant Attorney General, Civil Division, U.S. Department of Justice, Washington, D.C., for Defendant.

MEMORANDUM OPINION AND ORDER

TAPP, Judge.

This Contracts Dispute Act (“CDA”) case involves the catastrophic failure of a cofferdam in south Florida. Plaintiff, Lodge Construction, Inc. (“Lodge”), originally brought several claims seeking damages, retroactive modification of the construction contract, and conversion of its termination for default into a termination for convenience. On the heels of several fraud counterclaims brought by the United States, Lodge narrowed its challenge by withdrawing several claims. Lodge’s only remaining claims seek a 129-day contract extension and a conversion of the termination of default into a termination for convenience. (Case No. 13-500 Lodge Second Am. Compl. at 14, ECF No. 122; Compl. at 10, ECF No. 1). 1

On August 27, 2020, the United States informed the Court of its intention to move for summary judgment with respect to both liability and fraud. (Case No. 13-500 ECF No. 188). The Court ordered the parties to brief the liability and fraud issues separately. (See Oct. 30, 2020

1 This case originally included claims brought by Lodge’s surety, which were consolidated with Lodge’s claims under Lead Case No. 13-500. The litigation involving the sureties has been transferred to the District of Massachusetts. Lodge’s pending claims have been consolidated under Lead Case No. 13-499, but its Second Amended Complaint, which asserts the contract extension claim, is docketed under Case No. 13-500. All docket references are to Lead Case No. 13-499 unless otherwise noted. Sched. Order, ECF No. 18). Lodge also cross-moved for summary judgment with respect to the fraud issue. (Pl.’s Fraud Opp. and Cross-Mot. for Sum. J. (“Pl.’s Fraud MSJ”), ECF No. 21). After briefing on both issues concluded, Lodge moved for leave to file surreplies on both issues. (Pl.’s Mot. for Leave, ECF No. 26). The United States opposed that request. (ECF No. 28). The Court does not believe additional briefing would be helpful to the adjudication of the parties’ summary judgment motions. 2 Accordingly, Lodge’s Motion for Leave is DENIED. Thus, the summary judgment issues are ripe for decision.

To grant summary judgment, the Court must determine that there is no genuine dispute of material fact. RCFC 56(a). For reasons the Court will briefly outline, the Court finds that issues of material fact preclude summary judgment on both the liability and fraud issues. However, in its Opposition and Cross-Motion for Summary Judgment on Fraud, Lodge raises a timing issue that the Court finds fit to resolve. Lodge argues that the United States’ claims under Counterclaim Count II, based on the CDA’s anti-fraud provision, are time-barred. (Pl.’s Fraud MSJ at 49). The Court agrees with Lodge that the claim is time-barred. Consequently, the Court lacks subject matter jurisdiction to adjudicate the United States’ Counterclaim Count II and it must be dismissed.

Accordingly, the United States’ motions for summary judgment on liability and fraud, (ECF Nos. 19, 20), are DENIED. Lodge’s Cross-Motion for summary judgment on fraud is DENIED. 3 Based on issues Lodge raised in its Cross-Motion for summary judgment on fraud, the Court DISMISSES the United States’ Counterclaim Count II for lack of subject matter jurisdiction.

I. Background 4

In 2010, the U.S. Army Corps of Engineers (“the Corps”) awarded Lodge a competitively-bid fixed price contract to rehabilitate a levee in Palm Beach County—part of the Corps’ broader “Everglades Update” restoration mission. (Case No. 13-800 Compl. at ¶¶ 5–9). This project required subsurface work, and thus Lodge constructed a temporary cofferdam so that it could perform that subsurface work “in the dry.” (Id. at ¶ 11). Pursuant to the solicitation,

2 “The decision to grant or deny leave to file a surreply is committed to the sound discretion of the court, and in making its decision, the court considers whether the surreply is helpful to the adjudication of the motion and whether the defendant will be unduly prejudiced if the court grants leave.” Ute Indian Tribe of Uintah & Ouray Indian Reservation v. United States, 145 Fed. Cl. 609, 617 n. 6 (2019) (citing Plunkett v. Dep’t of Justice, 249 F. Supp. 3d 73, 74 n.2 (D.D.C. 2017)). 3 Lodge’s Motion (ECF No. 21) is styled as a cross-motion for summary judgment, rather than a motion to dismiss. Therefore, the Court dismisses Counterclaim Count II under RCFC 12(h)(3). 4 Given the disposition of the motions in this case, and the pendency of one or more trials, the Court provides only a brief overview of the facts, as gleaned from Lodge’s Complaints and the Court’s docket entries. The Court makes no factual findings here and draws all reasonable inferences in favor of the nonmovant.

2 Lodge was required to submit a design based on the Corps’ subsurface geotechnical site inspection and analysis. (Id. at ¶¶ 11–16). After revisions, the Corps accepted Lodge’s final cofferdam design proposal in July 2011, beginning work soon thereafter. (Id. at ¶¶ 40–45).

In mid-March 2012, water breached two sections of the cofferdam’s sheet pile wall. (Case No. 13-800 Compl. at ¶ 46). As described by one worker present at the time of the initial failure:

[W]e had started placing soil cement when I heard like a bang that was a little different than that, different than that banging against the wall, and I looked up on the levy, and a couple of us went up to the top of the levy, because I could be anywhere on the slope watching the soil cement, and I saw the backhoe walking very fast and you could see water chasing it. There was like a wave of, you know, a foot high or so was coming down this trench in the dry cofferdam, and the backhoe was going as fast as he could, because the ramp to get out of that hole is very close to where we were working. And I instantaneously knew something was happening to the bulkhead . . ..

...

The sheet piling was lifting, was somewhat lifted and continued to creak as you heard the metal of the waler and batter pile scraping as the top of the sheet pile was coming up, and as it came up more water was flowing, and the sheet piling was beginning to bend in. And, you know, it was obvious what happened. And it was not necessarily controlled flow of water. It was what I would describe as catastrophic failure.

The water continued to rise. And by the time -- you know, this was actually pretty scary, because I'm thinking if that levy failed, that 17-foot wall of water is coming down this river to my house, which is -- my dock is down here on the water, so I'm just looking at this, I've never been involved in such a catastrophic failure, and actually I get emotional thinking about it right now.

(Def.’s Mot. for Sum. J. on Liability (“Def.’s Liability MSJ”) Ex. B, ECF No. 19-2. (Deposition of R. Coddington)).

After the failure, the Corps retroactively disapproved of Lodge’s cofferdam design. (Id. at ¶ 52). Later in the spring of 2012, Lodge submitted two certified claims to the Contracting Officer: the first regarding the retroactive disapproval of its sheet pile design and the second regarding Lodge’s entitlement to compensation for the actual breach of the sheet pile wall.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rimade Ltd. v. Hubbard Enterprises, Inc.
388 F.3d 138 (Fifth Circuit, 2004)
Romagosa v. Thomas (In Re Van Diepen)
236 F. App'x 498 (Eleventh Circuit, 2007)
Russello v. United States
464 U.S. 16 (Supreme Court, 1983)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Irwin v. Department of Veterans Affairs
498 U.S. 89 (Supreme Court, 1991)
BedRoc Limited, LLC v. United States
541 U.S. 176 (Supreme Court, 2004)
White v. United States
543 F.3d 1330 (Federal Circuit, 2008)
Cloer v. Secretary of Health and Human Services
654 F.3d 1322 (Federal Circuit, 2011)
National Neighbors, Inc. v. The United States
839 F.2d 1539 (Federal Circuit, 1988)
Heino v. Dept. Of Veterans Affairs
683 F.3d 1372 (Federal Circuit, 2012)
Gabelli v. Securities & Exchange Commission
133 S. Ct. 1216 (Supreme Court, 2013)
Hernandez, Kroone and Associates, Inc. v. United States
110 Fed. Cl. 496 (Federal Claims, 2013)
Checo v. Shinseki
748 F.3d 1373 (Federal Circuit, 2014)
Menominee Indian Tribe of Wis. v. United States
577 U.S. 250 (Supreme Court, 2016)
Plunkett v. Department of Justice
249 F. Supp. 3d 73 (District of Columbia, 2017)
Hanover Insurance Company (The) v. United States
134 Fed. Cl. 51 (Federal Claims, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Lodge Construction, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lodge-construction-inc-v-united-states-uscfc-2021.