Ivy H. Smith Co. v. United States

154 Ct. Cl. 74, 1961 U.S. Ct. Cl. LEXIS 107, 1961 WL 8713
CourtUnited States Court of Claims
DecidedJune 7, 1961
DocketNo. 273-58
StatusPublished
Cited by7 cases

This text of 154 Ct. Cl. 74 (Ivy H. Smith Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ivy H. Smith Co. v. United States, 154 Ct. Cl. 74, 1961 U.S. Ct. Cl. LEXIS 107, 1961 WL 8713 (cc 1961).

Opinion

Jones, Chief Judge,

delivered the opinion of the court:

Plaintiff entered into a contract with the Army Corps of Engineers for the construction of a pumping station in the [76]*76Florida Everglades. The pumping station was part of the Central and Southern Florida Flood Control Project. One of the purposes of the Florida flood control project is to cope with the problems presented by storm and flood in the Lake Okeechobee and Everglades areas of Florida. To allay the heavy annual flood damage characteristic of the Okeechobee-Everglades region, the Congress has appropriated substantial amounts in aid of the Central and Southern Florida Flood Control Project.1 These funds have been used for flood control measures such as the construction of the pumping station, known as Pumping Station No. 9, which is the subject matter of this case.

The plaintiff experienced considerable difficulty and delay in the performance of this contract. As a consequence, the plaintiff says increased costs resulted from excess dewatering costs and delay. In the first count, plaintiff contends the excess dewatering costs claimed, as well as the delays, resulted because the defendant either misrepresented or withheld material facts. In this first count plaintiff also alleges that defendant approved use of a dewatering method that it had concluded would not work. In the second count, plaintiff contends that the excess dewatering costs claimed, as well as the delays, resulted from encountering a “changed condition” under Article 4 of the contract. Finally, the plaintiff seeks remission of liquidated damages assessed on account of delays in completing the work. The plaintiff therefore asks for $604,816.01 for alleged additional costs and also for the amount deducted as liquidated damages of $75,100, making a total of $679,916.01.

We shall first inquire into plaintiff’s allegation in its first count that the defendant did not sufficiently apprise plaintiff of information possessed by defendant. In essence, plaintiff’s claim in this count is this: the plaintiff informed the defendant of its plan to use wellpoints for dewatering the construction site but the defendant, in spite of knowledge that wellpoints would not be effective, remained silent. Moreover the plaintiff asserts that the defendant breached a contractual obligation in approving a dewatering plan submitted [77]*77by plaintiff when the defendant, on the basis of its information, knew that the plan would not work.

To determine the validity of these contentions we must examine the information that had been accumulated by the defendant. Before we can assay the significance of this information, however, a comment is necessary concerning two methods of dewatering in use in Florida at the time of this contract. One method consists of pumping the water out with open pumps or wellpoints. The other method consists of walling off or sealing off the water with a cofferdam, and then pumping from the cofferdam with open pumps to control any influx from below. The plaintiff says the defendant should have insisted on a method of dewatering other than wellpoints in view of the information defendant possessed. What then was the information that had been accumulated by the defendant ? For more than 2 years before asking for bids, the Corps of Engineers had been gathering information regarding subsurface conditions at Pumping Station No. 9.2 Bore holes were drilled. In connection with these, recharge tests were taken, i.e., holes were recharged with water to see how much could be put into a known depth of open hole. The Corps of Engineers, on the basis of these and later recharge tests, concluded that the most economical and practical method of dewatering was by the use of sheet steel cofferdams plus consolidation grouting with pumping from sumps.

The Corps of Engineers decided that the sole use of a wellpoint dewatering system was not feasible in view of the cost of drilling, and the fact that it was estimated the water flowing into the construction area would exceed 100,000 gallons per minute unless some means were used to retard the entry of water into the area.3 The Foundation and Materials Branch of the District Engineer’s office declared on August 24, 1953, that “the conditions indicated by recharge tests in the core borings suggest that unwatering by pumping alone would probably be infeasible.”4 On August 14, 1953, a conference attended by representatives of the Corps of Engineers was held in Jacksonville to discuss [78]*78Pumping Station No. 9, and to approve specifications for its construction. The Chief of the Foundations and Materials Branch told the conference that, on the basis of recharge test and seepage data, it was his opinion that the foundation area would hold 160,000 gallons of water per minute based on open pumping. It was concluded at the conference that cofferdam and foundation grouting should be used to dewater the site, and that by using this method the amount of water to be removed would be reduced to 10,000 gallons per minute. This conclusion of the Corps of Engineers was of course in sharp contrast to the conclusion of plaintiff’s subcontractor, Moretrench, that only up to 30,000 gallons of water per minute would be encountered.

The defendant says it did not reveal its conclusions to bidders largely because of the uncertainty and unreliability of the conclusions. However, the defendant insists that all the facts upon which defendant based its conclusions were made available to plaintiff. Furthermore, the defendant argues that the plaintiff indicated that it was not concerned with the defendant’s view with regard to the most effective method of dewatering but was placing all its trust on its subcontractor, Moretrench. Thus, when plaintiff was questioned about the 30,000 gallons-per-minute figure reached by Moretrench, the plaintiff was unable to show any computation to support that figure.5 The trial commissioner found that the subcontractor’s local manager, Mr. Callender, had a part in reaching the 30,000 gallons-per-minute figure. However, the trial commissioner also found that Mr. Callender did not put much stock in the recharge tests and believed that the defendant had overestimated the amount of water to be encountered.

The pattern of plaintiff’s complete reliance on Moretrench is borne out by other events. When Moretrench presented its dewatering plan which called for the use of wellpoints, defendant’s project engineer became disturbed by the plan, and asked the Chief of Foundations and Materials why there was such a difference between plaintiff’s bid and the defendant’s estimated costs for the dewatering. Defendant’s project engineer then told plaintiff’s superintendent he did [79]*79not believe the contract for Pumping Station No. 9 was a job which, could be dewatered with wellpoints alone. The plaintiff’s superintendent replied that plaintiff had a contract with the Moretrench people and “it was their baby.”6 When the plaintiff asked defendant’s project engineer what should be done, the engineer replied that while he did not disagree that the dewatering could be done with wellpoints, he believed it could be done only in conjunction with steel sheet cofferdams. Plaintiff’s superintendent replied this was a matter to be worked out with Moretrench.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Conner Brothers Construction Co. v. United States
65 Fed. Cl. 657 (Federal Claims, 2005)
Arundel Corp. v. United States
515 F.2d 1116 (Court of Claims, 1975)
Perini Corporation v. United States
381 F.2d 403 (Court of Claims, 1967)
Perini Corp. v. United States
381 F.2d 403 (Court of Claims, 1967)
River Construction Corp. v. United States
159 Ct. Cl. 254 (Court of Claims, 1962)

Cite This Page — Counsel Stack

Bluebook (online)
154 Ct. Cl. 74, 1961 U.S. Ct. Cl. LEXIS 107, 1961 WL 8713, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ivy-h-smith-co-v-united-states-cc-1961.