Fort Sill Associates v. United States

183 Ct. Cl. 301, 1968 U.S. Ct. Cl. LEXIS 78, 1968 WL 9145
CourtUnited States Court of Claims
DecidedMarch 15, 1968
DocketNo. 386-64
StatusPublished
Cited by9 cases

This text of 183 Ct. Cl. 301 (Fort Sill Associates v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fort Sill Associates v. United States, 183 Ct. Cl. 301, 1968 U.S. Ct. Cl. LEXIS 78, 1968 WL 9145 (cc 1968).

Opinion

Per Curiam:

This case was referred to Trial Commissioner Richard Arens with directions to make his recommendation for conclusions of law on plaintiff’s motion and defendant’s cross-motion for summary judgment under Rule 54(b). The commissioner has done so in an opinion and report filed on September 18, 1967. Plaintiff filed a request for review of the commissioner’s recommendations on November 17, 1967, and the case has been submitted to the court on oral argument of counsel and the briefs of the parties.

[304]*304Since this is a Capehart Act contract, the question arises whether the Armed Services Board of Contract Appeals had jurisdiction of the various claims. See Len Company v. United States, 181 Ct. Cl. 29, 385 F. 2d 438 (1967). Claim 1 (“Off-site Drainage”) concerns a changed condition under the “Changed Conditions” clause and was therefore within the Board’s jurisdiction. Kesk, Inc. v. United States, No. 219-63, order dated February 2, 1968. Claim 2 (“Core Compaction”) involves no more than a disputed legal issue and, accordingly, it makes no difference whether or not the ASBCA had jurisdiction. Claim 3 (“Borrow Material”) may or may not arise under the contract, but the parties have so treated the claim throughout; plaintiff agrees that it is bound by the administrative record, and it seeks no de novo trial. We therefore treat the count in this case as arising under the contract.

On the merits, Claim 1 is governed by the general rule recently announced in Chris Berg, Inc. v. United States, 182 Ct. Cl. 23, 389 F. 2d 401 (1968).

The court agrees with the commissioner’s recommendation and with his opinion, with minor modifications. It therefore adopts the commissioner’s recommendation and opinion, as modified, as hereinafter set forth together with the preceding paragraphs as the basis for its judgment. Therefore, defendant’s motion for summary judgment is granted, plaintiff’s motion for summary judgment is denied and plaintiff’s petition is dismissed.

Commissioner Arens’ opinion as modified by the court is as follows:

This case, which is before the court on cross-motions for summary judgment, involves three claims arising out of a contract entered into on July 27, 1959, by plaintiff with the Department of the Army for the construction under the Capehart Act1 of 349 housing units at Fort Sill, Oklahoma. On May 9, 1961, the contracting officer denied plaintiff’s request for equitable adjustments on the three claims pre[305]*305sented herein, and, npon appeal, the Armed Services Board of Contract Appeals, after extensive hearings, denied the appeal, except as hereinafter noted with respect to Claim 3.2 Plaintiff challenges the ASBCA decision as being arbitrary and capricious, not supported by substantial evidence, and as being erroneous as a matter of law in designated particulars.

Olaim 1. Off-site Drainage.

Plaintiff admitted that it had the responsibility under the contract for drainage of the site area, but asserted before the ASBCA that it was the understanding of the parties that storm sewers which were to be installed by an off-site contractor were to be available for use by plaintiff for drainage of the site area; but that as a result of various extensions in completion time for the off-site contractor (due primarily to weather and changes in sewer alignment) plaintiff was required to work under flooded and muddy conditions which resulted in increased costs; and that the absence of the off-site drainage facilities constituted a changed condition.

In denying the appeal on plaintiff’s Claim 1, the ASBCA stated:

To establish the existence of an understanding that the off-site drainage system would be available for use appellant relies on (1) contract provisions; and (0) oral commitments made to the appellant by Government agents.
The contract provisions relied on consist of: (1) Article XVII of the housing contract which states, “The Department shall provide those improvements and utilities which are designated in the Drawings and Specifications to be furnished by others * * (2) Technical specifications in the housing contract requiring appellant to connect the on-site sewer system to the off-site sewer system. (3) The time requirements in the off-site contract which required completion of the Fort Sill Boulevard contract within 75 days. (4) Technical specifications in the housing contract which required appellant to drain during construction the on-site area and 25 feet adjoining.
[306]*306The contract provisions encompassed by (1) and (2) above, show the interrelationship of the on-site and off-site work. But they contain no indication as to when the off-site work is to be done and no representations that the off-site work will be ready for appellant’s use by a certain date. The Government points out that there are expressions in the coordination clauses of the contract such as, “if the work in the adjacent area has not been performed” and “if the adjacent work has been completed.” Article XVII, referred to above, also provides in part that the contracting officer shall not delay final inspection and recommendation of acceptance because of non-completion of improvements and utilities to be furnished by others. This language negatives any implication that the off-site work had to be completed when appellant was ready to connect with it. But if a provision that appellant was to connect its sewer system with the off-site system could possibly be construed as a commitment that the off-site system would be available for connection, it does not mean that the off-site system would be ready before the on-site system was constructed. Insofar as we can determine from the record the Fort Sill Boulevard sewer was ready for connection before the on-site system in that area was completed.
The provisions covered by (3) above, concern the time schedule in the off-site contract. The off-site contractor agreed to complete various portions of the sewer system by certain dates. It was not a commitment by the Government to the off-site contractor, much less to the on-site contractor. There is no reference to the off-site time schedule in the housing contract.
The provisions covered by (4) above, impose an obligation on the on-site contractor to drain the area during construction. They place no obligation on the Government except the implied one not to interfere with the contractor’s contractual commitment. It is not shown that the Government did anything to interfere with appellant draining the housing site.

It is clear that the foregoing interpretation of the contract provisions is correct and supports the conclusion reached by the ASBGA that the Government did not commit itself contractually to have the off-site sewer system ready when plaintiff commenced on-site work. National Concrete and Foundation Co. v. United States, 170 Ct. Cl. 470 (1965); Lenry, Inc. and William P. Bergan, Inc. v. United States, [307]*307156 Ct. Cl. 46, 297 F. 2d 550 (1962); Gilbane Bldg. Co. v. United States, 166 Ct. Cl. 347, 333 F. 2d 867 (1964).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
183 Ct. Cl. 301, 1968 U.S. Ct. Cl. LEXIS 78, 1968 WL 9145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fort-sill-associates-v-united-states-cc-1968.