Maurice Mandel, Inc. v. United States

424 F.2d 1252, 1970 U.S. App. LEXIS 9574
CourtCourt of Appeals for the Eighth Circuit
DecidedApril 27, 1970
Docket19705_1
StatusPublished
Cited by8 cases

This text of 424 F.2d 1252 (Maurice Mandel, Inc. v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maurice Mandel, Inc. v. United States, 424 F.2d 1252, 1970 U.S. App. LEXIS 9574 (8th Cir. 1970).

Opinion

BRIGHT, Circuit Judge.

Maurice Mandel, Inc. (Mandel), as a successful bidder, undertook to construct and lease to the Government a post office building in Stillwater, Minnesota, upon a site which Mandel agreed to purchase from the United States. After its bid had been accepted and a contract signed with the Government, Mandel discovered that it had under-estimated the cost of construction by relying on certain data which it claimed to be erroneous contained in and made part of the Government’s invitation to bid. Mandel incurred unanticipated construction expenses of $7,932.00 for air conditioning and $495.95 for draining subsurface water.

Mandel brought an action against the Government in the district court under the Tucker Act, 28 U.S.C. § 1346(a) (2), and recovered a judgment on each of these two expense items. The United States appealed and presents a single issue on each claim, viz:

(1) Whether the Government warranted an estimate of air conditioning cooling load capacity contained in its invitation to bid, and

(2) Whether the Government warranted the depth of subsurface water at the proposed construction site.

We affirm on the claim for additional expense for air conditioning, but reverse on the additional construction expense for draining unanticipated subsurface water.

The documents submitted with the invitation to bid form our frame of reference for consideration of each of Man-del’s claims. Those documents, which included a set of tentative plans and specifications, outlined the entire scope of the project. The tentative plans and accompanying data specified basic construction requirements to be incorporated into the final plans which were to be drawn by an architect employed by the party whose bid was accepted. The Government reserved the right to approve these additional plans.

I.

AIR CONDITIONING

Incorporated into the tentative plans were “Mechanical Notes” directing the bidder’s attention to specific requirements for heating and air conditioning. These notes contained this specific item:

Estimated Cooling Load — 183,000 BTU (S.ee Addendum 1, Chap. 5, Par. I).

That addendum paragraph provided:

The capacities designated in the Specific Requirements are based on POD [Post Office Department] calculation for the tentative plan; however, in case of miscalculation or discrepancy, the actual loads based on the construction drawings shall apply and the Lessor shall submit building heating, ventilating and cooling load calculations as outlined in Fig. 1, Instructions for Thermal Load Calculations, using Form 2238, copies of which will be furnished by the Chief, Engineering Branch.

After award of the contract, Mandel employed a consulting engineer to prepare construction drawings. This engineer discovered that the Government had *1254 substantially miscalculated the air conditioning needs for the proposed building. Instead of fifteen tons, the equivalent in capacity to 183,000 BTU load, a building of the size and construction specified by the Government required approximately twenty-five tons of capacity. Mandel, upon being advised of the discrepancy, notified the Post Office Department of its error and later requested that it reimburse Mandel for the additional expense incurred in installing sufficient capacity to properly cool the building. The Government denied this request.

As a basis for reversal, the Government argues that no warranty arises from an estimation. Further, the language contained in the addendum constituted an admonition that responsibility for calculating air conditioning requirements rested with the contractor. We consider each of these arguments.

An estimate often serves as an expedient to be used when the Government must guide bidders on a particular point but has no more precise information available. Womack v. United States, 389 F.2d 793, 182 Ct.Cl. 399 (1968).

The term “estimate” as used here aptly connotes some variance in cooling requirements in the building as proposed and the one to be finally designed. Such term serves to encompass such changes in cooling load requirements attributable to modifications in the design of the proposed building within the ambit of the contract obligations. This language, however, does not serve to notify the bidder that substantial changes in the requirements are reasonably likely, since the final building is to be constructed in accordance with the basic requirements stipulated in the tentative plans. The use of the term “estimate” in the context of this contract does not cast the responsibility for gross miscalculation upon the bidder. Here the actual error amounts to two-thirds more than the requirement specified in the tentative plan.

We perceive no reason for the inclusion of the cooling estimate as datum accompanying the tentative plans unless the Government intended the bidder to rely on this information. The Government might be presumed to speak with some knowledge or authority on this matter since it had prepared and submitted the tentative plan. See Hollerbach v. United States, 233 U.S. 165, 172, 34 S.Ct. 553, 58 L.Ed. 898 (1914). Otherwise, the Government need only have required that the bidder calculate the necessary cooling capacity as dictated by design criteria. 1

In interpreting the term “estimate”, we attach to it that meaning which would be understood by a reasonably intelligent person aware of all the circumstances surrounding the making of the contract. See Sun Oil Co. v. Vickers Refining Co., 414 F.2d 383, 387 (8th Cir., 1969); Restatement of Contracts § 230 (1932). Applying these familiar principles, we hold that a reasonable bidder in Mandel’s circumstances would take the Government’s estimate of its cooling load capacity as specifying a reasonably accurate requirement on which the bidder could safely rely. See Eastern Service Management Co. v. United States, 363 F.2d 729 (4th Cir., 1966). In these circumstances, the estimate or statement constituted a positive representation or a warranty. Womack, supra, 389 F.2d 793.

The addendum clause furnishes no sound basis for the Government to avoid liability. Literally read, the clause addresses a caution to the “Lessor”, a status not yet attained by Mandel as it submitted its bid, and this clause ad *1255 monishes him that in case of miscalculation actual load shall be based on construction drawings, although only tentative ones were then in existence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cebe Farms, Inc. v. United States
116 Fed. Cl. 179 (Federal Claims, 2014)
D.F.K. Enterprises, Inc. v. United States
45 Fed. Cl. 280 (Federal Claims, 1999)
PT & L. CONST. v. Dept. of Transp.
531 A.2d 1330 (Supreme Court of New Jersey, 1987)
P.T. & L. Construction Co. v. State, Department of Transportation
531 A.2d 1330 (Supreme Court of New Jersey, 1987)
City of Columbia v. Paul N. Howard Co.
707 F.2d 338 (Eighth Circuit, 1983)
Caffall Bros. Forest Products, Inc. v. United States
678 F.2d 1071 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
424 F.2d 1252, 1970 U.S. App. LEXIS 9574, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maurice-mandel-inc-v-united-states-ca8-1970.