Zafer Construction Company v. United States

40 F.4th 1365
CourtCourt of Appeals for the Federal Circuit
DecidedJuly 18, 2022
Docket21-1547
StatusPublished
Cited by6 cases

This text of 40 F.4th 1365 (Zafer Construction Company v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Federal Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Zafer Construction Company v. United States, 40 F.4th 1365 (Fed. Cir. 2022).

Opinion

Case: 21-1547 Document: 65 Page: 1 Filed: 07/18/2022

United States Court of Appeals for the Federal Circuit ______________________

ZAFER CONSTRUCTION COMPANY, AKA ZAFER TAAHHUT INSAAT VE TICARET A.S., Plaintiff-Appellant

v.

UNITED STATES, Defendant-Appellee ______________________

2021-1547 ______________________

Appeal from the United States Court of Federal Claims in No. 1:19-cv-00673-EGB, Senior Judge Eric G. Bruggink. ______________________

Decided: July 18, 2022 ______________________

ABRAHAM GDANSKI, Gdanski Law PC, Teaneck, NJ, ar- gued for plaintiff-appellant. Also represented by SAM GDANSKI.

ROBERT R. KIEPURA, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, argued for defendant-appellee. Also rep- resented by BRIAN M. BOYNTON, STEVEN JOHN GILLINGHAM, MARTIN F. HOCKEY, JR. ______________________

Before NEWMAN, REYNA, and HUGHES, Circuit Judges. Case: 21-1547 Document: 65 Page: 2 Filed: 07/18/2022

HUGHES, Circuit Judge. Zafer Construction Company appeals a decision of the United States Court of Federal Claims dismissing Zafer’s complaint for failing to state a cause of action under Court of Federal Claims Rule 12(b)(6). The Court of Federal Claims determined that Zafer’s request for equitable ad- justment is not a claim under the Contract Disputes Act and that Zafer’s subsequent claim is time barred. Because Zafer’s request for equitable adjustment is a claim, we re- verse and remand. I In June 2008, the United States and Zafer agreed to a $40 million contract to design and build water systems on the Bagram Air Base in Afghanistan. Zafer completed the project and submitted a request for equitable adjustment on September 10, 2013, which it timely amended on De- cember 17, 2014. In its 167-page request, Zafer alleged that the government increased the cost of the project by causing delays and modifying the contract. Zafer’s detailed request sought $6.7 million and provided a breakdown of the rea- sons for the claimed amounts. Zafer submitted its request “so that the parties c[ould] engage in immediate discus- sions and negotiations to mutually amicably resolve [its] request.” Appx46 (request for equitable adjustment). And Zafer certified its request in accordance with the claim-cer- tification requirement of 41 U.S.C. § 7103(b)(1), going be- yond what is required by 48 C.F.R. § 252.243-7002(b) to certify mere requests for equitable adjustment. The parties negotiated for four-and-a-half years but did not fully resolve Zafer’s request. On February 7, 2018, Zafer asked to convert its request for equitable adjustment into a claim. The contracting officer reviewed Zafer’s claim and determined that most of it is time barred under 41 U.S.C. § 7103(a)(4)(A) because much of the govern- ment’s alleged conduct had transpired more than six years before Zafer had converted its request into a claim. Case: 21-1547 Document: 65 Page: 3 Filed: 07/18/2022

ZAFER CONSTRUCTION COMPANY v. US 3

Zafer sued in the Court of Federal Claims. The Court of Federal Claims found that Zafer’s claim had “accrued no later than August 1, 2011,” meaning Zafer had to have sub- mitted a claim by August 1, 2017 for the claim to be timely. Appx10. Although Zafer had submitted a request for equi- table adjustment in December 2014, the court determined that because this document “lacks a request for a final de- cision” and “asks for negotiations,” it is not a claim but a request for negotiations. Appx9–10. And because Zafer con- verted its request for equitable adjustment into a “proper” claim after the 2017 deadline, the court dismissed Zafer’s complaint for failure to state a cause of action upon which relief can be granted under the court’s Rule 12(b)(6). Appx10–11. Zafer appeals. We have jurisdiction under 28 U.S.C. § 1295(a)(3). II We review decisions to dismiss complaints under Rule 12(b)(6) de novo. Dehne v. United States, 970 F.2d 890, 892 (Fed. Cir. 1992). A The Federal Acquisition Regulation defines “claim” as a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjust- ment or interpretation of contract terms, or other relief arising under or relating to this contract. 48 C.F.R. § 52.233-1(c); see Todd Constr., L.P. v. United States, 656 F.3d 1306, 1311 (Fed. Cir. 2011) (“[T]he defini- tion of the term ‘claim’ in the FAR governs” the use of that term in the Contract Disputes Act.). The regulation further distinguishes claims from “routine request[s] for payment,” like vouchers or invoices. 48 C.F.R. § 52.233-1(c). Case: 21-1547 Document: 65 Page: 4 Filed: 07/18/2022

Under the Contract Disputes Act, if a contractor’s claim is for more than $100,000, the contractor must certify that (A) the claim is made in good faith; (B) the supporting data are accurate and complete to the best of the contractor’s knowledge and belief; (C) the amount requested accurately reflects the contract adjustment for which the contractor believes the Federal Government is liable; and (D) the certifier is authorized to certify the claim on behalf of the contractor. 41 U.S.C. § 7103(b)(1); see 48 C.F.R. § 52.233-1(d)(2)(iii). Requests for equitable adjustment, on the other hand, re- quire certification of only (A) and (B). 48 C.F.R. § 252.243- 7002(b). In addition to these requirements, a contractor must show that “what the contractor desires by its submissions is a final decision” from the contracting officer determining whether the contractor is entitled to the claimed amount. M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323, 1327–28 (Fed. Cir. 2010). We have derived this “re- quest” requirement from 41 U.S.C. § 7103(a)(1) and 48 C.F.R. § 33.206(a), which instruct contractors to submit claims “to the contracting officer for a decision.” See James M. Ellett Constr. Co. v. United States, 93 F.3d 1537, 1543 & n.4 (Fed. Cir. 1996) (emphasis added); Transamerica Ins. Corp. v. United States, 973 F.2d 1572, 1576 (Fed. Cir. 1992). To fulfill the request requirement, the contractor’s re- quest for a final decision can be either explicit or implicit. Transamerica, 973 F.2d at 1576. The claim does not need to “be submitted in any particular form or use any particu- lar wording.” Cont.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Al Ghanim Combined Group W.L.L.
Armed Services Board of Contract Appeals, 2026
Mindseeker, Inc.
Armed Services Board of Contract Appeals, 2024
Red Bobtail Transportation
Armed Services Board of Contract Appeals, 2024
AeroKool Aviation Corp.
Armed Services Board of Contract Appeals, 2023
Heart & Core LLC
Armed Services Board of Contract Appeals, 2023

Cite This Page — Counsel Stack

Bluebook (online)
40 F.4th 1365, Counsel Stack Legal Research, https://law.counselstack.com/opinion/zafer-construction-company-v-united-states-cafc-2022.