Koppers/Clough v. United States

201 Ct. Cl. 344, 1973 U.S. Ct. Cl. LEXIS 239, 1973 WL 21338
CourtUnited States Court of Claims
DecidedApril 13, 1973
DocketNo. 516-71
StatusPublished
Cited by10 cases

This text of 201 Ct. Cl. 344 (Koppers/Clough v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Koppers/Clough v. United States, 201 Ct. Cl. 344, 1973 U.S. Ct. Cl. LEXIS 239, 1973 WL 21338 (cc 1973).

Opinion

Davis, Judge,

delivered the opinion of the court :

This suit unfolds another phase of the construction difficulties encountered in the building of a radio communications base for the United States Navy at North West Cape in Western Australia. That project — and its pier — first came to our attention in Hardeman-Monier-Hutcherson v. United States, 198 Ct. Cl. 472, 458 F. 2d 1364 (1972), an action by the joint venture which undertook to erect the pier. This suit is by a later contractor on the project, Koppers/Clough (a joint venture of the Koppers Company, Inc., an American firm, and J. O. Clough & Son, Pty., Ltd., an Australian entity), which agreed with the Navy to build the high frequency communications and support facilities, family housing and related structures, together with necessary utilities and roads, all for a fixed sum of over $20,000,000.

The case comes here on review (by way of cross-motions for summary judgment) of the Armed Services Board of Contract Appeals, ASBCA Nos. 12485, 13119, 71-2 BCA [348]*348¶8920, which held the contractor not entitled to recover costs due to delayed access to the pier needed for unloading supplies for the construction project.1 Plaintiff seeks Wunderlich Act review, 41 U.S.C. §§ 321, 322 (1970), and also asks, if necessary, for relief on a claim of breach of contract.

Since the construction site was in a remote area of Australia, 250 miles from the nearest paved road, the Navy concluded that the most economical method for transporting construction materials and other supplies (e.g. oil) to the site would be by sea. As the board found (71-2 BCA ¶8920 at 41,444), the hope was that, by building a pier near the site and allowing its use by second-stage contractors (such as plaintiff), the over-all costs of construction would be reduced. The pier contract was awarded to Hardeman-Monier-Hutcherson in July 1963 for completion within one year, i.e. July 1964, in order to insure these anticipated savings on the second-stage bids. Despite the deadline, the pier was not completed by the time of the invitation for quotations for the later facilities contract in November 1964, nor by the bid-opening in February 1965.2 Koppers/Clough was awarded this facilities contract in March 1965. The terms called for work to begin May 1965 and to be completed, and the contractor demobilized, by December 1966. Construction was not actually finished until October 1967. Plaintiff blames most, if not all, of the delay on its failure to obtain timely use of the pier, which was not completed and made available to it until February 1967, and even then on a restricted basis for five more months. According to Koppers/Clough, this deprivation significantly increased its costs; it says that, in the absence of the pier, it was forced to adopt much more expensive and time-consuming means of bringing the supplies to the North West Cape.

To reimburse it for this cost-increase, the contractor sought an equitable adjustment under the government-furnished property and changes clauses. The board con[349]*349sidered tbe pier to be goyernment-fumisbed property but ruled that neither of these articles permitted relief “under the contract” in this situation. Plaintiff rejects that position, but adds that, if the board is right, there remains a valid breach claim, redressable in court, for the Government’s failure to make the pier available in proper time.

The specifications contained two explicit references to the pier.3 The first stated that “[w]hen completed, the pier structure may be used by the contractor on a scheduled basis * * * for the unloading of camp supplies and construction material. The contractor will be allowed nonexclusive use of the pier * * * for the life of this contract.” In the other reference, access dates for various projects being built 'by other contractors were detailed. Under the pier section of this schedule, it was stated that “[u]pon completion that the contractor may use the pier * * *.” Moreover, the contract contained a government-furnished property clause [GFP clause] saying that “[t]he time for completion of the work under this contract is based upon the expectation that the Government-furnished property, if any, as set forth in the specification will be delivered to the Contractor at the times stated or, if not so stated, in sufficient time to enable [350]*350the Contractor to perform within the time for completion of the contract work.” However, if the property were not delivered on time, and in the absence 'of a suspension-of-work clause — there was none in this contract — “the Government shall only be liable to make an equitable adjustment * * * for changes in the property furnished.” 4

These three clauses were the contractual basis for Koppers’ assumption that it would have access to the pier for most of its shipping needs — an assumption not contradicted by its own estimate at bidding time of a reasonable completion date for the pier.5

For the reasons which follow, we hold that the board was right in refusing relief “under the contract”, but that plaintiff has a breach claim, triable in this court, for any damage due to the Government’s own fault or responsibility for postponement of the pier’s completion.

I

For both administrative relief and recovery in breach, a double-barreled question comes first: did the defendant warrant or represent or affirm that the pier would be made available at any time before it happened to be completed (whenever that might be, and irrespective of fault), and [351]*351was the pier government-fumislied property ?6 Those are the twin issues we consider in this section of the opinion. The corollary problem of whether the defendant’s obligation was a full warranty or the lesser duty to refrain from conduct causing or enlarging the delay is discussed in Part III infra.

Although we shall separately scan the portions of the contract bearing on Koppers/Clough’s use of the pier, our overriding premise will be that, in adjudging whether the defendant had any obligation at all prior to actual completion, these three clauses cannot be read in isolation but must be understood as mutually related in the context of the whole contract and its background.

Taken alone, the first provision — the statement in “B-1.5 Pier”, supra note 3, (“When completed, the pier structure may be used by the contractor * * *”) — is similar to and no stronger than the contractual language found not a warranty in Chris Berg, Inc. v. United States, 182 Ct. Cl. 23, 389 F. 2d 401 (1968). In that case, a government-owned tramway was in existence at the time of contract and available for use by the contractor in building a new tramway. The contract specified that “[t]he existing towers and tramway may be used in erecting the new towers and tramway.” With only that representation present, the court held that the phrase “may be used”, in the absence of a GFP clause, “refers merely to permissive use and not to any specific suitable or intended use.” 182 Ct. Cl. at 28, 389 F. 2d at 405.7 By analogy, the language of this part of B-1.5 alone would provide only for permissive use of the pier and even then only after “completion” (whenever that might physically be).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Manuel Bros. v. United States
55 Fed. Cl. 8 (Federal Claims, 2002)
Precision Pine & Timber, Inc. v. United States
50 Fed. Cl. 35 (Federal Claims, 2001)
Croman Corp. v. United States
49 Fed. Cl. 776 (Federal Claims, 2001)
Northern States Power Co. v. United States
43 Cont. Cas. Fed. 77,450 (Federal Claims, 1999)
Yankee Atomic Electric Co. v. United States
42 Cont. Cas. Fed. 77,396 (Federal Claims, 1998)
Cedar Lumber, Inc. v. United States
32 Cont. Cas. Fed. 72,561 (Court of Claims, 1984)
Fruehauf Corp. v. United States
587 F.2d 486 (Court of Claims, 1978)
Gulf + Western Precision Engineering Co.
24 Cont. Cas. Fed. 82,292 (Court of Claims, 1978)
Koppers/Clough v. United States
529 F.2d 531 (Court of Claims, 1975)
Broome Construction, Inc. v. United States
492 F.2d 829 (Court of Claims, 1974)

Cite This Page — Counsel Stack

Bluebook (online)
201 Ct. Cl. 344, 1973 U.S. Ct. Cl. LEXIS 239, 1973 WL 21338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/koppersclough-v-united-states-cc-1973.