Terraseis Trading Limited

CourtArmed Services Board of Contract Appeals
DecidedNovember 19, 2015
DocketASBCA No. 58731, 58732
StatusPublished

This text of Terraseis Trading Limited (Terraseis Trading Limited) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Terraseis Trading Limited, (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Terraseis Trading Limited ) ASBCA Nos. 58731, 58732 ) Under Contract No. W91B4N-12-C-5045 )

APPEARANCE FOR THE APPELLANT: Brian Andrews, Esq. Raleigh, NC

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney Robert B. Neill, Esq. CPT Harry M. Parent, III, JA Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE MCILMAIL

INTRODUCTION

Appellant, Terraseis Trading Limited {Terraseis), and the government contracted for Terraseis to provide seismic data collection and processing in Afghanistan. Terraseis did not meet the data collection delivery date, and the government terminated the contract for cause. Terraseis had also presented to the contracting officer a certified claim for alleged delay costs, which the contracting officer denied. In ASBCA No. 58731, Terraseis appeals from the denial of its monetary claim, contending that the government owes it compensation because it delayed in delivering Terraseis's equipment. In ASBCA No. 58732, Terraseis appeals from the termination of the contract, contending that ( 1) a lack of worksite security excuses its failure to meet the delivery date, and (2) the government waived'the delivery date. Only entitlement is before us. The parties submitted the appeal on the record pursuant to Rule 11.

FINDINGS OF FACT

On 8 August 2012, Terraseis and the Bagram Regional Contracting Center on behalf of the Task Force for Business and Stability Operations (TFBSO) of the Department of Defense (government) entered into Contract No. W91B4N-12-C-5045, in the estimated amount of$9,000,000 for the delivery by Terraseis of seismic data acquisition and other services in Afghanistan (R4, tab 1 at 1-2, 5). The project was designed to support efforts to attract potential investment in the hydrocarbon sector of the Afghan economy (R4, tab 1 at 33). Phase I of contract performance consisted of data collection; Phase II consisted of data processing (R4, tab 1 at 5). In order to perform Phase I, Terraseis would have to survey, then line cut (that is, clear obstructions and level, with bulldozers), then lay out sensors, and, finally, record data (app. supp. R4, tab 274 at 2, ~ 2.5). To record, hydraulic trucks called "vibrators" (also referred to as ''vibes") would vibrate the ground (R4, tab 104 at 1; app. supp. R4, tab 274 at 1-2, ~~ 2.4, 2.5). Terraseis planned to conduct all four activities roughly simultaneously, moving from area to area in a "security bubble," to minimize risk (app. supp. R4, tab 274 at 3, ~ 3.5). Terraseis planned to begin recording five days after beginning topographical survey and line clearance operations (R4, tab 6 at 20-21).

The contract provides that:

Contract performance may require work in dangerous or austere conditions. Except as otherwise provided in the contract, the Contractor accepts the risks associated with required work performance in such operations.

(R4, tab 1 at 14 (252.225-7995(b)(2), CONTRACTOR PERSONNEL PERFORMING IN THE UNITED STA TES CENTRAL COMMAND AREA OF RESPONSIBILITY (DEVIATION 2011-00004) (APR 2011))), and that:

Unless specified elsewhere in the contract, the Contractor is responsible for all logistical and security support required for contractor personnel engaged in this contract.

(Id. at 15 (252.225-7995(c))

In addition, the contract incorporated by reference FAR clause 52.212-4(f), CONTRACT TERMS AND CONDITIONS-COMMERCIAL ITEMS (FEB 2012), which provides that:

The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers.

(R4, tab 1 at 9) The contract also provides:

2 Private security: If any contractor and its subcontractors at all tiers require arming or private security under this contract they shall agree to obey all laws, regulations, orders, and directives applicable to the use of private security personnel in Iraq and Afghanistan.... Contractors will ensure that all employees ... armed under the provisions of this contract, comply with the contents of clause 952.225-0001, Arming Requirements and Procedures for Personal Security Services Contractors and for Requests for Personal Protection.

(R4, tab 1at27-28 (clause 952.225-0015(d), HOST NATION CONTRACTOR AND SUBCONTRACTING REQUIREMENTS (AUG 2011))

During the contract's solicitation period, the government agreed to a proposal by Terraseis that the government provide transportation support to and from the "seismic line" (R4, tab 5 at 1). After contract award, the parties attended a 15 August 2012 kick-off meeting attended by the contracting officer (R4, tab 9 at 1). The minutes of that meeting reflect that the government would arrange for the transportation ofTerraseis's equipment beginning 10 days after the submission of certain "paperwork," after which it would take 5-7 days to drive to Camp Stone, the delivery point (id.). On 23 August 2012, the government submitted that paperwork (R4, tab 10 at 1), making the latest, projected delivery date 9 September 2012, 17 days later. On 28 August 2012, the government received word from its transportation contractor that the equipment would be picked up on 4 September 2012, and that the expected delivery date was 11 September 2012 (R4, tab 11 at 1-2).

By 4 September 2012, Terraseis had contracted with the Afghan government to provide security for the project through a 100-person Afghan Public Protection Force (APPF) (R4, tab 16 at 1). In its 9 July 2012 proposal for the contract, Terraseis proposed that it would contract for an APPF, estimating that 200 APPF guards would be needed "to secure the project area day and night" (R4, tab 6 at 1, 9). Terraseis proposed employing a security bubble consisting of a perimeter of security forces deployed up to 600 meters around its technical crew "to prevent any direct sniper attack on the crew" (id.). Terraseis also proposed patrols to deter ambushes and the planting of improvised explosive devices (IEDs) (id. at 10). 1 On 26 August 2012, Terraseis began interviewing local personnel as candidates for the APPF (R4, tab 11 at 3). By 10 September 2012, Terraseis had interviewed 85 guards (R4, tab 23 at 1). On 9 September 2012, Terraseis and the APPF entered into a contract for guards for the project (id., R4, tab 30 at 1).

1 In its proposal, Terraseis used the term "EID" to refer to "IED" (R4, tab 6 at 10).

3 On 25 September 2012, Terraseis informed the government that it would like to begin surveying and clearing on 27 September 2012 (R4, tab 62 at 1). On 27 September 2012, the government delivered the first ofTerraseis's equipment (see R4, tab 67 at 1). However, Terraseis did not begin surveying and clearing until 4 October 2012, because of a delay through 3 October 2012 in licensing weapons for security personnel (R4, tab 73 at 1, tab 75 at 1; app. supp. R4, tab 477 at 3). Terraseis began the work with 100 APPF personnel, and was able to work for 11 days before coming under attack (see supp. R4, tab 405 at 1636). Then, on 15 October 2012, Terraseis's crew was attacked by small arms and mortar fire, causing it to pull back to its base camp (app. supp. R4, tab 477 at 2-3). 2 In response, Terraseis on 16 October 2012 suspended field operations and turned to training the APPF, an effort that continued through 5 November 2012 (see app. supp. R4, tab 477 at 3). On 18 October 2012, the last ofTerraseis's equipment, including the vibes, was delivered to Camp Stone (R4, tab 104 at 1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Gas & Electric Co. v. United States
536 F.3d 1282 (Federal Circuit, 2008)
General Injectables & Vaccines, Inc. v. Gates
519 F.3d 1360 (Federal Circuit, 2008)
General Injectables & Vaccines, Inc. v. Gates
527 F.3d 1375 (Federal Circuit, 2008)
CLIMATIC RAINWEAR, CO. v. United States
88 F. Supp. 415 (Court of Claims, 1950)

Cite This Page — Counsel Stack

Bluebook (online)
Terraseis Trading Limited, Counsel Stack Legal Research, https://law.counselstack.com/opinion/terraseis-trading-limited-asbca-2015.