Kellogg Brown & Root Services, Inc.

CourtArmed Services Board of Contract Appeals
DecidedNovember 24, 2021
DocketASBCA No. 62681, 62843, 62844
StatusPublished

This text of Kellogg Brown & Root Services, Inc. (Kellogg Brown & Root Services, Inc.) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Kellogg Brown & Root Services, Inc., (asbca 2021).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Kellogg Brown & Root Services, Inc. ) ASBCA Nos. 62681, 62843, 62844 ) Under Contract No. W912GB-13-C-0011 )

APPEARANCES FOR THE APPELLANT: Daniel J. Kraftson, Esq. Sean M. Howley, Esq. Jonathan J. Straw, Esq. Kraftson Caudle PLC McLean, VA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Paul L. Huhtanen, Esq. Herbert J. Aldridge, Esq. Paul Cheverie, Esq. LuzDanielle O. Bolong, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Europe

OPINION BY ADMINISTRATIVE JUDGE HERZFELD ON THE GOVERNMENT’S MOTION TO DISMISS

Respondent, the United States Army Corps of Engineers asserts that appellant, Kellogg Brown & Root Services, Inc. (KBR), did not timely appeal the agency’s final decisions assessing liquidated damages and recoupment of provisional payments. The Army Corps of Engineers asserts that the government claims were embedded in the contracting officer’s final decision denying KBR’s certified claim and KBR’s timely appeal of that final decision did not properly appeal the government claims within that decision. We disagree. Indeed, KBR timely appealed every document that could be construed as a contracting officer’s final decision on these government claims. For the reasons discussed below, we deny the Army Corps of Engineers’ motion to dismiss and conclude that the letters demanding payment from KBR constituted the government claims and contracting officer’s final decisions.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

In 2009, President Obama mandated that the government have a European missile defense system operational “in the 2015 timeframe” (R4, tab 38). On July 9, 2013, the Army Corps of Engineers and KBR executed Contract No. W912GB-13-C- 0011 (Contract) for a firm, fixed-price amount of $134,211,592 to construct an Aegis Ashore Missile Defense System site on Deveselu Air Base in Deveselu, Romania (R4, tab 3 at 1-2). The Contract and modifications included milestone dates for KBR’s completion of certain tasks by specific dates starting with the first milestone in November 2013 and with project completion to occur in September 2015 (R4, tab 1 at 2-3, tab 65 at 2 (Modification No. A00003)). The Contract also stated that the Army Corps of Engineers would assess liquidated damages if contractor-caused delay resulted in KBR missing the September 2015 completion deadline and three interim milestones (R4, tab 3 at 7; see also tab 3 at 54 (Contract includes Federal Acquisition Regulation (FAR) 52.211-12, LIQUIDATED DAMAGES – CONSTRUCTION (SEP 2000))).

On December 3, 2014, the parties modified the contract to accelerate efforts to complete the project and to increase funding for the contract (R4, tab 75 at 4-7 – Modification No. P00007). The modification – P00007 – advised that new payments based on this funding “[we]re not advance payments” and reminded KBR that “time is of the essence and the Government is not waiving the right to assess liquidated damages” (R4, tab 75 at 2-3). The Army Corps of Engineers stated that the modification was “provisional and contingent upon KBR’s ability to demonstrate excusable delays” but that “the Government will not collect any liquidated damages pending KBR’s substantiation of delays” (R4, tab 75 at 3). After several additional contract modifications, the Army Corps of Engineers added a total of $27 million to the contract funding to assure timely completion of the project (R4, tab 97 at 2 (Modification No. P00023)). KBR substantially completed the project on December 19, 2015 to meet the presidential mandate (consolidated & amended compl. ¶ 73; gov’t answer to appellant’s consolidated & amended compl. ¶ 73).

On May 31, 2016, KBR submitted a request for equitable adjustment to receive compensation of $75,000,900 for impacts and delays to the project (R4, tab 118 at 2). On August 4, 2017, the Army Corps of Engineers denied the request (R4, tab 137).

On March 15, 2019, KBR submitted a certified claim, which requested a 411-day extension of the contract completion date to November 4, 2016 (and commensurate extensions to the interim milestones) and payment of $50,206,830.98 based on the Army Corps of Engineers’ delays and constructive and written changes (including accelerated performance) (R4, tab 2 – KBR’s Certified Claim). KBR claimed it incurred $88.2 million in costs due to the delay, but subtracted $37.9 million in accelerated provisional and other payments made by the Army Corps of Engineers during performance, so sought only $50.2 million in damages (R4, tab 140 at 13).

On July 1, 2020, the contracting officer issued a final decision denying KBR’s entire certified claim, concluding that the delay damages were unrecoverable because KBR had failed to demonstrate any excusable delays (R4, tab 1). The contracting officer acknowledged that KBR’s claim reduced its $88.2 million in damages based on

2 provisional and other payments that the Army Corps of Engineers had already made and, thus, only sought $50.2 million in its certified claim (R4, tab 1 at 1 n.1). The decision informed KBR of its right to appeal the decision to the Board or file an action at the United States Court of Federal Claims (R4, tab 1 at 107-08).

In addition to denying KBR’s claim as failing to demonstrate any excusable delays, the decision also discussed recoupment of the provisional payments and liquidated damages (R4, tab 1). As to the provisional payments, the contracting officer found that KBR had failed to demonstrate any delays were attributable to the government and stated “the $27M in provisional payments made under the modification are subject to recoupment or offset by the Government due to KBR’s failure [to] substantiate . . . excusable delay” (R4, tab 1 at 48). In its conclusion and section denoted as the “decision,” the contracting officer repeated the finding that KBR had “failed to justify excusable delay as required under Modification No. P00007 and in accordance with the terms of that bilateral modification the Government is entitled to recoup or offset the provisional payments for acceleration by modification of the Contract or other measures permitted by the FAR” (R4, tab 1 at 107).

As to liquidated damages, the decision referenced the liquidated damages provisions of the Contract (including modifications), the number of days of delay, and the dollar amount penalty for each day of unexcused delay (R4, tab 1 at 3, 17-18, 32-33). The decision did not provide a dollar figure for the liquidated damages owed based on the Contract and days of delay (see generally R4, tab 1). The contracting officer concluded, “Concerning liquidated damages, the Contractor has not demonstrated entitlement to waiver of liquidated damages under the terms of the Contract in the claim and the Government reserves the right to collect those damages in a future decision” (R4, tab 1 at 107).

On September 24, 2020, KBR filed a combined notice of appeal and complaint with the Board (ASBCA No. 62681). KBR attached a copy of the entire July 1, 2020 contracting officer’s final decision to its filing. KBR stated, “KBR is justly due the amounts sought in its Claim and, as such, KBR hereby appeals the Contracting Officer’s Final Decision.” (Notice of Appeal & compl. at 2) KBR repeated that its claim sought $88,167,545.49, but had reduced it by $37,960,714.51 based on provisional and other payments by the government. (Notice of Appeal & compl. ¶ 79) KBR’s complaint also alleged that the contracting officer’s final decision “asserted, without analysis or support, that KBR is responsible for the delays to the Project. These assertions of performance failures by KBR and its subcontractors in the Decision were made without analytical basis or support.” (Notice of Appeal & compl. ¶ 84)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Cosmic Construction Co. v. The United States
697 F.2d 1389 (Federal Circuit, 1982)
Placeway Construction Corporation v. The United States
920 F.2d 903 (Federal Circuit, 1990)
The Sharman Company, Inc. v. United States
2 F.3d 1564 (Federal Circuit, 1993)
Raytheon Company v. United States
747 F.3d 1341 (Federal Circuit, 2014)
K-Con Building Systems, Inc. v. United States
778 F.3d 1000 (Federal Circuit, 2015)
Sharman Co. v. United States
37 Cont. Cas. Fed. 76,246 (Court of Claims, 1991)
Boeing Co. v. United States
37 Cont. Cas. Fed. 76,276 (Court of Claims, 1992)
Raytheon Co. v. United States
105 Fed. Cl. 236 (Federal Claims, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
Kellogg Brown & Root Services, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/kellogg-brown-root-services-inc-asbca-2021.