T. F. Scholes, Inc., and Berks County Trust Company v. The United States

357 F.2d 963, 174 Ct. Cl. 1215, 1966 U.S. Ct. Cl. LEXIS 182
CourtUnited States Court of Claims
DecidedMarch 18, 1966
Docket34-63
StatusPublished
Cited by14 cases

This text of 357 F.2d 963 (T. F. Scholes, Inc., and Berks County Trust Company v. The United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
T. F. Scholes, Inc., and Berks County Trust Company v. The United States, 357 F.2d 963, 174 Ct. Cl. 1215, 1966 U.S. Ct. Cl. LEXIS 182 (cc 1966).

Opinion

PER CURIAM:

This case was referred to Trial Commissioner Mastín G. White with directions to make findings of fact and recommendation for conclusions of law; The commissioner has done so in an opinion and report filed on November 24, 1965. On December 20, 1965, plaintiffs filed an election to submit the case on the commissioner’s report without exceptions and brief, and on January 3, 1966, defendant filed a statement under Rule 62 (b) and motion that the court adopt the commissioner’s report, including conclusions of fact and law. Since the court agrees with the trial commissioner’s findings, his opinion, and his recommended conclusion of law, as hereinafter set forth, it hereby adopts the same as the basis for its judgment in this case without oral argument. The court therefore concludes that plaintiffs are not entitled to recover and the petition is dismissed. It is further concluded that the defendant is entitled to recover of and from the plaintiff, T. F. Scholes, Inc., on the counterclaims, and judgment is entered for defendant and against the said plaintiff thereon in the sum of $168,059.-22, together with penalties and interest as provided by law on the $146,620.06 involved in the second counterclaim.

Opinion of Commissioner *

Changed Conditions

White, Commissioner: One of the problems before the court in this case is to decide whether the plaintiff T. F. Scholes, Inc., was entitled to an equitable adjustment under the “changed conditions” provision of a contract numbered AF OS^IS)^?. 1 This question has previously been considered by the Armed Services Board of Contract Appeals, which gave a negative answer to the question in a decision dated December 27, 1957 (ASBCA No. 4616).

Contract AF 05(613)-87 was entered into on March 23, 1956, between T. F. Scholes, Inc., and the defendant, represented by a contracting officer of the United States Air Force. It covered 52 items of work that related, in general, to the improvement of the site for the new United States Air Force Academy, located approximately 10 miles north of Colorado Springs, Colorado. The total contract price was $2,373,586.30. (For the sake of convenience, T. F. Scholes, Inc., will usually be referred to hereafter in the opinion as “Scholes,” and contract AF 05(613)-87 will usually be referred to as “the contract.”)

The contract contained the standard “changed conditions” provision that is customarily found in Government construction contracts, under which the contractor was authorized to submit to the contracting officer a claim for an equitable adjustment in the contract price if an increase in the cost of performance was *966 caused by “(1) subsurface or latent physical conditions at the site differing materially from those indicated in this contract, or (2) unknown physical conditions at the site, of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in this contract.” If the contractor was dissatisfied with the contracting officer’s action on such a claim, the contractor was authorized to take an appeal under the “disputes” provision of the contract to the Armed Services Board of Contract Appeals, acting for the Secretary of the Air Force. The “disputes” provision declared that the decision of the Board should, “unless determined by a court of competent jurisdiction to have been fraudulent or capricious or arbitrary or so grossly erroneous as necessarily to imply bad faith, or not supported by substantial evidence, be final and conclusive.”

In soliciting bids for the performance of the proposed contract, the Air Force had listed the numerous items of work that were to be performed, and had set out an estimated quantity of material in connection with each item. Of special significance in connection with this case were Items 6 and 7, as follows:

Prospective bidders were informed that rock excavation would cover the removal and disposition of all boulders measuring % cubic yard or more in volume, as well as rock in ledges and other rock deposits which could not be removed without drilling and blasting, and that common excavation would cover the removal and disposition of “all material not classified as rock, ditch, structural and exclusive of stripping of topsoil.” Hence, boulders and other rocks measuring less than % cubic yard in volume were to be removed and disposed of as part of the common excavation.

Scholes’ bid was 20 cents per cubic yard on the common excavation, and $8 per cubic yard on the rock excavation, and these unit prices were incorporated in the contract for Items 6 and 7, respectively.

Upon receiving the award of the contract, Scholes entered into a subcontract with Paul Hooper, Inc., whereby the latter was to perform the work called for under Items 6 and 7 of the contract.

Paul Hooper, Inc., commenced the excavating operations about the middle of April 1956. In approximately two weeks, the subcontractor began to encounter considerable quantities of rocks in the subsurface at depths that ranged from 5 to 25 feet in different parts of the excavation area. Thereafter, and throughout the remainder of the excavation work, rocks comprised a very substantial percentage of the material excavated at the work site. They were of all sizes, from small rocks up to one boulder that measured approximately 44 cubic yards in volume.

During the course of the performance of the excavation work, the subcontractor encountered, and was required to remove and dispose of, a total of approximately 60,000 cubic yards of so-called “classified rock.” All of this classified rock consisted of large boulders measuring % cubic yard or more in volume. This total quantity of big boulders was, of course, vastly disproportionate to the Government’s estimate of 200 cubic yards of classified rock under Item 7 of the contract. However, no claim was ever submitted to the contracting officer — and no claim is asserted in the present litigation *967 —on the ground that, instead of encountering and having to deal with the estimated quantity of 200 cubic yards of classified rock, Scholes (through the subcontractor) encountered and was compelled to deal with approximately 60,000 cubic yards of big boulders measuring % cubic yard or more in volume. Scholes and the excavation subcontractor were evidently satisfied with the unit price of $8 per cubic yard for the excavation of such boulders, irrespective of the quantity involved.

In addition to the big boulders mentioned in the preceding paragraph, the excavation subcontractor also encountered, and was required to remove and dispose of, a large quantity of boulders and other rocks measuring less than % cubic yard in volume. Such of these rocks as were 6 inches or less in diameter could be handled effectively by the subcontractor’s equipment, and they could be used, and were used, without difficulty as part of the fill on the construction job. However, the rocks that were more than 6 inches in diameter caused the excavation subcontractor great difficulty.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Daewoo Engineering & Construction Co. v. United States
73 Fed. Cl. 547 (Federal Claims, 2006)
Granite Construction Co. v. United States
37 Cont. Cas. Fed. 76,240 (Court of Claims, 1991)
Gardner-Zemke Co. v. State
790 P.2d 1010 (New Mexico Supreme Court, 1990)
J.F. Shea Co. v. United States
31 Cont. Cas. Fed. 71,811 (Court of Claims, 1983)
L.G. Everist, Inc. v. United States
30 Cont. Cas. Fed. 70,356 (Court of Claims, 1982)
United States v. Buiges
524 F. Supp. 1288 (S.D. New York, 1981)
Arundel Corp. v. United States
515 F.2d 1116 (Court of Claims, 1975)
H. N. Bailey & Associates v. The United States
449 F.2d 376 (Court of Claims, 1971)
Maurice Mandel, Inc. v. United States
424 F.2d 1252 (Eighth Circuit, 1970)
J. A. Jones Construction Company v. The United States
390 F.2d 886 (Court of Claims, 1968)
L. M. Jones Co. v. United States
178 Ct. Cl. 636 (Court of Claims, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
357 F.2d 963, 174 Ct. Cl. 1215, 1966 U.S. Ct. Cl. LEXIS 182, Counsel Stack Legal Research, https://law.counselstack.com/opinion/t-f-scholes-inc-and-berks-county-trust-company-v-the-united-states-cc-1966.