Lockheed Martin Aeronautics Company

Armed Services Board of Contract Appeals·Decided June 24, 2021·No. ASBCA No. 62505, 62506·Published

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeals of -- )

)

Lockheed Martin Aeronautics Company ) ASBCA Nos. 62505, 62506 )

Under Contract Nos. FA8615-16-C-6048 )

FA8615-17-C-6045 )

APPEARANCES FOR THE APPELLANT: Stephen J. McBrady, Esq.

Skye Mathieson, Esq. Michelle D. Coleman, Esq. John Nakoneczny, Esq. Crowell & Morning LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq.

Air Force Chief Trial Attorney Caryl A. Potter, Esq. Christopher M. Judge-Hilborn, Esq. Trial Attorneys

MAJORITY OPINION BY ADMINISTRATIVE JUDGE PROUTY

The question presented by these appeals is whether a unilateral contract definitization 1 action by a contracting officer (CO) constitutes a government claim that may be directly appealed to the Board by the contractor (as happened here), or whether it is an act of contract administration, subject to a claim by the contractor, but not a direct appeal. It turns out, we answered this question 33 years ago in Bell Helicopter Textron, ASBCA No. 35950, 88-2 BCA ¶ 20,656, aff’d on mot. for recon., 88-3 BCA ¶ 21,048. In that case, we held that such a unilateral contract definitization is not a government claim and that, to obtain relief, the contractor must first file a claim with the CO and then appeal to us if it is dissatisfied with the results. Appellant here, Lockheed Martin Aeronautics Company (LM), is well aware of Bell Helicopter, but appealed the unilateral definitization directly to us anyway, arguing that Bell Helicopter has been effectively, if not expressly, overruled in the years since its issue. Judge Clarke, in dissent, agrees with LM.

Though we certainly agree that the definition of “claim” and the universe of actions subject to a claim has grown more liberal since the issuance of Bell Helicopter,

1 Contract definitization is the setting of a final price for a contract that was awarded without a set price.

see, e.g., Todd Constr. v. United States, 656 F.3d 1306, 1311-12 (Fed. Cir. 2011), we respectfully disagree with Judge Clarke’s conclusion that it has changed so much as to effectively overrule that decision. That being the case, we must follow our prior precedent, see SWR, Inc., ASBCA No. 56708, 15-1 BCA ¶ 35,832 at 175,220, and continue to hold that a unilateral contract definitization does not constitute a government claim and may not be directly appealed to us. The government motion to dismiss on these grounds is granted.

STATEMENT OF FACTS FOR THE PURPOSES OF THE MOTION

Strictly speaking, the motion before us is a motion to dismiss for lack of jurisdiction. The government submitted with its motion a statement of undisputed material facts, in the style of a motion for summary judgment. Those proposed facts – at least those which we find material to our decision today – may be gleaned almost completely from LM’s complaint in this action.2 The salient ones are below.

These appeals involve two contracts in which the Air Force contracted with LM to upgrade F-16 fighter aircraft on behalf of two different foreign governments pursuant to the Foreign Military Sales program. Contract No. FA8615-16-C-6048 (the Singapore contract) was entered in December 2015 and was for the purpose of upgrading the avionics of F-16s owned by Singapore. Contract No. FA8615-17-C-6045 (the Korea contract) was entered into in November 2016. (See compl. ¶¶ 1-2).

Each contract was an undefinitized contract action (UCA), meaning that the contract was awarded before the final price was set (see compl. ¶ 2). In each case, LM was entitled to charge the government for the costs that it incurred as it performed the contract until it was definitized (see compl. ¶ 3). Each contract also included a “not to exceed” (NTE) amount, which limited the costs that LM could incur before the contract price was definitized (see compl. ¶ 17 (Singapore contract); ¶ 19 (Korea contract)).

The contract provisions governing definitization came from different sources for each contract, though they were identical for our purposes. The relevant provision for the Singapore contract came from the Federal Acquisition Regulation (FAR) 52.216-25(c); the provision for the Korea contract came from the Department of Defense Supplement to the Federal Acquisition Regulation (DFARS) 252.217-7027(c). (See compl. ¶ 5). Each

2 In a motion to dismiss for lack of jurisdiction, well-pleaded facts in the complaint are generally treated as true unless controverted. See, e.g., Reynolds v. Army and Air Force Exch. Svs., 846 F.2d 746, 747 (Fed. Cir. 1988).

provided that, in the event the parties were unable to come to agreement upon the definitized price within the time set by the contract:

the Contracting Officer may, with the approval of the head of the contracting activity, determine a reasonable price or fee in accordance with subpart 15.4 and part 31 of the FAR, subject to Contractor appeal as provided in the Disputes clause. In any event, the Contractor shall proceed with completion of the contract, subject only to the Limitation of Government Liability clause.

See compl. ¶ 10 (citing FAR 52.216-25(c); DFARS 252.217-7027(c)).

And, speaking of the Disputes clause, each contract included the same Disputes clause, FAR 52.233-1, DISPUTES (MAY 2014) ALTERNATE I (DEC 1991)) (see compl. ¶ 11; R4, tab 1 at 47 (Singapore contract); R4, tab 7 at 42 (Korea contract)).

LM submitted proposals for definitization of the contracts in a timely manner and included cost data to support its proposals (see compl. ¶¶ 20-43 (Singapore contract); ¶¶ 47-65 (Korea contract)). Nevertheless, after a period of several years, the parties were unable to come to agreement upon the contract prices and, on February 12, 2020, the CO issued contract modifications to unilaterally set the price for each contract. In the case of the Singapore contract, Modification No. PZ0010 unilaterally definitized the total project price at $1,008,584,243 (see comp. ¶ 44). In the case of the Korea contract, Modification No. PZ0012 unilaterally definitized the total project price at $970,462,643 (see compl. ¶ 66).

LM did not file a claim with the CO challenging these definitization actions.

Instead, on May 8, 2020, LM filed Notices of Appeal of each definitization action with the ASBCA, stating that it was appealing directly from the government’s two unilateral modifications. (See compl. ¶ 12). At the time of its submission of the appeals, LM asserts, both contracts had over a year of performance remaining and in neither contract had LM’s costs exceeded the unilaterally definititzed price set by the CO (see compl. ¶ 9).

The appeals have since been consolidated.

DECISION

I. Bell Helicopter is Dispositive (if it Remains Good Law)

As noted above, the government has moved to dismiss these appeals upon the ground that LM has not filed claims with the CO challenging the two definitization actions at issue. Without a decision upon claims to appeal, of course, there is no

jurisdiction under the Contract Disputes Act (CDA), 41 U.S.C. §§ 7101-7109. Islands Mechanical Contractor, Inc., ASBCA No. 59655, 17-1 BCA ¶ 36,721 at 178,809.

LM recognizes the need for a CO final decision for Board jurisdiction, but argues that it has that in the CO’s definitization decision, which LM asserts is a government claim against the contractor which may be directly appealed (see app. opp’n at 15-16 (citing Garrett v. Gen. Elec. Co., 987 F.2d 747, 749-50 (Fed. Cir. 1993))). Unfortunately for LM, that argument was rejected by the Board in Bell Helicopter, where we held that a “contracting officer’s decision [that] did no more than establish the contract price in accordance with [the terms of the contract] did not amount to a government claim.” 88-2 BCA ¶ 20,656 at 104,392. The CO’s decisions challenged here, likewise, established the contract price in accordance with the contracts’ terms, and are thus not government claims – so long as Bell Helicopter remains binding.

II. Bell Helicopter Remains Good Law

Free access — add to your briefcase to read the full text and ask questions with AI

Lockheed Martin Aeronautics Company, (asbca 2021).

Lockheed Martin Aeronautics Company (Lockheed Martin Aeronautics Company) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related