Silas Mason Co. v. United States

90 Ct. Cl. 266, 1940 U.S. Ct. Cl. LEXIS 139, 1940 WL 4043
CourtUnited States Court of Claims
DecidedJanuary 8, 1940
DocketNo. 44659
StatusPublished
Cited by6 cases

This text of 90 Ct. Cl. 266 (Silas Mason Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Silas Mason Co. v. United States, 90 Ct. Cl. 266, 1940 U.S. Ct. Cl. LEXIS 139, 1940 WL 4043 (cc 1940).

Opinion

GkeeN, Judge,

delivered the opinion of the court:

The petition sets out thirty-one separate causes of action and defendant demurs severally to each thereof. Among, other things, the petition alleges in general that the plaintiffs entered into a contract with the defendant to construct a dam in accordance with specifications and supplemental-notices made part of the contract. The contract price was stated to be $29,339,301.50. On September 25, 1934, the plaintiffs received notice from the contracting officer of the defendant to proceed with the work provided in the contract. The contract provided that change orders might be made by the defendant. An “Order for Changes No. 1” which plaintiffs received from the contracting officer provided in part that instead of constructing the dam in accordance with the drawings and specifications attached to the contract, the contractor was directed to construct the dam and appurtenant works in accordance with revised designs as shown by attached general drawings. The “Order for Changes No. 1” provided for a structure vastly greater in magnitude and widely different in character and purpose from that provided by the original specifications.

The last paragraph of the “Order for Changes No. 1” provided that “compensation for the work involved as a result of this order shall be made in pursuance of the provisions of paragraph 24 of specifications No. 570 and (or) the provisions of Article 4 of the contract” and limited the time to submit claims for adjustment of compensation to sixty days from the date of the receipt of the order unless the contracting officer for proper cause shall extend such time. Subsequently, the plaintiffs received from the chief engineer a document entitled “Adjustment of Com[268]*268pensation” with whicli were enclosed typewritten sheets entitled “Specifications Attached and Made a Part of Order for Changes No. 1 in Contract Dated July 16, 1934.” The “Adjustment of Compensation” provided inter alia:

Your claim dated August 23, 1935, has been considered and you have been found to be entitled to the following adjustment of compensation.

Twenty-eight additional drawings were attached and a tabulation which set forth the prices to be paid for the new work. Some items under Specifications No. 570 were eliminated, some new items were added, and a large number of items were modified. The “Adjustment of Compensation” was signed by the chief engineer of defendant and had appended the following:

Chief Engineee,
Bureau of Reclamation, Denver, Colorado.
DeaR Sir: Adjustment of the amount of compensation due under the contract and/or in the time required for its performance by reason of the changes above ordered is satisfactory and is hereby accepted.

In December 1935 this was signed by the plaintiffs, the Atkinson-Kier Company, the Silas Mason Company, and the Walsh Construction Company, and in January next was approved by the Commissioner of the Bureau of Reclamation and the Acting Secretary of the Interior.

The petition further alleges:

While plaintiffs were pursuing the execution of the work as provided in the contract, the contracting officer, upon a multitude of times and occasions, willfully, arbitrarily, and coercively neglected and refused to recognize his obligations and to perform his duties; interfered with, delayed, and prevented plaintiffs’ performance of work as provided in the contract; required and refused payment for the performance of work not required by the contract; failed and refused to make payment to the plaintiffs in accordance with the provisions of the contract; and in many and various other ways and with utter disregard of the provisions of the contract and the rights of plaintiffs thereunder wrongfully and tyrannically imposed upon plaintiffs, by reason whereof plaintiffs were caused to suffer great loss and damage.

[269]*269Following these general allegations, as above stated, the petition sets out thirty-one separate causes of action, all with one exception based on a claim arising out of the contract and work performed in the construction of the dam. We do not think it is necessary to set out specifically each of these separate counts. The wording of any of these counts can easily be ascertained by referring to the petition.

The petition recites that copies of the contract, specifications No. 570, the supplemental notices, schedule and drawings are filed herewith and marked Exhibit “A.” Exhibit A is not included in the printed record and it may be questioned whether what is recited above conforms to Rule 12 of this court. We think, however, it is not necessary for us to pass on this question for the reason that both parties in their arguments quote freely from the contract, make reference to the specifications, and appear to be in entire accord as to what is contained therein so far as material to the decision of the demurrer. We think we are accordingly justified in treating these matters as a part of the petition for the purpose of submitting the demurrer.

Paragraph 14 of Specifications No. 570 and Article 15 of the contract are set out in the argument made for defendant. Paragraph 14 provides:

If the contractor considers any work demanded of him to be outside the requirements of the contract, or considers any record or ruling of the contracting officer or of the inspectors to be unfair, he shall immediately upon such work being demanded or such record or ruling being made, ask for written instructions or decision, * * * and, within ten (10) days after the date of receipt of the written instructions or decision, he shall file a written protest with the contracting officer, stating clearly and in detail the basis of his objections. Except for such protests or objections as are made of record in the manner herein specified and within the time limit stated, the records, rulings, instructions, or decisions of the contracting officer shall be final and conclusive.

Article 15 of the contract provides:

ART. 15. Disputes. — All labor issues arising under this contract which cannot be satisfactorily adjusted by [270]*270the contracting officer shall be submitted to the Board of Labor Review. Except as otherwise specifically provided in this contract, all other disputes concerning questions arising under this contract shall be decided by the contracting officer or his duly authorized representative, subject to written appeal by the contractor within 30 days to the head of the department concerned or his duly authorized representative, whose decision shall be final and conclusive upon the parties thereto as to such questions.

The defendant further in argument cites certain parts of specifications No. 570 with reference to the placing, curing, and protection of the concrete and the sand and other materials used in the making of the concrete; also that part of specifications No. 570 which relates to contraction joint sealing strips and the pipe for grouting contraction joints.. Other provisions of the specifications are also set out in defendant’s argument. As there is no controversy in relation to the wording thereof, these provisions will be treated as supplemental to plaintiffs’ petition in considering the defendant’s demurrer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
90 Ct. Cl. 266, 1940 U.S. Ct. Cl. LEXIS 139, 1940 WL 4043, Counsel Stack Legal Research, https://law.counselstack.com/opinion/silas-mason-co-v-united-states-cc-1940.