Zafer Construction Company v. United States

40 F.4th 1365
Court of Appeals for the Federal Circuit·Decided July 18, 2022·No. 21-1547·Published·Cited by 6 cases

Opinion

United States Court of Appeals for the Federal Circuit

ZAFER CONSTRUCTION COMPANY, AKA ZAFER TAAHHUT INSAAT VE TICARET A.S., Plaintiff-Appellant

v.

UNITED STATES, Defendant-Appellee

2021-1547

Appeal from the United States Court of Federal Claims in No. 1:19-cv-00673-EGB, Senior Judge Eric G. Bruggink.

Decided: July 18, 2022

ABRAHAM GDANSKI, Gdanski Law PC, Teaneck, NJ, argued for plaintiff-appellant. Also represented by SAM GDANSKI.

ROBERT R. KIEPURA, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, DC, argued for defendant-appellee. Also represented by BRIAN M. BOYNTON, STEVEN JOHN GILLINGHAM, MARTIN F. HOCKEY, JR.

Before NEWMAN, REYNA, and HUGHES, Circuit Judges.

2 ZAFER CONSTRUCTION COMPANY v. US

HUGHES, Circuit Judge.

Zafer Construction Company appeals a decision of the United States Court of Federal Claims dismissing Zafer’s complaint for failing to state a cause of action under Court of Federal Claims Rule 12(b)(6). The Court of Federal Claims determined that Zafer’s request for equitable adjustment is not a claim under the Contract Disputes Act and that Zafer’s subsequent claim is time barred. Because Zafer’s request for equitable adjustment is a claim, we reverse and remand.

I

In June 2008, the United States and Zafer agreed to a $40 million contract to design and build water systems on the Bagram Air Base in Afghanistan. Zafer completed the project and submitted a request for equitable adjustment on September 10, 2013, which it timely amended on December 17, 2014. In its 167-page request, Zafer alleged that the government increased the cost of the project by causing delays and modifying the contract. Zafer’s detailed request sought $6.7 million and provided a breakdown of the reasons for the claimed amounts. Zafer submitted its request “so that the parties c[ould] engage in immediate discussions and negotiations to mutually amicably resolve [its] request.” Appx46 (request for equitable adjustment). And Zafer certified its request in accordance with the claim-certification requirement of 41 U.S.C. § 7103(b)(1), going beyond what is required by 48 C.F.R. § 252.243-7002(b) to certify mere requests for equitable adjustment.

The parties negotiated for four-and-a-half years but did not fully resolve Zafer’s request. On February 7, 2018, Zafer asked to convert its request for equitable adjustment into a claim. The contracting officer reviewed Zafer’s claim and determined that most of it is time barred under 41 U.S.C. § 7103(a)(4)(A) because much of the government ’s alleged conduct had transpired more than six years before Zafer had converted its request into a claim.

ZAFER CONSTRUCTION COMPANY v. US 3

Zafer sued in the Court of Federal Claims. The Court of Federal Claims found that Zafer’s claim had “accrued no later than August 1, 2011,” meaning Zafer had to have submitted a claim by August 1, 2017 for the claim to be timely. Appx10. Although Zafer had submitted a request for equitable adjustment in December 2014, the court determined that because this document “lacks a request for a final decision ” and “asks for negotiations,” it is not a claim but a request for negotiations. Appx9–10. And because Zafer converted its request for equitable adjustment into a “proper” claim after the 2017 deadline, the court dismissed Zafer’s complaint for failure to state a cause of action upon which relief can be granted under the court’s Rule 12(b)(6). Appx10–11.

Zafer appeals. We have jurisdiction under 28 U.S.C.

§ 1295(a)(3).

II

We review decisions to dismiss complaints under Rule 12(b)(6) de novo. Dehne v. United States, 970 F.2d 890, 892 (Fed. Cir. 1992).

A

The Federal Acquisition Regulation defines “claim” as a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to this contract. 48 C.F.R. § 52.233-1(c); see Todd Constr., L.P. v. United States, 656 F.3d 1306, 1311 (Fed. Cir. 2011) (“[T]he definition of the term ‘claim’ in the FAR governs” the use of that term in the Contract Disputes Act.). The regulation further distinguishes claims from “routine request[s] for payment,” like vouchers or invoices. 48 C.F.R. § 52.233-1(c).

4 ZAFER CONSTRUCTION COMPANY v. US

Under the Contract Disputes Act, if a contractor’s claim is for more than $100,000, the contractor must certify that (A) the claim is made in good faith; (B) the supporting data are accurate and complete to the best of the contractor’s knowledge and belief;

(C) the amount requested accurately reflects the contract adjustment for which the contractor believes the Federal Government is liable; and (D) the certifier is authorized to certify the claim on behalf of the contractor.

41 U.S.C. § 7103(b)(1); see 48 C.F.R. § 52.233-1(d)(2)(iii). Requests for equitable adjustment, on the other hand, require certification of only (A) and (B). 48 C.F.R. § 252.243- 7002(b).

In addition to these requirements, a contractor must show that “what the contractor desires by its submissions is a final decision” from the contracting officer determining whether the contractor is entitled to the claimed amount. M. Maropakis Carpentry, Inc. v. United States, 609 F.3d 1323, 1327–28 (Fed. Cir. 2010). We have derived this “request ” requirement from 41 U.S.C. § 7103(a)(1) and 48 C.F.R. § 33.206(a), which instruct contractors to submit claims “to the contracting officer for a decision.” See James M. Ellett Constr. Co. v. United States, 93 F.3d 1537, 1543 & n.4 (Fed. Cir. 1996) (emphasis added); Transamerica Ins. Corp. v. United States, 973 F.2d 1572, 1576 (Fed. Cir. 1992).

To fulfill the request requirement, the contractor’s request for a final decision can be either explicit or implicit. Transamerica, 973 F.2d at 1576. The claim does not need to “be submitted in any particular form or use any particular wording.” Cont. Cleaning Maint., Inc. v. United States,

ZAFER CONSTRUCTION COMPANY v. US 5

811 F.2d 586, 592 (Fed. Cir. 1987). For example, a request for equitable adjustment can constitute a claim. Hejran Hejrat Co. v. U.S. Army Corps of Eng’rs, 930 F.3d 1354, 1357 (Fed. Cir. 2019). And “[t]here is no necessary inconsistency between” a claim and “an expressed desire to continue to mutually work toward a claim’s resolution.” Reflectone, Inc. v. Dalton, 60 F.3d 1572, 1583 (Fed. Cir. 1995).

B

The parties appear to agree that Zafer’s December 2014 request for equitable adjustment satisfies the definition of a “claim” in 48 C.F.R. § 52.233-1(c) and the claimcertification requirement. See Appellee’s Br. 8–10 (identifying but not disputing these requirements). At issue is whether Zafer satisfied the request requirement.

Zafer argues that its December 2014 request for equitable adjustment fulfills the request requirement because the document at length discusses Zafer’s request for money owed, showing that Zafer intended for the contracting officer to make a decision regarding entitlement. Zafer contends that the Court of Federal Claims’ contrary conclusion relies on a “hyper-technical analysis” that Zafer asserts we have previously rejected. Appellant’s Br. 8.

The government responds that Zafer “sent clear signals ” that it intended only to negotiate a contract proposal, not to request a final decision. Appellee’s Br. 10. In the government ’s view, Zafer knew the difference between a request for equitable adjustment and a claim because Zafer submitted a proper, but untimely, claim in December 2018.

C

The parties suggest that the request requirement focuses on a contractor’s subjective intent. See Appellant’s Br. 11 (arguing that the length of the request for equitable adjustment evinces Zafer’s “intent for the contracting officer [to] make a decision for entitlement”); Appellee’s Br.

6 ZAFER CONSTRUCTION COMPANY v. US

Free access — add to your briefcase to read the full text and ask questions with AI

Zafer Construction Company v. United States, 40 F.4th 1365 (Fed. Cir. 2022).

40 F.4th 1365 (Zafer Construction Company v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Al Ghanim Combined Group W.L.L.
Armed Services Board of Contract Appeals, 2026
Mindseeker, Inc.
Armed Services Board of Contract Appeals, 2024
Red Bobtail Transportation
Armed Services Board of Contract Appeals, 2024
AeroKool Aviation Corp.
Armed Services Board of Contract Appeals, 2023
Heart & Core LLC
Armed Services Board of Contract Appeals, 2023