L. M. Jones Co. v. United States

178 Ct. Cl. 636, 1967 U.S. Ct. Cl. LEXIS 63, 1967 WL 8856
CourtUnited States Court of Claims
DecidedFebruary 17, 1967
DocketNo. 373-60
StatusPublished
Cited by5 cases

This text of 178 Ct. Cl. 636 (L. M. Jones Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
L. M. Jones Co. v. United States, 178 Ct. Cl. 636, 1967 U.S. Ct. Cl. LEXIS 63, 1967 WL 8856 (cc 1967).

Opinion

Pee Ctjeiam :

This case was referred to Trial Commissioner George Willi, with directions to make recommendation for conclusions of law on plaintiff’s motion and defendant’s cross-motion for summary judgment. The commissioner did so in an opinion and report filed on February [638]*63816, 1966. Plaintiff filed a request for review of the commissioner’s opinion and the case was submitted to the court on the briefs of the parties and on oral argument of counsel. Since the court is in agreement with the opinion and recommendation of the commissioner, with modifications, it hereby adopts the same, as modified, as the basis for its judgment in this case, as hereinafter set forth. Therefore, plaintiff’s motion for summary judgment is denied, defendant’s cross-motion for summary judgment is granted, and plaintiff’s petition is dismissed.

Commissioner Willi’s opinion, as modified by the court, is as follows:

In 1954 the Army Corps of Engineers awarded a contract for the construction of the Table Nock Dam, a very large flood control and hydroelectric project situated on the White River in southwestern Missouri.

From the beginning it was evident that the size of the proposed dam was such that its impoundment of upstream waters would be so extensive as to necessitate the relocation of a number of highway bridges across the White River and certain of its tributaries.

The entire Table Rock project, including both the Dam and the relocation of various upstream bridges, was under the auspices of the Corps of Engineers pursuant to a master plan under which performance of the latter work was to be chronologically integrated with the construction of the Dam.

One of the affected bridges was located east of Blue Eye, Missouri, on Long Creek, a stream that entered White River a short distance above the Table Rock Dam. The replacement bridge was to be located about five miles from the Dam and was within the reservoir to be created by the Dam. This suit, presented for decision on the parties’ cross-motions for summary judgment, arises out of plaintiff’s performance of a Corps of Engineers contract let in 1956 for the construction of the substructure of that bridge.

Under its contract, advertised to bidders on September 24, 1956, and awarded October 31, 1956 (with a completion date of July 15, 1957), plaintiff was to build six reinforced concrete supporting piers across Long Creek plus a bridge abutment at each end. Only two of the piers, Nos. 3 and 4, were [639]*639to be built in the stream bed proper. The remainder were to be put in ascending locations on the banks of the stream with the abutments to be placed at the highest elevations on each side.

Paragraph 7c of the Special Conditions of plaintiff’s contract 1 provided as follows:

Stream data. Hydrographs and rating curves for the White River are available for inspection at the office of the District Engineer, Little Rock District, 300 Broadway, Little Rock, Arkansas. There are no stream flow records on Long Creek. The stream is subject to sharp-crested rises which occur most frequently in the spring. Final closure at Table Rock Dam was made on 9 September 1956 and all river flow is being diverted through the four 4- by 9-foot conduits in the dam which have invert elevations at 722. The conduit capacity is sufficient to pass the flow of White River except during flood periods when water will be temporarily impounded in the reservoir.

The progress schedule for the Dam, approved December 17, 1954, contemplated the commencement of concreting operations on May 1, 1955, and the completion of such operations on May 31, 1958, thirty-seven months later. It was on this projected timetable for work at the Dam that the Corps based the award and completion dates that it utilized in the several contracts, including plaintiff’s, that it later let for the upstream relocation work.

In fact, by October 31, 1956, when the plaintiff’s contract was awarded, work on the Dam was some seven months ahead of the schedule previously described. With the Dam at that stage of completion, the flow of the White River past it was limited to the volume of water that could pass through the four 4x9 foot conduits that had been provided for that purpose near the base of the Dam structure.2 The discharge capacity of these conduits was almost precisely equivalent to the average annual flow rate of the White River over the period 1922 through 1954. Upstream water volumes in [640]*640excess of tbe total discharge capacity of the four conduits were necessarily impounded until such time as the level of those waters exceeded the elevation of the low point in the upper profile of the main structure. Thereafter the excess waters simply spilled over the top of the uncompleted Dam.

Aside from the four conduits mentioned above, the only apertures built into the lower elevations of the Dam were several so-called penstocks or sluiceways whose eventual function it was to conduct regulated quantities of water into the Dam’s turbine chambers for the generation of hydroelectric power. During the period between installation of these openings and final completion of the Dam, they were sealed off by temporarily immovable (so rendered by use of wedges in combination with water pressure) bulkheads that were fashioned from the gates with which the penstocks were to be ultimately equipped for normal operation. The bulkheads were held solidly in place by the downstream pressure of the impounded waters.

The interaction of an unusual but precedented volume of precipitation in the spring of 1957 with the substantially accelerated progress towards completion of the Table Nock Dam created an impoundment of upstream waters so extensive that on April 4, 1957, the plaintiff had to suspend further work on piers 3 and 4 of its contract until September 23, 1957, when the water level receded to a point that permitted resumption. Because of this delay on the piers mentioned, the plaintiff did not complete its contract until December 16, 1957, rather than July 15, 1957, as originally specified.

Despite the problems encountered as to piers 3 and 4, the flooding that the plaintiff experienced did not materially interfere with the prosecution of any of its other work under the contract, because such work was to be performed at elevations above the flood level. Thus, when inundation necessitated the suspension of further work on the uncompleted piers 3 and 4, the plaintiff continued the remaining items of its contract work without interruption and completed them on or about June 17, 1957. It was from then until late September that the plaintiff was totally idled by the flooding.

The plaintiff seasonably requested, and was duly allowed, time extensions covering the entire period between the sched[641]*641uled and actual completion dates of its contract — a period of approximately five and one-half months.

The present litigation stems from the contracting officer’s refusal to authorize any additional compensation on account of the above delay and the subsequent affirmance of that action by the Corps of Engineers Board of Contract Appeals.

No testimony was offered by either party before the Board. The record consisted of the contract papers and a series of documentary exhibits plus a stipulation containing an agreed statement of the single factual issue presented for decision,3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
178 Ct. Cl. 636, 1967 U.S. Ct. Cl. LEXIS 63, 1967 WL 8856, Counsel Stack Legal Research, https://law.counselstack.com/opinion/l-m-jones-co-v-united-states-cc-1967.