PROTEC GmbH

CourtArmed Services Board of Contract Appeals
DecidedMay 15, 2019
DocketASBCA No. 61185
StatusPublished

This text of PROTEC GmbH (PROTEC GmbH) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
PROTEC GmbH, (asbca 2019).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) PROTEC GmbH ) ASBCA No. 61185 ) Under Contract No. W912CM-14-P-0008 )

APPEARANCES FOR THE APPELLANT: Paul D. Reinsdorf, Esq. Attorney at Law Frankfurt/Main, Germany

Steven J. Kmieciak, Esq. Seyfarth Shaw LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Raymond M. Saunders, Esq. Army Chief Trial Attorney Dana J. Chase, Esq. Trial Attorney

OPINION BY ADMINISTRATIVE JUDGE SWEET

This appeal involves a contract between the Regional Contracting Office, Wiesbaden (government) and appellant PROTEC GmbH (PROTEC) to maintain and repair equipment at U.S. Army Garrison, Wiesbaden. The government refused to pay some invoices. PROTEC submitted a claim seeking to have the government pay the unpaid invoices. The contracting officer (CO) issued a final decision (COFD) denying that claim, which PROTEC appeals.

The government argues that it properly refused to pay the unpaid invoices because, inter alia, 1 PROTEC submitted electronic reports and invoices late, which prevented the government from verifying that PROTEC properly performed the billed-for services. PROTEC responds that the government suffered no prejudice from the late electronic reports and invoices because timely paper reports, the maintenance schedule, and the contracting officer representative's (COR's) role in arranging emergency repairs allowed the government to verify performance. PROTEC also argues that it submitted the invoices late because of delays receiving signed work certificates from the government and invoices from suppliers.

1 Because we find that PROTEC' s late submission of reports and invoices justified the government's refusal to pay the unpaid invoices, we do not address the government's other proffered reasons for not paying the unpaid invoices. ·The government properly refused to pay the unpaid invoices because PROTEC failed to submit timely electronic reports and invoices. The lack of timely electronic reports and invoices prevented the government from verifying the work because PROTEC did not submit the paper reports on time, follow the maintenance schedule, or arrange all repairs through the COR or the fire inspector. For repairs in particular, timely reports and invoices were necessary to verify the time and material charges. Nor did government work certificate signature delays or supplier invoice delays cause-let alone justify-the late unpaid invoice submissions. Because the government properly refused to pay the unpaid invoices, the appeal is denied.

FINDINGS OF FACT

I. Contract

1. On December 20, 2013, the government awarded Contract No. W912CM-14-D-0008 (0008 Contract) to PROTEC for the maintenance and repair of electronic doors, gates, scanners, sauna compact system and electric/hydraulic barriers, and bollards at U.S. Army Garrison, Wiesbaden (R4, tab 3). The 0008 Contract consisted of two main types of services-preventative maintenance and on-call emergency repairs (id. at 51-53).

2. PROTEC had to submit a maintenance schedule within ten days of contract award (R4, tab 3 at 54).

3. Only the COR or the fire inspector could place an emergency repair call, to which PROTEC had to respond within four hours (R4, tab 3 at 53).

4. The 0008 Contract provided that the government would monitor PROTEC's performance in accordance with a Quality Assurance Surveillance Plan (QASP) (R4, tab 3 at 47). The QASP detailed the surveillance and evaluation of PROTEC's performance (supp. R4, tab 204). Under the QASP, the government would document deficient performance in non-conformance reports (NCRs) (id. at 4-6).

5. The 0008 Contract required PROTEC to submit an electronic on-call emergency report within two days of performing an emergency repair, and an electronic condition report (collectively, reports) within seven days of performing maintenance (R4, tab 3 at 54-55).

6. The 0008 Contract also required PROTEC to "[ s ]ubmit invoices for the previous month's contract services in Wide Area Work Flow (WA WF) for approval by the COR No Later Than (NL T) the 10th working [day] of the next month." By stating that invoices had to be for "the previous month's services," the 0008 Contract required

2 that each invoice be for no more than one month's services. (R4, tab 3 at 30 (emphasis added))

7. The government would pay PROTEC for the maintenance on a fixed-price basis, and for the repairs on a time-and-material basis (R4, tab 3 at 3-25, 47).

II. Contract Administration

A. Maintenance Schedule and Emergency Calls

8. In accordance with Performance Work Statement§ 5.7, PROTEC submitted a proposed maintenance schedule on January 13, 2014, which the government approved (app. supp. R4, tab 11).

9. PROTEC did not follow the maintenance schedule, even before April 2016, 2 as the COR repeatedly informed PROTEC through NCRs (R4, tabs 22-24, 29, 34, 41, 44, 75, 97, 99, 125, 139, 156, 199, 199a; app. supp. R4, tabs 3d, 3s; tr. 1/95, 2/126-28). In particular, at a February 10, 2016 performance meeting, the government faulted PROTEC for not following the maintenance schedule. However, it also noted that the schedule was not logical. 3 Therefore, the parties agreed that PROTEC would submit a revised maintenance schedule (R4, tab 39 at 4; app. supp. R4, tab 343n).

10. Melanie Brill-PROTEC's business manager-testified that PROTEC notified the government weekly what work it would perform. However, she did not testify for how long PROTEC provided those weekly notifications. (Tr. 1/122) As documented in NCR 0016, PROTEC provided weekly schedules for a few weeks, but then stopped (app. supp. R4, tab 3n at 17; tr. 2/206).

11. On April 7, 2016, PROTEC submitted a proposed revised maintenance schedule (R4, tab 55; app. supp. R4, tab 13).

12. On May 2, 2016, the CO informed PROTEC that the proposed revised maintenance schedule was unacceptable. The COR also certified that PROTEC had not performed electrical work on schedule. (R4, tab 73) Indeed, PROTEC never performed the electrical work (tr. 2/111 ).

2 As discussed below, April 2016 is significant because PROTEC claims that the cause of schedule slippage was the government's delay in responding to an April 7, 2016 proposed revised maintenance schedule. 3 The schedule was not logical because it called for maintenance of a climbing wall after the climbing season started (tr. 1/113-14 ).

3 13. On May 7, 2016, PROTEC responded to the CO, explaining that it was unable to perform work according to the schedule due to its employee's injury (app. supp. R4, tab 3n at 11 ).

14. At a May 11, 2016 performance meeting, the government faulted PROTEC for not following the schedule (R4, tab 76 at 2).

15. On May I 7, 2016, PROTEC submitted a second revised proposed maintenance schedule (R4, tab 84 at 1-2). The government did not approve that schedule (tr. 1/131).

16. On June 16, 2016, the CO added a comment to an NCR, indicating that PROTEC still was not adhering to the revised schedule (app. supp. R4, tab 3n at 25).

17. On September 8, 2016, the CO emailed PROTEC to inform it that the COR had observed PROTEC employees performing unscheduled maintenance. PROTEC responded that it had been unable to reach the COR by telephone to schedule the maintenance. The CO responded that PROTEC was not authorized to perform unscheduled maintenance without the COR's prior approval, and an unanswered telephone call did not constitute prior approval. PROTEC agreed not to perform unauthorized maintenance in the future. (R4, tab l 55e)

18. The failure to follow the maintenance schedule prevented the government from verifying that PROTEC had performed the maintenance properly (tr. 2/126-28).

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
PROTEC GmbH, Counsel Stack Legal Research, https://law.counselstack.com/opinion/protec-gmbh-asbca-2019.