John McShain, Inc. v. United States

88 Ct. Cl. 284, 1939 U.S. Ct. Cl. LEXIS 245, 1939 WL 4269
CourtUnited States Court of Claims
DecidedFebruary 6, 1939
DocketNo. 43084
StatusPublished
Cited by4 cases

This text of 88 Ct. Cl. 284 (John McShain, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
John McShain, Inc. v. United States, 88 Ct. Cl. 284, 1939 U.S. Ct. Cl. LEXIS 245, 1939 WL 4269 (cc 1939).

Opinion

Booth, Chief Justice,

delivered the opinion of the court:

This case is now before the court upon plaintiff’s motion for a new trial.-

The plaintiff is a Pennsylvania corporation known as -John McShain, Inc. On April I, 1934, plaintiff contracted .in writing with the United States to furnish all labor and materials and perform all work for clearing the site, as well as to do all essential excavation and construct foundations for the erection of an extension to the Internal Revenue Building in Washington.

The work exacted by the contract and specifications included the site bounded by Pennsylvania Avenue, Tenth, Eleventh, and C Streets NW., and the expressed consideration was $149,200. On this site were a number of buildings (Finding 5) which plaintiff was to remove, and in connection with the necessary excavation to be made plaintiff was advised by the specifications that “The term ‘earth’ as used’ in this paragraph shall be accepted as defining all material * * * practicable to remove and handle with pick and shovel or by hand * * * including boulders up to y2 cubic yard in size.”

Within the limits of the site was a large vacant lot covered with cinders, and underneath the surface, in nowise visible from the usual inspection, was a large quantity of reinforced concrete put there in former years as a foundation for the building which had originally stood thereon. Plaintiff was told to remove the concrete and submit to the Supervising Architect through the construction engineer a claim for so doing. This the plaintiff did.

Paragraph 59 of the specifications reads as follows:

If other material, not indicated on the drawings or specified herein, is encountered within the limits of the excavations required under the contract, or if the actual sub-surface conditions as encountered vary materially from the conditions as shown and specified, then the contractor shall continue with the work and shall submit to the Supervising Architect through the Construe[295]*295tion Engineer or other authorized representative • of the Government a complete report of the conditions encountered, and proper adjustment will be made in the contract as determined by the contracting officer.

Plaintiff’s claim for $1,350 for performing- this work was allowed and approved in accord with the contract and specifications (Finding 5). The General Accounting Office sought to reverse the allowance, and did disapprove and disallow its payment. The defendant does not challenge plaintiff’s right under the law to receive a judgment for the sum involved. There are a great number of cases upholding plaintiff’s right to recover. We will not cite them all. Penn Bridge Co. v. United States, 59 C. Cls. 892, and McShain Co. v. United States, 83 C. Cls. 405, are in point. Judgment for $1,350 will be awarded the plaintiff on this item.

What we previously said and held with respect to the facts as found in Findings 6 and 7 was erroneous. Plaintiff’s motion for a new trial covering this item points out the error as to the principle of law applicable.

Paragraphs 66 and 67 of the specifications are as follows:

66. Backfill over sub-drains outside the foundation or area walls to within 6 inches of the tops of walls shall be clean, hard gravel or broken stone or slag that will pass a 3-inch mesh and be retained on a %-inch mesh screen. See details on Drawing No. E-404. The reinforced paper next to the backfill shall be a strong, two ply, kraft paper with asphalt membrane in the center; the paper to be reinforced with crossed fibers completely embedded in the asphalt.
67. All other backfilling shall be clean earth placed in horizontal layers not over 8 inches in depth. Each layer shall be thoroughly tamped, packed, or puddled, as directed, so that no settlement shall occur.

Sub-drainage was provided for at three different locations, i. e., outside the exterior foundations, outside the areaway wall, and underneath the center portion of the concrete slab. It is conceded that with respect to the first two locations the plans and specifications exacted a backfill composed of clean, hard gravel or broken stone or slag that would pass a 3-inch mesh and be retained on a %-inch mesh screen. [296]*296Plaintiff complied with the above plans and specifications, respecting sub-drainage and was paid therefor.

It is by this suit contended that the backfill over the sub-drainage to be placed beneath the areaway concrete slab,, which extended from the exterior foundation wall of the building to the outer limits of the concrete slab areaway,, was to be composed of clean earth as stated in paragraph. 61 of the specifications. The plaintiff was not permitted, by the construction engineer to use clean earth. He was-required by this official to backfill with clean, hard gravel as provided in specification 66. Plaintiff did not assent to: doing the work in accord with the construction .engineer’^ views.

During the course of existing differences over the backfill item, the construction engineer in order to forestall an apparent delay in finishing the work requested the plaintiff in writing to proceed with the same and at the same time said “your observance of this request to proceed with the work”' will be the subject of an adjustment of the costs later on. Using a backfill of gravel increased the plaintiff’s cost of doing the work by the sum of $1,817.93.

Specification 66 refers to Drawing E-404 and this drawing points out where the subsurface drains are to be installed, and does not provide for a backfill of gravel as to the tile drain to be installed underneath the center of the concrete-slab.

It is admitted that a difference existed between the specifications and the work called for under the plans and this-difference was as to the character of backfill over the drains. Drawing E-404 expressly discloses an entire absence of any requirement to backfill the drainage area under the center of the concrete slab with gravel, and the determination of this question involved not a determination of facts but an interpretation of the contract, drawing, and specifications.

The contracting officer, in order to reach a conclusion, did' of necessity predicate the same by construing the specifications and drawing to exact a backfill of gravel for the drain under the concrete slab by implication. It could not have [297]*297been done otherwise, for it is clear that no express language imposed this duty upon the contractor. The official was in doubt and his request to the contractor to proceed in accord with his wishes and later adjust the issue indicates that what was to be determined was a construction of the scope of the contract, specifications, and drawing.

The case of Davis v. United, States, 82 C. Cls. 334, 346, is similar to the instant one. In the Damis ease this court held—

There is no question that parties to a contract are competent to make a stipulation of this kind, and its provisions, when made, are binding upon them. But the competency of the parties to so stipulate, as the. courts have many times pointed out, is limited to the decision of questions of fact arising under the contract, such as the quantity and quality of materials delivered, whether the work performed meets contract requirements, causes of delay in the performance of the work, etc.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Moorman
338 U.S. 457 (Supreme Court, 1950)
Alamo Construction Co. v. United States
86 F. Supp. 845 (Court of Claims, 1949)
Silas Mason Co. v. United States
90 Ct. Cl. 266 (Court of Claims, 1940)

Cite This Page — Counsel Stack

Bluebook (online)
88 Ct. Cl. 284, 1939 U.S. Ct. Cl. LEXIS 245, 1939 WL 4269, Counsel Stack Legal Research, https://law.counselstack.com/opinion/john-mcshain-inc-v-united-states-cc-1939.