Chris Berg, Inc. v. The United States

389 F.2d 401, 182 Ct. Cl. 23, 1968 U.S. Ct. Cl. LEXIS 46
United States Court of Claims·Decided January 19, 1968·No. 452-65·Published·Cited by 12 cases

Opinion

OPINION

NICHOLS, Judge. *

This is in many respects a companion case to S. S. Mullen, Inc. v. United States, Ct.Cl. 389 F.2d 390 decided today. The contract called for much the same kind of performance, in the same part of the world, in support of the same program. The relief sought is the same. Though the general contractors are different, the dispute again relates primarily to work to be performed by the same subcon *403 tractor, West Coast Steel Co. However, the eases are not consolidated. But a small part of the record in Mullen, relating to the qualification of witnesses, was stipulated into the record here. There are significant differences as to the facts, which we hold compel a different conclusion as to the Government’s liability. With respect to the instant claim, it has not committed a breach and is not obligated to make an equitable adjustment.

The contract let to plaintiff, hereinafter called Berg, in June 1961 (about a year after the Mullen contract) called for erection of new aerial tramways of the Riblet type at Cape Newenham and Northeast Cape, to replace old tramways of the single-track Columbia type.

When this opinion does not call attention to fact differences, the reader may assume the facts are the same as in Mullen. The dispute here relates to the Cape Newenham job and the other is not hereinafter mentioned. Cape Newenham is 460 miles southwest of Anchorage. The tramway there is, like the one in the Mullen ease at Tin City, to support operation of a radome, and leads from a lower terminal over seven intervening towers to a hilltop terminal 1,130 feet higher and 4,294 feet away. The original single-track tramway had been built in 1951, and the track cable had averaged under a 4-year useful life, the last previous replacement having been in September 1958. The icing conditions were less severe than at Tin City, but were second only to that unblessed location in that regard.

The contract was generally similar to the one in Mullen, but it omitted the Government Furnished Property and Joint Inspection clauses. It permitted use of the existing tramway in the same terms. Plaintiff expected to use the existing tramway as in Mullen, to transport 6,000-pound components to the sites of the new towers, which were along the axis of the old. Plaintiff computed its bid on that basis. It made no pre-award site investigation as to any matters here relevant. It expected to accomplish preliminary work in 1961, have the tower components fabricated in Portland, Oregon, and bring them to Cape Newenham by barge for installation in the 1962 construction season. It considered that any method of installation, excluding use of the existing tramway as a “high line” would be more expensive and difficult, particularly in light of the poor access by land to the tower sites.

Mr. Robert McLellan, the engineer and tramway expert who figures in the Mullen case, was also retained by the subcontractor in the case at bar. He first visited the Cape Newenham site in July 1961, shortly after the award, and made a “cursory inspection.” He noticed the corroded condition of the towers and the cables, unlike anything he had observed at other Alaskan tramways, and concluded that there was something peculiarly corrosive in the Cape Newenham air. He noticed a diameter decrease in the track cable similar to that in the failed cable at Tin City. The traction line was badly corroded and worn, but this was of less immediate significance as it was slated to be — and was — replaced in August. While the distance of 961 feet between two towers at Tin City was an adverse factor there, here a stretch occurred of 1,367 feet. This indicated to him that far less ice thickness would be needed to be “critical.” Thereafter, working at other tramways, he built up a lack of confidence in Air Force maintenance methods, particularly the failure, as he saw it, of proper lubrication or greasing of cables to inhibit corrosion.

The contractor in early 1962 asked the defendant to operate the tramway for it during the 1962 construction season, but defendant refused to do so. The legal aspects of this refusal are discussed infra. Realizing it would have to take the tramway over, if it were to carry out its construction plan, it asked Mr. Mc-Lellan to inspect the tramway thoroughly, and this he did in April. The result was an unqualified condemnation. Meanwhile the new traction cable had failed and had been spliced, but the principal grounds for rejection were those already noticed *404 in July. The corrosion of the towers was significant, not as indicating that the towers might fail, but as evidencing the existence of some evil property in the air which might be wreaking destruction on interior strands of the cable which could not be seen.

The defendant, then and through the subsequent proceedings before the Board, maintained that the tramway was perfectly all right. It had its own expert in support of its position. Plaintiff did in fact operate the existing tramway for about six weeks in the construction season, but only on a few occasions and for purposes other than moving or installing most of the 6,000-pound components of the Riblet towers. These it wrestled into place over the inhospitable terrain, at what it says were greatly increased costs.

The case, as in Mullen, went under the Dispute article to the ASBCA (Appeal of Chris Berg, ASBCA #8673, 65-1 BCA ¶ 4643).

The Board found that “Appellant’s decision not to use the tramway exclusively was a reasonable one.” Besides the McLellan testimony, it refers to the fact that the track cable had been used four years in 1962, and that was as long as previous cables had lasted. Also, it found plaintiff was going to use the tramway more frequently and with heavier loads than the Air Force did.

The Board also found:

* * * Nor was the condition of the tramway either unknown or unusual. The condition of the tramway did not change materially from the time of the bid until it was dismantled and its condition was readily ascertained by a site investigation. * * *

Free access — add to your briefcase to read the full text and ask questions with AI

Chris Berg, Inc. v. The United States, 389 F.2d 401, 182 Ct. Cl. 23, 1968 U.S. Ct. Cl. LEXIS 46 (cc 1968).

389 F.2d 401 (Chris Berg, Inc. v. The United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Tom Shaw, Inc. v. United States
824 F.2d 980 (Federal Circuit, 1987)
Kolar, Inc. v. United States
650 F.2d 256 (Court of Claims, 1981)
B-E-C-K Constructors v. State, Department of Highways
604 P.2d 578 (Alaska Supreme Court, 1979)
Turnkey Enterprises, Inc. v. United States
597 F.2d 750 (Court of Claims, 1979)
Fruehauf Corp. v. United States
587 F.2d 486 (Court of Claims, 1978)
Allied Materials & Equipment Co. v. United States
569 F.2d 562 (Court of Claims, 1978)
Koppers/Clough v. United States
201 Ct. Cl. 344 (Court of Claims, 1973)
Maurice Mandel, Inc. v. United States
424 F.2d 1252 (Eighth Circuit, 1970)
Koppers Company, Inc. v. The United States
405 F.2d 554 (Court of Claims, 1968)
Ambrose-Augusterfer Corporation v. The United States
394 F.2d 536 (Court of Claims, 1968)
Fort Sill Associates v. United States
183 Ct. Cl. 301 (Court of Claims, 1968)