Baltimore Contractors, Inc. v. United States

34 Cont. Cas. Fed. 75,267, 12 Cl. Ct. 328, 1987 U.S. Claims LEXIS 80
CourtUnited States Court of Claims
DecidedApril 30, 1987
DocketNo. 272-70
StatusPublished
Cited by5 cases

This text of 34 Cont. Cas. Fed. 75,267 (Baltimore Contractors, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baltimore Contractors, Inc. v. United States, 34 Cont. Cas. Fed. 75,267, 12 Cl. Ct. 328, 1987 U.S. Claims LEXIS 80 (cc 1987).

Opinion

OPINION

MOODY R. TIDWELL, III, Judge:

On June 1, 1964, the United States, acting through the Architect of the Capitol (Architect) in his role as contracting officer, issued an invitation for bids for the construction of two underground parking garages and related facilities in Washington, D.C. Plaintiff, Baltimore Contractors, Inc., was awarded Contract No. ACho-264 for a fixed price of $11,770,000 on August 10, 1964. A variety of alleged changed conditions, changes to the contract, and delay claims were filed throughout the con[331]*331struction of the garages, requesting an equitable adjustment to the contract in the total amount of $1,760,000 and a 241-day extension of time for performance.

Although all claims before the House Office Building Commission Board of Contract Appeals were eventually settled, denied, or dismissed, plaintiff filed actions in the United States Court of Claims in 1970 and 1975 alleging lack of due process in the administrative proceedings. The trial judge allowed a trial de novo on all contract claims as a result of finding the administrative remedy defective, but on appeal the Court of Claims remanded the case for a de novo decision.1 After careful review of a truly voluminous record, this court finds defendant liable for some of the alleged changed conditions, changes, and delay claims.

PACTS

The two underground garages were constructed in adjacent city blocks, designated Squares 637 and 691. Square 637 is immediately south of the Rayburn House Office Building. Square 691 is located immediately south of the Longworth House Office Building. The two garages were part of the same major construction project as the then-new Rayburn House Office Building.

The garages have three floors for parking plus top decks with grass areas, walks, and fountains for public use. The concrete exterior of the garages is faced with granite. The foundations and bottom floors of the two garages are concrete slabs or mats, five or more feet thick, and the bottom or subgrade elevations of these base slabs are as much as 48 feet below existing ground levels.

The contract called for completion within 18 calendar months. The notice to proceed, which directed plaintiff to begin performance on October 7, 1964, established an initial completion date of April 7, 1966. The Architect accepted beneficial occupancy on September 18, 1967, which was 529 calendar days after the originally specified completion date of April 7, 1966. The Architect allowed a total of 288 days in time extensions, but also assessed a total of $60,250 in liquidated damages for 241 days at the contract specified rate of $250 per day.

A number of disagreements arose during performance of the contract. Many of these centered around excavation for the garages, design and construction of a bracing system to support the excavation, and subsequent backfilling around the garages. When the disputes were not otherwise resolved, plaintiff submitted a series of claims for equitable adjustment to the Architect for decision. Plaintiff filed its first of 32 appeals from adverse decisions of the Architect on September 16, 1968 with the House Office Building Commission Board of Contract Appeals (HOBC), which was staffed on a part-time basis by employees of the General Accounting Office. Of the 32 appeals, three were settled prior to hearing. The remaining appeals were denied or dismissed by the Board.

On August 6, 1970, plaintiff filed a petition in the United States Court of Claims for review of the decision of the Board. On September 8, 1970, the United States filed a motion to dismiss the petition on the ground that plaintiff had failed to exhaust its administrative remedy under the disputes clause. Although the motion was denied on January 15, 1971, the court ordered the proceedings to be suspended for a period of six months from that date to await completion of the administrative proceedings then pending before the Board. These administrative proceedings were not concluded until 1975, some five years after the petition was filed.

Plaintiff had moved in April 1974 that judicial proceedings be resumed. It reiterated the grounds set forth in its petition filed in 1970 (and for three years prior [332]*332thereto before the HOBC) that the proffered administrative remedy was defective and inadequate, and therefore, need not be exhausted. In an Order dated March 3, 1976, the trial judge allowed a trial de novo on the issue of whether or not the administrative remedy was inadequate or deficient. Following a trial on that issue, the trial judge found that the administrative remedy was defective and a de novo trial was required on all contract claims.

On appeal, the United States Court of Claims concluded that the administrative proceedings before the Board were indeed inadequate, but disagreed with the trial judge’s conclusion that all of the issues would have to be retried de novo. The United States Court of Claims remanded the case for a de novo decision, based upon the administrative record before the HOBC, vice a trial de novo.2

DISCUSSION

Plaintiff’s claims arising out of its construction of the underground garages are discussed in the following order: changed conditions, changes to the contract,3 unreasonable delays, and breaches of the contract. Although quantum is not determined by the court, this Opinion on liability is intended to provide guidance in resolving damage issues.

A. Changed Conditions

There are two types of changed conditions that are compensable under the contract’s changed condition clause.4 The first, Type 1, are those that differ materially from what is indicated in the contract and the second, Type 2, are those that differ materially from those ordinarily encountered. Foster Constr. C.A. & Williams Bros. Co. v. United States, 193 Ct.Cl. 587, 435 F.2d 873 (1970).

1. Changed Soil Conditions

Plaintiff alleged that it encountered subsurface conditions at the site that dif[333]*333fered materially from those indicated by the contract borings (a Type 1 changed condition). The relevant considerations for plaintiff's claim are: (a) whether the conditions encountered by plaintiff differed materially from those indicated in the contract documents, (b) could the changed condition have been reasonably anticipated from the site examination and review of the contract documents, and (c) did plaintiff, in fact, rely on its interpretation of the contract documents. Baltimore Contractors, Inc., GSBCA No. 4808, 80-2 BCA ¶ 14,539 at 71,671 (1980).

a. Material Difference in the Conditions Actually Encountered

“The ultimate question in every case is whether the conditions encountered by a contractor were materially different from those reported in the specifications of the contract.” Wm. A. Smith Contracting Co. v. United States, 188 Ct.Cl. 1062, 1088, 412 F.2d 1325, 1339 (1969) (citing Fehlhaber Corp. v. United States, 138 Ct.Cl. 571, 585, 151 F.Supp.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AAB Joint Venture v. United States
75 Fed. Cl. 414 (Federal Claims, 2007)
CEMS, Inc. v. United States
59 Fed. Cl. 168 (Federal Claims, 2003)
North Star Alaska Housing Corp. v. United States
39 Cont. Cas. Fed. 76,607 (Federal Claims, 1993)
Concrete Placing Co. v. United States
37 Cont. Cas. Fed. 76,267 (Court of Claims, 1992)
Spirit Leveling Contractors v. United States
36 Cont. Cas. Fed. 75,770 (Court of Claims, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
34 Cont. Cas. Fed. 75,267, 12 Cl. Ct. 328, 1987 U.S. Claims LEXIS 80, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baltimore-contractors-inc-v-united-states-cc-1987.