Gardner-Zemke Co. v. State

790 P.2d 1010, 109 N.M. 729
CourtNew Mexico Supreme Court
DecidedApril 10, 1990
Docket18517
StatusPublished
Cited by50 cases

This text of 790 P.2d 1010 (Gardner-Zemke Co. v. State) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gardner-Zemke Co. v. State, 790 P.2d 1010, 109 N.M. 729 (N.M. 1990).

Opinion

OPINION

BACA, Justice.

This case is before us on an appeal of the grant of defendants-appellees’ motion for summary judgment in an action for breach of contract and negligence. We find that no material issues of fact exist, that summary judgment was appropriately granted, and we affirm the judgment below. FACTS

This case arises out of a construction project to build the Las Cruces Medium Security Facility. Multiple parties are involved: Gardner-Zemke Company (Gardner-Zemke), plaintiff below, which was the prime electrical contractor for the project, sued the State of New Mexico, MorrisonKnudson, the construction manager for the project, W.C. Kruger (Kruger), the architect, and Fox & Associates, Inc. (Fox), the firm that prepared the soil reports.

To secure contractors for the various aspects of the project, the state solicited bids. Included in the bid document package was a soil report, prepared by Fox, describing subsoil conditions at the site. The report consisted of several sections, including a narrative section summarizing the subsoil conditions and a technical section describing the data summarized in the narrative section. The technical section contained graphs detailing blow counts — the amount of feet a 140-pound hammer drove a two-inch sampler after a number of blows — and a legend explaining their significance. Kruger and Morrison-Knudson were contractually bound to prepare bidding documents, and they decided to include the Fox report with the pre-bid documents.

Gardner-Zemke, relying in part on the Fox soil report that it received in the bid package, was the successful bidder for the electrical work. The parties dispute the meaning of the report, but Gardner-Zemke maintains that the report meant to it that the soil consisted primarily of sand. This was relevant to their bid because the electrical work required trenching through the surface. Gardner-Zemke submitted affidavits below indicating that other electrical contractors would interpret the report as it did, relying primarily on the narrative portion and interpreting the term “calcareous sand” to mean sand consisting of limestone, rather than hard subsurface soil. The affidavits also indicate that electrical contractors do not know what “blow count” means, and appellant submits that it was acting reasonably when it relied on the narrative portion of the report rather than the technical sections detailing the blow counts.

Portions of the subsurface soil consisted, however, not of sand but of hard limestone rock and caliche. This was more expensive to trench through than Gardner-Zemke had anticipated, and appellant brought this suit under the contract’s changed conditions clause to recover its excess costs.

The contract contained a clause pertaining to concealed conditions allowing the contract to be equitably adjusted if subsurface conditions differed materially from what the contractor could reasonably expect.

Several issues are raised on appeal. Appellant contends that the trial court failed to interpret the report as would a reasonable contractor, asserting that the proper standard for the trial court to use in reviewing the Fox report is from the perspective of a reasonable electrical contractor interpreting the report. It maintains that the trial court improperly ignored the affidavit evidence presented, which indicated that other electrical contractors would interpret the report as did Gardner-Zemke, and that this disputed interpretation of the report made summary judgment inappropriate. Appellant further contends that the trial court erred by relying on an unpublished opinion of the court of appeals, Mesilla Valley Construction Co. v. Morrison-Knudson Co., No. 9404 (N.M.Ct.App., filed March 3, 1988), a case involving different parties but similar issues and that involved an interpretation of the Fox soil report. Appellant also argues that Morrison-Knudson, Fox, and Kruger all owed a duty to Gardner-Zemke to ensure that the report was accurate, and that exculpatory language in the contract was ineffective to defeat the claim based on the changed conditions clause. The essence of appellant’s argument is that a reasonable electrical contractor, such as itself, would not read the technical information in the report to indicate the presence of limestone rock and would not consider that the technical information was relevant to its bid. It would read the narrative portion to indicate sand, and therefore the meaning to be assigned to the report was an issue of fact, making summary judgment inappropriate.

The various appellees dispute GardnerZemke’s assertions. They all argue that the soil report was unambiguous; that the court applied the proper standard in reviewing the report; that no material issues of fact exist regarding the report — the court properly interpreted the report as a matter of law; and that the court made an independent interpretation of the Fox report and did not rely exclusively on Mesilla Valley. Fox, Kruger, and Morrison-Knudson also contend that each owed no duty to Gardner-Zemke that was breached. Kruger and Morrison-Knudson contend that the contract’s exculpatory provisions effectively preclude Gardner-Zemke’s claims, and Fox contends that certain issues raised by the appellant are not included in the docketing statement and may not be raised on appeal.

We consider the following issues to determine whether summary judgment was appropriate: (1) Whether the court applied the proper standard of review in examining the Fox report; and (2) whether the court properly determined that the report was unambiguous as a matter of law. Our disposition of these issues resolves the dispute, and we do not find it necessary to consider the other issues raised.

Preliminarily, we dispose of Fox’s contention that certain issues raised on appeal were not included in the docketing statement and therefore may not be raised on appeal. In Gallegos v. Citizens Insurance Agency, 108 N.M. 722, 731, 779 P.2d 99, 108 (1989), we determined that for this court the docketing statement, although mandatory to perfect appeals, is not jurisdictional, and we may in our discretion consider error properly preserved below but omitted from the docketing statement.

Summary judgment is appropriate if no genuine issue as to any material fact exists, so that the movant is entitled to judgment as a matter of law. State v. Intigon Indem. Corp., 105 N.M. 611, 612, 735 P.2d 528, 529 (1987); SCRA 1986, 1-056(C). In considering a motion for summary judgment, the trial court must view the pleadings, affidavits, and depositions in the light most favorable to the opposing party. Intigon, 105 N.M. at 612, 735 P.2d at 529. The movant bears the initial burden of demonstrating he is entitled to summary judgment; once the movant makes out a prima facie showing, the burden shifts to the opposing party to show at least a reasonable doubt that a genuine issue exists. Koenig v. Perez, 104 N.M. 664, 666, 726 P.2d 341, 343 (1986). A summary judgment motion is not an opportunity to resolve factual issues, but should be employed to determine whether a factual dispute exists. Pharmaseal Laboratories, Inc. v. Goffe, 90 N.M.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Syed v. Paramount Prince Rehab.
New Mexico Court of Appeals, 2022
La Salle v. County of Otero
New Mexico Court of Appeals, 2021
Wilcox v. GEO Grp. Inc.
New Mexico Court of Appeals, 2021
McGregor v. Platinum Bank
New Mexico Court of Appeals, 2021
Plant v. BNSF Railway Co.
New Mexico Court of Appeals, 2019
Sparta v. Russell
New Mexico Court of Appeals, 2019
Phillip Merillat Corp. v. Elkins
New Mexico Court of Appeals, 2018
Carrillo v. My Way Holdings, LLC
2017 NMCA 24 (New Mexico Court of Appeals, 2016)
Centex/Worthgroup, LLC v. Worthgroup Architects, L.P.
2016 NMCA 013 (New Mexico Court of Appeals, 2015)
Frank v. O'Friel
New Mexico Court of Appeals, 2013
Vives v. VERZINO
2009 NMCA 083 (New Mexico Court of Appeals, 2009)
Beggs v. City of Portales
2009 NMSC 023 (New Mexico Supreme Court, 2009)
In Re Crowder
397 B.R. 544 (Tenth Circuit, 2008)
Seeds v. Lucero
2005 NMCA 67 (New Mexico Court of Appeals, 2005)
Williams v. Stewart
2005 NMCA 061 (New Mexico Court of Appeals, 2005)
Deaton v. Gutierrez
2004 NMCA 043 (New Mexico Court of Appeals, 2003)
Martinez v. Martinez
2004 NMCA 007 (New Mexico Court of Appeals, 2003)
Turner Ex Rel. Manzano Resources v. Bassett
2003 NMCA 136 (New Mexico Court of Appeals, 2003)
Village of Wagon Mound v. Mora Trust
2003 NMCA 035 (New Mexico Court of Appeals, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
790 P.2d 1010, 109 N.M. 729, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gardner-zemke-co-v-state-nm-1990.