Midatlantic Construction & Design Associates, Inc. v. United States

CourtUnited States Court of Federal Claims
DecidedMay 5, 2023
Docket22-447
StatusUnpublished

This text of Midatlantic Construction & Design Associates, Inc. v. United States (Midatlantic Construction & Design Associates, Inc. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Midatlantic Construction & Design Associates, Inc. v. United States, (uscfc 2023).

Opinion

In the United States Court of Federal Claims NOT FOR PUBLICATION

No. 22-447C (Filed: May 5, 2023)

) MIDATLANTIC CONSTRUCTION ) & DESIGN ASSOCIATES, INC., ) ) Plaintiff, ) ) v. ) ) UNITED STATES, ) ) Defendant. )

Ruth E. Ganister, Rosenthal and Ganister, LLC, West Chester, PA, for plaintiff.

Robert C. Bigler, Trial Attorney, Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington, DC, for defendant, with whom on the briefs were Brian M. Boynton, Principal Deputy Assistant Attorney General, and Patricia M. McCarthy, Director, and Elizabeth M. Hosford, Assistant Director, Commercial Litigation Branch, Civil Division, U.S. Department of Justice, Washington, DC.

OPINION AND ORDER1

BONILLA, Judge.

Pending before the Court is Defendant’s Motion to Dismiss for lack of subject matter jurisdiction pursuant to RCFC 12(b)(1) (ECF 6). The crux of the government’s motion is that plaintiff failed to timely submit a duly certified claim to the contracting officer under the Contract Disputes Act (CDA), 41 U.S.C. § 7103. Noticeably absent from both parties’ briefs is a citation to–let alone any discussion of–Sikorsky Aircraft Corp. v. United States, 773 F.3d 1315 (Fed. Cir. 2014), wherein the United States Court of Appeals for the Federal Circuit squarely held: “§ 7103

1This case was transferred to the undersigned for adjudication on March 1, 2023, pursuant to Rule 40.1(b) of the Rules of the United States Court of Federal Claims (RCFC). is not jurisdictional and need not be addressed before deciding the merits.” Id. at 1322. For the reasons set forth below, defendant’s motion is DENIED.

BACKGROUND

On September 21, 2012, the U.S. Department of Defense, Defense Logistics Agency (DLA) awarded Midatlantic Construction & Design Associates, Inc. (MCDA) a nearly $3 million firm fixed-price construction contract to repair and upgrade fire sprinkler systems in 38 government facilities located in New Cumberland and Mechanicsburg, Pennsylvania.2 The scheduled contract performance period was October 2, 2012, through September 30, 2013 (i.e., Fiscal Year 2013). Due to contested delays (e.g., building access and accessibility, stop work orders, response time for requests for information and change orders, inspections, differing site conditions, availability of government personnel, weather conditions, government furlough, subcontractor demobilization and remobilization) and disputed contract requirements (e.g., delivery and format of construction and maintenance drawings), performance continued through February 10, 2015.

Two years later, on May 8, 2017, MCDA submitted a request for equitable adjustment (REA) in the amount of $405,929.21 for “unabsorbed corporate overhead costs incurred as a result of the changes and delays experienced under [the DLA] contract.”3 See ECF 1-2 at 25.4 The contractor specifically noted that the request did not include $108,180.93 in “jobsite unabsorbed overhead costs” purportedly incurred and “not recovered through the various modifications to the contract.” See id. In closing, the REA states:

We are willing to discuss this request for equitable adjustment with you, and we are willing to meet with you concerning the same. We are submitting this request as a Request for Equitable Adjustment (REA). It is our understanding that your agency is willing to review and resolve this matter with MCDA on that basis. However, we reserve the right to present this request as a formal claim pursuant to the

2The record presented indicates the small business set aside contract ultimately involved work in 41 DLA buildings.

3Although dated May 8, 2017, MCDA’s REA was reportedly received by DLA on May 17, 2017. In their exchange of correspondence, the parties refer to the REA based upon the date submitted and date received, respectively. For clarity, and consistent with the parties’ briefs, the Court adopts the document date and cites the document as the “May 8, 2017 REA.”

4MCDA appended a series of documents to its complaint as well as its response to defendant’s motion to dismiss. In ruling upon a motion to dismiss under RCFC 12(b)(1), the Court may consider matters outside the complaint. See Alisud-Gesac Handling-Servisair 2 Scarl v. United States, 161 Fed. Cl. 655, 662 (2022) (citing Cedars-Sinai Med. Ctr. v. Watkins, 11 F.3d 1573, 1584 (Fed. Cir. 1993)), appeal docketed, No. 23-1087 (Fed. Cir. filed Oct. 27, 2022).

2 Contract Disputes Act. We would appreciate your early review of this matter.

As noted, should we receive any claims from vendors and subcontractors concerning this job, we reserve the right to amend this REA to include the same. We also reserve the right to amend this REA to include jobsite unabsorbed overhead as appropriate.

We will contact you to set a time to discuss this matter with you further.

Id. at 36. The REA does not include a certification or any representations regarding the nature and accuracy of the information included or the identity or authorization of the author.

Over the next four years, MCDA engaged DLA and the Defense Contract Audit Agency (DCAA) in intermittent communications regarding the sufficiency of MCDA’s supporting documentation, the allowability of certain costs, and the REA’s missing certification. See, e.g., ECF 1-2 at 40–41, 43–44, 46–47, 49, 51–53, 55–56, 61; ECF 1-3 at 2–8, 10–11, 13–14, 16–17; see also ECF 1-5 at 3–5 (“Timeline of Correspondence”). In the interim, on November 2, 2018, MCDA met with DLA and DCAA officials, at which time the contracting officer recommended MCDA engage professional assistance to substantiate the REA. See ECF 1 ¶ 30; ECF 8 at 48–49 ¶ 9. Two years and two months later, on January 8, 2021, MCDA requested the opportunity to submit a revised REA. See ECF 1-3 at 16. DLA authorized MCDA’s request and then twice extended the submission deadline to March 1, 2021. See ECF 1-3 at 19, 21–22.

On March 1, 2021, MCDA submitted a revised REA seeking to recover $855,038 in alleged unforeseen increases in labor, equipment, and overhead costs attributable to government (in)actions and delays. See ECF 1-4. The revised REA more than doubled MCDA’s initial request of $405,929.21 and presents different valuations and calculations. Signed by MCDA’s President, the revised REA includes the following certification: “I certify that the request is made in good faith, and that the supporting data are accurate and complete to the best of my knowledge and belief.” Id. at 16. The revised REA does not formally request a contracting officer’s final decision.

The DLA contracting officer rejected MCDA’s submission on March 22, 2021, explaining that MCDA changed its theory of recovery without providing the documentary proof necessary to substantiate the requested equitable adjustment. See ECF 1-5 at 2–5. After outlining the protracted effort to resolve MCDA’s May 8, 2017 REA, the contracting officer closed, stating:

3 . . . both DLA and DCAA exerted a considerable amount of time and effort assisting MCDA in submitting an adequate REA proposal. From the outset of this effort, however, MCDA failed to reciprocate in its efforts to provide substantiating documentation to support its REA. At this point, and given that MCDA abandoned its REA for over two years and then provided no new information to support its revised REA, DLA believes that any further discussion concerning this matter is no longer fruitful. Accordingly, DLA has concluded its review of this matter.

Id. at 5.

On April 1, 2021, MCDA requested that DLA reconsider the decision not to perform a substantive review or DCAA audit of MCDA’s March 1, 2021 revised REA.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

M. Maropakis Carpentry, Inc. v. United States
609 F.3d 1323 (Federal Circuit, 2010)
Todd Construction, L.P. v. United States
656 F.3d 1306 (Federal Circuit, 2011)
Trusted Integration, Inc. v. United States
659 F.3d 1159 (Federal Circuit, 2011)
Sikorsky Aircraft Corporation v. United States
773 F.3d 1315 (Federal Circuit, 2014)
Hejran Hejrat Co. Ltd v. US Army Corps of Engineers
930 F.3d 1354 (Federal Circuit, 2019)
Electric Boat Corporation v. Secretary of the Navy
958 F.3d 1372 (Federal Circuit, 2020)
Zafer Construction Company v. United States
40 F.4th 1365 (Federal Circuit, 2022)
Skelly v. United States
685 F.2d 414 (Court of Claims, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
Midatlantic Construction & Design Associates, Inc. v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/midatlantic-construction-design-associates-inc-v-united-states-uscfc-2023.