Southland Enterprises, Inc. v. United States

37 Cont. Cas. Fed. 76,238, 24 Cl. Ct. 596, 1991 U.S. Claims LEXIS 573, 1991 WL 260784
CourtUnited States Court of Claims
DecidedDecember 9, 1991
DocketNo. 612-84C
StatusPublished
Cited by4 cases

This text of 37 Cont. Cas. Fed. 76,238 (Southland Enterprises, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Southland Enterprises, Inc. v. United States, 37 Cont. Cas. Fed. 76,238, 24 Cl. Ct. 596, 1991 U.S. Claims LEXIS 573, 1991 WL 260784 (cc 1991).

Opinion

OPINION

SMITH, Chief Judge.

This case is a direct-access appeal from the contracting officer’s denial of plaintiff’s requests for equitable adjustments, and comes before the court for disposition following a ten day trial. This dispute arises from a September 24, 1982 contract between Southland Enterprises, Inc. (South-land) and the United States Department of Interior, National Park Service (Park Service) for the construction of a roadway and bridges. Upon consideration of the evidence at trial, examination of the job site, and the post trial briefs, the court finds that the government’s refusal to grant most of the equitable adjustments sought was clearly contrary to the law and the government’s litigation position was not substantially justified. Accordingly, the court awards Southland damages in the amount of $743,861.90 plus interest, with a later determination on the amount of plaintiff’s attorneys’ fees.

FACTS

In 1982, the Park Service’s Denver Service Center initiated an Invitation for Bids for work at Davis Bayou, Gulf Island National Seashore, in Gulfport, Mississippi. The proposed unit price contract called for the construction of a road exiting from U.S. Highway 90. Specifically, Southland was to clear an area between U.S. 90 and Starks Boulevard, lay down road bedding, construct two bridges, and finish and grade the road. The first bridge was near U.S. 90 and crossed the L & N Railroad tracks and was designed at a slope of 1.5 to 1.0. The second bridge crossed Old U.S. 90 and had a slope of 2.0 to 1.0. Some parts of the road were to be constructed through a marshy area known locally as the “buttercup.”

On September 24, 1982, Southland was awarded the contract. Its bid of $1,898,-[598]*598120.80 was the lowest submitted. The Park Service had estimated the contract’s value at $1,804,880.00. The contract contemplated completion within 365 calendar days of the date of the Notice to Proceed. The Notice to Proceed provided that work would begin on November 15, 1982, with a completion date of November 14, 1983. Southland immediately began clearing and grubbing the area upon which the road was to be built. It also began removing an estimated 500 cubic yards (c.y.) of unsatisfactory material1 from the job site.

On December 14, 1982, the Park Service instructed Southland to temporarily cease its clearing and grubbing north of Old U.S. 90. The Park Service realized that there would be an overrun of approximately 18,-500 cy of unsuitable material removed due to poor ground conditions. To avoid massive cost overruns for which it would be responsible, the Park Service issued Change Order Number 1 (Mod. # 1) in March of 1983. Mod. # 1 modified the design of the road. Instead of removing and replacing unsuitable material, South-land was to create a stable road base by laying filter fabric and a bed of shell and sand. An additional 90 days was added to the contract completion date. During the negotiations leading to the change order, Southland reserved its right to collect costs for delay and extended time.

The Park Service issued another five change orders,2 pushing the contract completion date back to May 1, 1984. Work was not, however, completed by that date. The Park Service provided Southland a certificate of substantial completion on November 16, 1984. The Park Service assessed $37,250.00 in liquidated damages. Southland filed a claim with the contracting officer on May 30, 1984. It was denied on September 10, 1984. On November 26, 1984, Southland filed the initial complaint in this case alleging damages of $304,-402.58 due primarily to productivity, clearing and grubbing,3 and other project losses. Southland filed additional claims with the contracting officer in April, 1985. Those claims were rejected on August 21, 1985. Southland filed an amended complaint on September 25, 1985 alleging further damages of $684,409.15.4 In its post-trial brief, Southland claims total damages of $800,-793.62.

DISCUSSION

Following trial both parties attempted to settle. Trial counsel apparently worked out a tentative settlement on all issues. However, this settlement was not approved. Thus it is the court's duty to resolve the dispute. Trial counsel are, however, to be commended for their effective and efficient efforts.

I. BURDEN OF PROOF

The government, in deducting from Southland’s earnings, must carry the burden of proof to show that its actions were correct. Martin J. Simko Constr., Inc. v. United States 11 Cl.Ct. 257, (1986), vacated in part, 852 F.2d 540 (Fed.Cir.1988). “[T]he government has the burden of proving how much of a downward adjustment in price should be made ... the defendant has the laboring oar, and bears the risk of failure of proof, when a decrease is at issue.” Nager Elec. Co. v. United States, 442 F.2d 936, 194 Ct.Cl. 835, 853 (1971).

Southland must prove all elements of the breach of contract in order to obtain an equitable adjustment. Winn-Senter [599]*599Constr. Co., v. United States, 75 F.Supp. 255, 110 Ct.Cl. 34, 63 (1948). Southland must further show that it was harmed by the government’s breach. Id.

II. LIABILITY

There are two basic disputes over liability in this case. The first is whether the Park Service is responsible for the delays in completing the roadway and bridges. The second is whether there were latent defects in the Park Service’s design of the project. In addition, there are various damages claims or factual disputes to which these claims of liability apply. In order to deal with these somewhat complex disputes efficiently, the court will first discuss the two general issues. After addressing defendant’s evidentiary objections, the court will then discuss each item of damages.

A. Delay Claim

Mod. # 1 covered only the direct costs associated with the design modification. It did not compensate Southland for any delays which were within the control of the Park Service. Southland did not waive any claims for losses associated with any such delays.

Southland “ ‘bears the risk of both time and cost for delays which [it] causes or which are within [its] control____ The Government is responsible for both the time and cost effect of delays which it causes, which are under its control, or for which it has agreed to compensate the contractor.’ ” Weaver-Bailey Contractors, Inc. v. United States, 19 Cl.Ct. 474, 476 (quoting J. Cibinic & R. Nash, Administration of Government Contracts 409 (2d ed. 1986)), recon. denied, 20 Cl.Ct. 158 (1990). Moreover, a contractor is entitled to both an extension and recovery of excess costs associated with delay only if the delay was caused solely by the government. See William F. Klingensmith, Inc. v. United States, 731 F.2d 805, 809 (Fed.Cir.1984).

Contract item numbers 3 and 28 required Southland to remove a total of 1,000 c.y. of unsatisfactory material.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

PCL Construction Services, Inc. v. United States
53 Fed. Cl. 479 (Federal Claims, 2002)
M.A. Mortenson Co. v. United States
42 Cont. Cas. Fed. 77,264 (Federal Claims, 1998)
Neal & Co. v. United States
41 Cont. Cas. Fed. 77,003 (Federal Claims, 1996)
Hardwick Bros. v. United States
41 Cont. Cas. Fed. 76,972 (Federal Claims, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
37 Cont. Cas. Fed. 76,238, 24 Cl. Ct. 596, 1991 U.S. Claims LEXIS 573, 1991 WL 260784, Counsel Stack Legal Research, https://law.counselstack.com/opinion/southland-enterprises-inc-v-united-states-cc-1991.