Fleisher Engineering & Construction Co. v. United States

98 Ct. Cl. 139, 1942 U.S. Ct. Cl. LEXIS 30, 1942 WL 4407
CourtUnited States Court of Claims
DecidedOctober 5, 1942
DocketNo. 45010
StatusPublished
Cited by5 cases

This text of 98 Ct. Cl. 139 (Fleisher Engineering & Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fleisher Engineering & Construction Co. v. United States, 98 Ct. Cl. 139, 1942 U.S. Ct. Cl. LEXIS 30, 1942 WL 4407 (cc 1942).

Opinion

Whitaker, Judge,

delivered the opinion of the court:

The plaintiffs jointly entered into a contract with the defendant to construct the superstructure of a number, of buildings known as the Kenfield Housing Project. The basement already had been excavated and the foundation walls had been constructed by another contractor. Plaintiffs allege they were required to do work not required by the contract and that they have not been paid therefor. For this alleged extra work they sue.

I

The first extra is for alleged additional excavation and additional concrete in constructing the front foundation walls of the back and rear entrances to the buildings. Plaintiffs claim they were required to excavate to a greater depth than that called for by the contract and specifications, and that this necessitated additional concrete.

The architectural drawings required that the front foundation walls of these entrances should extend to a minimum depth of 4 feet below finished grade and to at least 6 inches below the present or original grade. The structural drawings required that these walls be carried down to solid bearing. Plaintiffs originally contended that their contract required them to go no deeper than the depths fixed in the architectural drawings, to wit, 4 feet below finished grade, and not less than 6 inches below present or original grade, and that if it was necessary to go deeper in order to reach solid bearing, additional compensation therefor would be paid. However, they now have abandoned this position and admit they were required by the contract to go to solid bearing. This is obviously correct.

Their present contention is that they were required by defendant’s representative to go not only to solid bearing but below it. There is some conflict in the proof on this point. Defendant’s project engineer testified definitely they were not required to go below solid bearing. A Mr. Knight, employed at the time of giving his testimony as a construe[154]*154tion superintendent by John McShain, Inc., but employed on this project in a similar capacity by the plaintiffs, testified that, except in the case of three or four buildings, solid bearing was reached at six or twelve inches below present grade, and in many cases long before they reached the four-foot minimum. (Plaintiffs claim the defendant required them tó go to depths below the four-foot minimum varying from 0.26 feet to 4.81 feet.) Mr. Helsing, who was the president of the Easthom-Melvin Company, the subcontractor doing the.concrete work, testified that, except in the case of from four to six buildings, solid bearing, in his opinion, was reached before the four-foot minimum depth was reached. Mr. Helsing, however, says:

I would say, in most of these cases, that the solid bearing was at the four'-foot minimum, but he [the inspector] was naturally going to be sure of himself, and very naturally carried the thing down to a point where he was positive that there was solid ground. As I see it, it is a matter of interpretation of what is solid ground, where the solid ground is and in some of these cases we could have filled a lot and been on solid ground, but in the inspector’s interpretation it would not have been on solid ground, and he thought the drawings could have made it go down any depth, due to this minimum requirement of solid bearing. He contended throughout that he could require it to be carried to any depth which,in his opinion, would be solid ground.

He sums the case up by saying that it was a matter of a difference of opinion between the plaintiffs and the inspector as to what was solid ground.

Both he and Taylor, plaintiffs’ chief architectural engineer on the job, say that the contractor who had excavated the basement and built the foundation walls had excavated so far beyond the foundation walls that the front foundation walls of the entrances would have been deprived of lateral support if they were carried only to the four-foot minimum, and that this made it necessary to go down to a greater depth ■in order to reach a bearing that was solid underneath and had solid lateral support.

Whatever the reason necessitating excavation below the four-foot minimum, or whether or not it was necessary to do [155]*155so, all parties agree that the excavation was carried no further than was necessary, in the opinion of the defendant’s engineer, to reach solid ground. The only difference between them is whether or not as a matter of fact they were carried below solid ground. It is unnecessary, however, for us to determine this fact, because the contract commits the settlement of such disputes to the contracting officer. Article 15. of the contract provides:

* * * Except as otherwise specifically provided in this contract, all other disputes concerning questions arising under this contract shall be decided by the Contracting Officer, or his duly authorized representative, subject to written appeal by the Contractor within 80 days to the head of the department concerned or his duly authorized representative, whose decision shall be final and conclusive upon the parties thereto as to such questions. * * *

Plaintiffs agree that what is solid bearing is a matter of opinion. They concede that two men might honestly disagree about this. 'They did disagree in this case and that disagreement has been settled adversely to the plaintiffs by the party to whom the contract commits the settlement of such disputes. John McShain, Inc., v. United States, 808 U. S. 512, 513, and cases there cited. There can be no doubt that the settlement of questions of this sort was within the province of the contracting officer or his duly authorized representative. He was on the ground and saw the actual conditions and ivas in much better position to determine what was solid bearing than anyone not on the ground. The parties plainly intended to leave to him the settlement of such disputes.

Even though the extra depth was necessitated by the work of the foundation contractor, plaintiffs are not entitled to recover of the defendant, because, among other reasons, paragraph 5 of section 8 of the “Special Conditions” of the specifications required the contractors to examine the work already performed on the site and to notify the contracting officer if they thought there was any discrepancy between the work actually done and that called for under the foundation contract. This section provided that—

[156]*156* * * Failure of the Contractor to notify the Contracting Officer within fifteen (15) days after turning over the project site or any section thereof to the Contractor that the foundation work done under the Foundation Contract is not in accordance with the Foundation Contract will be deemed conclusive evidence that the work called for under the Foundation Contract has been performed in accordance with that contract. * * *

II

Plaintiffs’ next claim is that certain waterproofing which they were required to do was an extra.

As stated, a previous contractor had constructed the foundation walls of the buildings, but the plaintiffs were required to install a concrete slab on the floor of the basement which connected with the foundation walls. Water seeped in between the foundation walls and the basement floor slab, and the Project Engineer, under date of March 13, 1937, demanded of plaintiffs that this situation be corrected.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Information Systems & Networks, Corp. v. United States
81 Fed. Cl. 740 (Federal Claims, 2008)
Martin J. Simko Construction, Inc. v. United States
33 Cont. Cas. Fed. 74,888 (Court of Claims, 1986)
The Len Company and Associates v. The United States
385 F.2d 438 (Court of Claims, 1967)
Fox Valley Engineering Inc. v. United States
151 Ct. Cl. 228 (Court of Claims, 1960)
Crystal Soap & Chemical Co. v. United States
103 Ct. Cl. 166 (Court of Claims, 1945)

Cite This Page — Counsel Stack

Bluebook (online)
98 Ct. Cl. 139, 1942 U.S. Ct. Cl. LEXIS 30, 1942 WL 4407, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fleisher-engineering-construction-co-v-united-states-cc-1942.