Krueger v. United States

38 Cont. Cas. Fed. 76,399, 26 Cl. Ct. 841, 1992 U.S. Claims LEXIS 404, 1992 WL 191196
CourtUnited States Court of Claims
DecidedJuly 27, 1992
DocketNo. 90-4042C
StatusPublished
Cited by5 cases

This text of 38 Cont. Cas. Fed. 76,399 (Krueger v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Krueger v. United States, 38 Cont. Cas. Fed. 76,399, 26 Cl. Ct. 841, 1992 U.S. Claims LEXIS 404, 1992 WL 191196 (cc 1992).

Opinion

OPINION

YOCK, Judge.

This contract dispute is before the Court on the defendant’s motion to dismiss the plaintiff’s complaint for lack of jurisdiction. For the reasons stated herein, the defendant’s motion is granted, and the plaintiff’s complaint will be dismissed.

Facts

This case concerns a dispute over a procurement contract and fourteen purchase orders between the plaintiff, Robert E. Krueger, and the Defense Construction Supply Center (DCSC).1 On July 7, 1986, the DCSC requested bids for the manufacture of twenty-seven test fixtures for discharge valves. Mr. Krueger, in a letter dated July 30, 1986, advised the DCSC that the item description in the request for bids was incorrect and that a higher level inspection system, in accordance with MIL-I-45208, was necessary for the item. After extending the invitation for bids several times, the DCSC revised the item description and set the bid deadline on the contract for December 15, 1986. Mr. Krueger, in a letter dated December 10,1986, that he submitted with his offer, stated that his offer included the higher level inspection system, MIL-I-45208, and all fabrication, welding, and inspection in accordance with MID-STD-278. When the DCSC awarded Contract No. DLA 700-87-C-2005 (hereafter C-2005 contract) to Mr. Krueger on March 26, 1987, clause J02 of the contract incorporated Mr. Krueger’s letter of December 10, as well as three other letters he had submitted. However, the contract did not include the standard clause, E06, which specifies higher-level contract quality requirements.

Between January 15, 1987, and June 22, 1989, the DCSC issued fourteen purchase orders to Mr. Krueger for various items, including valves, levers, and cylinders. The first order, DLA 700-87-M-BC17, was terminated for the convenience of the Government on May 3, 1988. Mr. Krueger has not submitted a claim for costs incurred under this purchase order.

[843]*843On June 22, 1988, Mr. Krueger wrote to the administrative contracting officer at the Defense Contract Management Area Office (DCMAO) in San Francisco. In the letter, Mr. Krueger detailed the current status of the contract and eight of the remaining purchase orders. The contract and the eight purchase orders provide most of the basis of Mr. Krueger’s complaint. For six of these purchase orders, Mr. Krueger stated that he “required” specific price increases to cover extra costs allegedly caused by Government delays. For the other two purchase orders, Mr. Krueger did not request price increases. As for the C-2005 contract, Mr. Krueger asked for a price increase of $27,000 ($1,000 per unit) to offset additional storage costs for the material. The additional storage time is the result of a dispute over the welder’s qualification required by the quality inspection that delayed acceptance of the materials by the Government.

On July 21, 1988, Mr. Krueger wrote to the contracting officer at the DCSC and attached a copy of the June 22, 1988 letter that detailed the status of the contract and the purchase orders. Mr. Krueger reiterated that he could not ship the materials due to a dispute about inspection and requested the contracting officer’s assistance in resolving the problem. Also, Mr. Krueger stated that, due to the Government’s prolonged delay in answering his requests for clarification or correction of the inspection requirements, he requested equitable price increases.

Over the next year, Mr. Krueger and the Government maintained a correspondence in which they disputed the inspection terms required in the contract and the purchase orders. Finally, on November 13, 1989, a DCSC contracting officer wrote to Mr. Krueger in response to his letters of June 22 and July 21, 1988, and denied his request for a price increase for Contract No. DLA 700-87-C-2005. The letter stated that it was the final decision of the contracting officer and outlined Mr. Krueger’s options for appealing the decision, including bringing suit in the United States Claims Court within twelve months of the date he received the final decision. The contracting officer sent the final decision to Mr. Krueger by certified mail, and he received it on November 20, 1989.

Also on November 13, 1989, the contracting officer issued Modification P00001 terminating Contract No. DLA 700-87-C-2005 for failure to make progress. The modification stated that it was the final decision of the contracting officer and listed Mr. Krueger’s avenues of appeal and the applicable time limits. The contracting officer sent the modification to Mr. Krueger by certified mail, and he received it on November 20, 1989. In addition, the contracting officer also sent by regular mail a copy of the modification marked “duplicate original,” which Mr. Krueger received on February 5, 1990.

As for the fourteen purchase orders, over a two year period, from January of 1988 to July of 1990, Mr. Krueger was notified that they had either lapsed or been cancelled by modification. Mr. Krueger did not explicitly demand a written final decision on any of the purchase orders, and no final decisions were issued.

Additionally, in early 1989, the DCMAO administrative contracting officer initiated a “Recommendation for Debarment for Poor Performance, Robert E. Krueger” based on Mr. Krueger’s ongoing failure to meet the requirements of a MIL-I-45208 inspection system. On October 17, 1990, Mr. Krueger and his company were debarred until July 24, 1993.

On December 26,1990, Mr. Krueger filed suit in this Court. He seeks (1) rescission of all terminations and cancellations of the contract and the purchase orders, (2) increased prices on contracts and purchase orders to cover additional costs that accrued due to delay, (3) additional monetary compensation plus costs and expenses, (4) rescission and voiding of all records concerning quality deficiencies, (5) rescission of the debarment, and (6) declaratory relief.2

[844]*844 Discussion

This suit is governed by the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 601-613 (1988), which applies to any express or implied contract entered into by an executive agency for the procurement of property. 41 U.S.C. § 602. In its motion to dismiss, the defendant argues that the plaintiff filed his complaint after the end of the twelve-month statute of limitations imposed by the CDA in 41 U.S.C. § 609(a)(3). Alternatively, the Government argues that the portions of the complaint relating to the purchase orders must be dismissed because the plaintiff never requested a final decision from the contracting officer regarding these purchase orders as required by 41 U.S.C. § 605(a). Accordingly, this Court will consider the contract and the purchase orders separately.

I. The C-2005 Contract

The CDA provides that a contractor may file an action directly on a claim in the Claims Court, but this action “shall be filed within twelve months from the date of the receipt by the contractor of the decision of the contracting officer concerning the claim * * 41 U.S.C. §

Related

Brisbin v. United States
119 Fed. Cl. 701 (Federal Claims, 2015)
M.E.S., Inc. v. United States
104 Fed. Cl. 620 (Federal Claims, 2012)
Renda Marine, Inc. v. United States
71 Fed. Cl. 782 (Federal Claims, 2006)
Frymire v. United States
51 Fed. Cl. 450 (Federal Claims, 2002)
Spodek v. United States
51 Fed. Cl. 221 (Federal Claims, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
38 Cont. Cas. Fed. 76,399, 26 Cl. Ct. 841, 1992 U.S. Claims LEXIS 404, 1992 WL 191196, Counsel Stack Legal Research, https://law.counselstack.com/opinion/krueger-v-united-states-cc-1992.