Philadelphia Regent Builders, Inc. v. United States

634 F.2d 569, 28 Cont. Cas. Fed. 80,803, 225 Ct. Cl. 234, 1980 U.S. Ct. Cl. LEXIS 340
CourtUnited States Court of Claims
DecidedOctober 22, 1980
DocketNo. 360-79C
StatusPublished
Cited by14 cases

This text of 634 F.2d 569 (Philadelphia Regent Builders, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Philadelphia Regent Builders, Inc. v. United States, 634 F.2d 569, 28 Cont. Cas. Fed. 80,803, 225 Ct. Cl. 234, 1980 U.S. Ct. Cl. LEXIS 340 (cc 1980).

Opinion

BENNETT, Judge,

delivered the opinion of the court:

This Government contract case is before us to review a decision in defendant’s favor by the Veterans Administration Contract Appeals Board, VACAB No. 1179, 79-1BCA ¶ [235]*235have moved for summary judgment. We have read and considered carefully the papers before us, and, without oral argument, grant defendant’s motion, deny plaintiffs motion, and dismiss the petition.1

The essential facts as found by the VACAB and sustained by the record are that plaintiff, Philadelphia Regent Builders (PRB), a minority contractor, was given a subcontract on July 30, 1973, by the Small Business Administration (SBA), pursuant to section 8(a) of the Small Business Act, 15 U.S.C. § 637(a) (1976) (current version at 15 U.S.C. § 637(a) (Supp. Ill 1979). The prime contract, No. V613C-48, dated June 20, 1972, was between the SBA and the Veterans Administration (VA) for roofing repair work at the Veterans Administration Center in Martinsburg, West Virginia. The subcontract provided for a price of $91,862 and a period of 90 days for performance. Plaintiff was to perform all the work. The SBA delegated to the VA the responsibility for administering the subcontract and PRB was to have the right of appeal from decisions of the contracting officer under the disputes clause of the subcontract. Appeals were to be taken to the VACAB. The contract between SBA and the VA also included the following special provision:

It is agreed that the provisions of the "Termination for Convenience”, "Changes”, "Disputes”, "Default”, and "Price Reduction” Clauses which are included in the contract between the SBA and its Contractor shall be invoked in appropriate cases when requested by the Procuring Contracting Officer (PCO). If the SBA does not agree with the Procuring Contractor Officer’s (PCO) request, the case shall be referred to the Secretary2 or his designee for decision.

Work was scheduled to begin October 1, 1973, and did begin sometime in October. PRB initially sub-subcontracted the entire project to Zeus Construction and Painting Company for $65,000. On the night of October 28-29, 1973, [236]*236the area was There was damage to the interior of the building due to leakage through the part of the roof being worked on. The VA determined that the contractor had not properly sealed the roof area and issued plaintiff a collection voucher for the damage in the amount of $26,509.

On November 7, 1973, plaintiff contract with Zeus and requested and received a 90-day extension of time. Plaintiff then engaged Edward Bannister, roofing contractor, to complete the work. Bannister took up the work but ceased after about 5 weeks and thereafter PRB performed the work with its own forces. The work progressed with successive extensions of time being allowed to December 7, 1974, upon PRB’s requests based on delay due to inclement weather. Six progress payments were routinely approved. In September 1974 plaintiff was notified that since the collection voucher and a follow-up inquiry had been ignored, no additional progress payments would be made until the voucher had been paid.

Plaintiffs president, was attempting to resolve the collection voucher matter, but that he was unable to resume work on the project because of the refusal to make further progress payments, because the cost of materials had escalated 30 percent, and because delays had increased certain overhead costs by $14,500.

. The situation was discussed by SBA. The SBA urged that the withheld progress payment be made and, after consultation among VA officials, it was made. However, even after the progress payment was made, no substantial work was done on the project. On December 12, 1974, plaintiff requested $24,623 from SBA, to cover costs so that the contract could be completed, and a 90-day time extension. The extension was granted until March 7, 1975.

On December 16,1974, Mr. Odom, telephoned Mr. Monteleone, the SBA representative involved in the contract, to discuss the situation. Mr. Odom complained that plaintiff was not making any progress. Mr. Monteleone indicated that SBA had no funds with which to assist PRB. The two men discussed the alternatives, includ[237]*237ing a termination for default. Mr. Monteleone agreed that default termination would be the next course of action although he was reluctant to see that happen. He promised to contact plaintiff to see if something could be worked out. Later that day, Mr. Monteleone called Mr. Odom back. He asked if the contract could be terminated for convenience rather than default. Mr. Odom replied that it could not be done because there was no convenience to the Government. Mr. Monteleone then remarked that the bonding company could finish the job when the contractor defaulted. Mr. Odom agreed. Shortly afterwards, VA concluded that it could not supply PRB with any additional funds.

On January 21,1975, Mr. Odom urged plaintiff to resume work, since no recent work had been done and there was leakage in uncompleted areas. Plaintiff requested a 90-day extension of time from March 7, 1975, citing weather conditions, unavailability of materials at quoted prices, and negotiations for a contract price increase as relevant factors. A 30-day extension was granted, and the contractor was notified that further extensions would be considered if work was resumed or evidence was otherwise given that the contract would be completed. The time was later further extended 15 days, and then another 21 days (to May 12, 1975) on the basis of information that the contractor’s surety would bring in another contractor to complete the project. The notice of this final extension stated it was imperative that further physical progress be made before more extensions would be considered and that the contractor would be declared in default in the absence of evidence of intent to proceed.

No work was performed, no evidence of intent to proceed was received, and no extension of time from May 12, 1975, was requested or granted. A final decision terminating the contract for default was issued on June 4,1975.

Our review of the board’s decision is governed by the standards of the Wunderlich Act, 41 U.S.C. §§ 321, 322 (1976). All findings of fact by the board must be upheld unless they are fraudulent, arbitrary, capricious or so grossly erroneous as necessarily to imply bad faith, or not supported by substantial evidence. Koppers Co. v. United States, 186 Ct. Cl. 142, 147, 405 F.2d 554, 557 (1968). [238]*238Furthermore, our rules require a overturn administrative findings of fact must specifically enumerate such findings separately and in numbered paragraphs, and must give reasons why the administrative finding is not entitled to finality along with supporting citations to pertinent parts of the administrative record. Ct. Cl. Rule 163. Plaintiff has not complied with our rules but in any case appears to attack only three findings of fact by the board. These are totally insignificant and immaterial for the purposes of the instant motions.3

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
634 F.2d 569, 28 Cont. Cas. Fed. 80,803, 225 Ct. Cl. 234, 1980 U.S. Ct. Cl. LEXIS 340, Counsel Stack Legal Research, https://law.counselstack.com/opinion/philadelphia-regent-builders-inc-v-united-states-cc-1980.