Harry Pepper and Associates, Inc.

CourtArmed Services Board of Contract Appeals
DecidedDecember 10, 2020
DocketASBCA No. 62038, 62039, 62040, 62041, 62042
StatusPublished

This text of Harry Pepper and Associates, Inc. (Harry Pepper and Associates, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Harry Pepper and Associates, Inc., (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- ) ) Harry Pepper and Associates, Inc. ) ASBCA Nos. 62038, 62039, 62040 ) 62041, 62042 Under Contract No. NNS14AA30T )

APPEARANCES FOR THE APPELLANT: David W. Mockbee, Esq. D. Wesley Mockbee, Esq. Mockbee Hall & Drake, P. A. Jackson, MS

APPEARANCES FOR THE GOVERNMENT: Scott W. Barber, Esq. NASA Chief Trial Attorney Jeffrey A. Renshaw, Esq. Shannon A. Sharkey, Esq. Trial Attorneys Stennis Space Center, MS

OPINION BY ADMINISTRATIVE JUDGE THRASHER ON THE GOVERNMENT’S MOTION FOR SUMMARY JUDGMENT AND APPELLANT’S CROSS-MOTION FOR PARTIAL SUMMARY JUDGMENT

The National Aeronautics and Space Administration (NASA or government) filed a motion for summary judgment based on Harry Pepper & Associates’ (HPA’s or appellant’s) failure to follow contractual notification procedures for impacts to schedule and cost, which it now claims in these five appeals. NASA’s motion also asserts the affirmative defense of accord and satisfaction as to ASBCA No. 62040 based upon Modification No. 2 to the contract. Appellant cross-moved for partial summary judgment to dismiss this affirmative defense as it applies to ASBCA Nos. 62039 and 62040. Due to NASA having had actual and constructive notice of some claims, and genuine issues of material fact as to the others, we deny the first basis of NASA’s motion. Due to the limited release language in Modification No. 2, we deny NASA’s motion on its second basis and grant appellant’s cross-motion as to the application of the affirmative defense of accord and satisfaction in 62039 and 62040.

STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE MOTIONS

1. NASA awarded Contract No. NNS12AA84B (the contract), a multiple award construction contract to HPA, on August 3, 2012. On January 9, 2014, NASA awarded HPA Task Order NNS14AA30T (TO) for restoration of the B2 Test Stand at the John C. Stennis Space Center, MS, valued at $36,577,459. This involved relocation of the Main Propulsion Test Article (MPTA) Superstructure, reinforcement of Battleship Point, 1 and other tasks. (R4, tab 2 at 94-95) On February 7, 2014, NASA issued HPA a Notice to Proceed, which HPA acknowledged the same day. This document indicated all work was to be completed by March 14, 2015. (R4, tab 3 at 132)

2. Relevant to the government’s motion, the contract included the following four clauses which required HPA to notify the contracting officer (CO) when it encountered circumstances contrary to contractual expectations or for which claims might be submitted (the relevant portions are italicized here):

(1). NFS 1852.242-70, TECHNICAL DIRECTION (SEP 1993) (clause G-2), which reads in pertinent part:

(a). . . . ‘Technical direction’ means a directive to the Contractor that approves approaches, solutions, designs, or refinements; fills in details or otherwise completes the general description of work or documentation items; shifts emphasis among work areas or tasks; or furnishes similar instructions to the Contractor....

(b) The [Contracting Officer Technical Representative] COTR does not have the authority to, and shall not, issue any instruction purporting to be technical direction that --

(1) Constitutes an assignment of additional work outside the statement of work;

(2) Constitutes a change as defined in the changes clause;

(3) Constitutes a basis for any basis for any increase or decrease in the total estimated contract cost, the fixed fee (if any), or; or the time required for contract performance;

(4) Changes any of the expressed terms conditions, or specifications of the contract; or

(5) Interferes with the Contractor’s rights to perform the terms/conditions of the contract.

(d) The Contractor shall proceed promptly with the performance of technical direction duly issued by the COTR

1 The “Battleship” was not an actual battleship, but was a frame used to support a rocket booster to be tested on the B2 Test Stand.

2 in the manner prescribed by this clause and within the COTR’s authority.

If, in the Contractor’s opinion, any instruction or direction by the COTR falls within any of the categories defined in paragraph (b) above, the Contractor shall not proceed but shall notify the Contracting Officer in writing within 5 working days after receiving it and shall request the Contracting Officer to take action as described in this clause. [Emphasis added]

(f) Any action(s) taken by the Contractor in response to any direction given by any person other than the Contracting Officer or the COTR shall be at the Contractor’s risk.

(R4, tab 1 at 23-24)

(2). FAR 52.236-2 – DIFFERING SITE CONDITIONS (APR 1984):

(a) The Contractor shall promptly, and before the conditions are disturbed, give a written notice to the Contracting Officer of --

(1) Subsurface or latent physical conditions at the site which differ materially from those indicated in the contract; or

(2) Unknown physical conditions at the site, or an unusual nature, which differ materially from those ordinarily encountered and generally recognized as inhering in work of the character provided for in the contract.

....

(c) No request by the Contractor for an equitable adjustment to the contract under this clause shall be allowed, unless the Contractor has given the written notice required; provided, that the time prescribed in paragraph (a) of this clause for giving written notice may be extended by the Contracting Officer. [Emphasis added]

(R4, tab 1 at 38)

3 (3). FAR 52.243-4, CHANGES (JUN 2007):

(d) If any change under this clause causes an increase or decrease in the Contractor’s cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any such order, the Contracting Officer shall make an equitable adjustment and modify the contract in writing. However, except for an adjustment based on defective specifications, no adjustment for any change under paragraph (b) of this clause shall be made for any costs incurred more than 20 days before the Contractor gives written notice as required. In the case of defective specifications for which the Government is responsible, the equitable adjustment shall include any increased cost reasonably incurred by the Contractor in attempting to comply with the defective specifications. [Emphasis added]

(R4, tab 1 at 39)

(4). FAR 52.242-14, SUSPENSION OF WORK (APR 1984):

(c) A claim under this clause shall not be allowed-

(1) For any costs incurred more than 20 days before the Contractor shall have notified the Contracting Officer in writing of the act or failure to act involved (but this requirement shall not apply as to a claim resulting from a suspension order); and

(2) Unless the claim, in an amount stated, is asserted in writing as soon as practicable after the termination of the suspension, delay, or interruption, but not later than the date of final payment under the contract.

(R4, tab 1 at 22)

3. Specification 200HF-G013, section 050523, paragraph 1.5.1 states:

Contractor shall perform fabrication/erection inspections as necessary prior to assembly, during assembly, during welding, and after welding to ensure that materials and workmanship meet the requirements of the contract documents. . . . Unacceptable welds shall be immediately

4 repaired and made ready for Government re-inspection at no additional cost to the Government.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Comtrol, Inc. v. United States
294 F.3d 1357 (Federal Circuit, 2002)
Engineered Maintenance Services, Inc. v. United States
55 Fed. Cl. 637 (Federal Claims, 2003)
ACE Constructors, Inc. v. United States
70 Fed. Cl. 253 (Federal Claims, 2006)
Hoel-Steffen Construction Co. v. United States
456 F.2d 760 (Court of Claims, 1972)
Schnip Building Co. v. United States
645 F.2d 950 (Court of Claims, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
Harry Pepper and Associates, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/harry-pepper-and-associates-inc-asbca-2020.