Davis v. United States

82 Ct. Cl. 334, 1936 U.S. Ct. Cl. LEXIS 318, 1936 WL 3024
CourtUnited States Court of Claims
DecidedJanuary 6, 1936
DocketNo. 42374
StatusPublished
Cited by13 cases

This text of 82 Ct. Cl. 334 (Davis v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Davis v. United States, 82 Ct. Cl. 334, 1936 U.S. Ct. Cl. LEXIS 318, 1936 WL 3024 (cc 1936).

Opinion

Williams Judge,

delivered the opinion of the court:

The plaintiffs, trustees in bankruptcy for Foote Bros. Gear & Machine Company, seek recovery of $2,268.20, the value of materials demanded by the defendant and furnished by Foote Bros. Gear & Machine Company, alleged to be in excess of materials required to be furnished under a contract with the United States; also for $275, an amount deducted and withheld upon final settlement as liquidated damages because of delay in delivery of certain materials. For convenience Foote Bros. Gear & Machine Company will hereinafter be referred to as the plaintiff.

In March 1931 plaintiff received from the War Department an invitation for bid “for furnishing all labor and materials and performing all work for furnishing, delivering and installing, ready to operate; or furnishing and delivering only, gate and valve operating machinery, including motors, switchboards, controls, wiring, handrails, motor and machine covers, recess covers, gratings, etc., for Guard Lock in Inland Waterway at Great Bridge, Va.” Specifications, schedules and drawings covering the work to be performed and the materials to be furnished accompanied the invitation for bid. In the specifications it was stated:

Bids will be required as follows:
Proposal A: For furnishing, delivering, and installing eight (8) units of gate operating machinery; eight (8) units of valve operating machinery; all handrails, motor and machine covers, bridges and gratings for eight (8) units of gate operating machinery; and all ladders, motor and machine covers, recess covers, gratings, etc., for eight (8) units of valve operating machinery.
Proposal B: For furnishing and delivering only, the material mentioned in Proposal A, above.

If the contract provided for furnishing and delivering only, delivery was to be completed within 150 calendar days after date of receipt of notice to proceed, liquidated damages at the rate of $25 to be paid for each calendar day of delay by the contractor.

[342]*342In response to the invitation the plaintiff, on or about April 11, 1931, submitted a bid under proposal B, only as follows:

Item. (1) : For furnishing and delivering only, eight (8) units of gate-operating machinery at thirty-one hundred fifty dollars and — cents ($3,150.00) per unit-$25,200. 00
Item (2) : For furnishing and delivering only, eight (8) units of valve-operating machinery at seventeen hundred fifty dollars and — cents ($1,750.00) per unit- 14,000.00
Item (3) : For furnishing and delivering only, all handrails, motor and machine covers, bridges, and gratings for eight (8) units of gate-operating machinery at two hundred dollars and — cents ($200.00) per unit- 1,600.00
Item (4) : For furnishing and delivering only, all ladders, motor and machine covers, recess covers, gratings, etc., for eight (8) units of valve-operating machinery at two hundred dollars and — cents ($200.00) per unit— 1,600.00
Total_ 421,400*. 00

The plaintiff’s bid was accepted and a contract was thereafter entered into between the plaintiff and the United States whereby the plaintiff agreed to furnish and deliver the articles enumerated in proposal B of its bid, at the prices therein stated, in accordance with the specifications, schedules, and drawings, all of which were made a part of the contract. The plaintiff thereafter delivered to the defendant at the point stipulated in the contract all the articles enumerated in the contract, and the same were inspected and accepted by the defendant. All the articles enumerated were delivered by the plaintiff within the time specified except certain patterns described in the specifications, which were delivered 11 days after the expiration of the stipulated date.

After the articles above mentioned had been delivered by plaintiff and accepted by the defendant, and after the defendant had entered into a contract with another party for their installation, the contracting officer wired plaintiff that certain articles shown on the plans had not been received. ■These articles included power and lighting cables and wires, switches, boxes, conduits, condulets, fuses, bushings, lock-nuts, bolts, screws, washers, rubber and friction tape, solder[343]*343ing paste, connectors, and other articles appropriate to the electrical connection and lighting of various parts of the lock mechanism, all being materials necessary to the proper installation of the articles furnished and delivered by plain-tiif. The plaintiff immediately by wire and letter protested the demand that it furnish and deliver the additional materials, contending that the delivery of such materials was not included in its bid and did not come within the contract terms. However, upon the insistent demand of the defendant and with the understanding that it was complying under protest and would ask for reimbursement for the cost of the additional materials and an adjustment of the matter of liquidated damages, the plaintiff furnished and delivered such materials at an actual cost of $2,062.00.

After the additional articles mentioned had been delivered by plaintiff and accepted by the defendant, a voucher! for the amount due under the contract was prepared by the district engineer in charge of the work and forwarded to plaintiff. In this voucher the cost to the plaintiff of the additional articles was not included and there was deducted from the amount otherwise due under the contract the sum of $3,850 liquidated damages, computed on the basis of 154 days’ delay in delivery, at $25 per day. The plaintiff protested this settlement and immediately presented a claim to ¡the defendant for an additional amount of $6,018.20, which included $3,750 of the amount withheld as liquidated damages, together with $2,268.20, the cost plus 10%, of the additional articles delivered under protest. The claim was considered by the contracting officer in charge of the work and forwarded to the Chief of Engineers, U. S. Army, Washington, D. C., with the recommendation that the claim for $2,268.20 for electrical wiring and supplies be disallowed and that the liquidated damages assessed and withheld be remitted to the extent of $3,575.00. The claim was then forwarded by the Chief of Engineers to the General Accounting Office for settlement with the recommendation that it be allowed in full.

The Comptroller General upon the final adjustment of the claim allowed it to the extent of $3,575 of the amount [344]*344of liquidated damages retained, and disallowed it as to the balance.

Two questions are presented: (1) The plaintiff’s right to recover the cost of the additional articles furnished under protest, plus 10%, and, (2) its right to recover $275 withheld as liquidated damages because of 11 days’ delay in furnishing the patterns.

Paragraph 2 of the specifications, under “Work to be done”, consists of two subdivisions — proposal A, and proposal B. Proposal A calls for furnishing, delivering, and installing. Proposal B calls for furnishing and delivering only, the material mentioned in proposal A. The plaintiff’s bid was for furnishing and delivering only, and the materials to be furnished were specifically enumerated. The bid was accepted as made and was incorporated in the contract without change.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Len Company and Associates v. The United States
385 F.2d 438 (Court of Claims, 1967)
Wunderlich v. United States
117 Ct. Cl. 92 (Court of Claims, 1950)
United States v. Johnson
153 F.2d 846 (Ninth Circuit, 1946)
United States v. Lundstrom
139 F.2d 792 (Ninth Circuit, 1943)
S. J. Groves & Sons Co. v. Warren
135 F.2d 264 (D.C. Circuit, 1943)
Fleisher Engineering & Construction Co. v. United States
98 Ct. Cl. 139 (Court of Claims, 1942)
General Steel Products Corp. v. United States
36 F. Supp. 498 (E.D. New York, 1941)
W. E. Callahan Construction Co. v. United States
91 Ct. Cl. 538 (Court of Claims, 1940)
A. P. Williams Iron & Bronze Co. v. United States
90 Ct. Cl. 111 (Court of Claims, 1939)
State Highway Department v. MacDougald Construction Co.
6 S.E.2d 570 (Supreme Court of Georgia, 1939)
John McShain, Inc. v. United States
88 Ct. Cl. 284 (Court of Claims, 1939)

Cite This Page — Counsel Stack

Bluebook (online)
82 Ct. Cl. 334, 1936 U.S. Ct. Cl. LEXIS 318, 1936 WL 3024, Counsel Stack Legal Research, https://law.counselstack.com/opinion/davis-v-united-states-cc-1936.