Dan Rice Construction Co. v. United States

36 Fed. Cl. 1, 1996 WL 325923
CourtUnited States Court of Federal Claims
DecidedJune 12, 1996
DocketNo. 95-274 C
StatusPublished
Cited by2 cases

This text of 36 Fed. Cl. 1 (Dan Rice Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dan Rice Construction Co. v. United States, 36 Fed. Cl. 1, 1996 WL 325923 (uscfc 1996).

Opinion

OPINION AND ORDER

TURNER, Judge.

This opinion addresses defendant’s motion filed March 19, 1996 for summary judgment. For reasons stated below, we conclude that genuine issues of material fact remain regarding the issues covered in defendant’s motion and, consequently, that defendant’s motion must be denied.

I

In June 1992, plaintiff entered into a construction contract with the National Aeronautics and Space Administration for the replacement of a Payload Spin Test Facility and for construction of additions to the Hazardous Operation Support Facility at Kennedy Space Center, Florida. The original contract amount was $6,958,220 and the original performance time was 500 calendar days. On September 24,1992, plaintiff received the notice to proceed.

As part of the concrete foundation for the Support Facility structure, the contract required plaintiff to install 248 augured, grout-injected concrete piles. Plaintiff began work on this portion of the contract in the fall of 1992. When the piles were finished, they were examined and tested to insure integrity and lack of contamination. The inspection showed possible contamination of some of the piles. Plaintiff agreed to perform pile integrity tests upon a random sample of the piles, and a subcontractor was hired to perform these tests. The parties disagreed over the significance of the test results; defendant was not satisfied with the results. Thereafter, plaintiff removed the top two feet of all of the piles and performed additional integrity testing. Plaintiff claims that the piles were not found to be defective or nonconforming and brought this suit to recover for increased costs and delay allegedly incurred as a result of unnecessary repair work and reconstruction. Plaintiff contends that this work was beyond the scope of the original contract and constituted a constructive change to the contract. According to plaintiff, it is entitled to an equitable adjustment of not less than $200,000.

II

Summary judgment is appropriate when there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. RCFC 56(c); Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 247, 106 S.Ct. 2505, 2509-10, 91 L.Ed.2d 202 (1986); Mingus Constructors, Inc. v. United States, 812 F.2d 1387, 1390 (Fed.Cir.1987). A “material fact” is a fact that could make a difference in the outcome of a case. Curtis v. United States, 144 Ct.Cl. 194, 199, 168 F.Supp. 213, 216 (1958), cert. denied, 361 U.S. 843, 80 S.Ct. 94, 4 L.Ed.2d 81 (1959). Only disputes over facts that might affect the outcome of a suit properly will prevent the court from entering summary judgment. Anderson, 477 U.S. at 248, 106 S.Ct. at 2510.

The moving party initially bears the burden of demonstrating the absence of any genuine issue of material fact. That burden may be discharged by showing the absence of evidence in support of the non-moving party’s case. Celotex Carp. v. Catrett, 477 U.S. 317, 322-23, 106 S.Ct. 2548, 2552-53, 91 L.Ed.2d 265 (1986). Once the moving party has discharged its burden, thé burden shifts to the party opposing the motion to demonstrate by sufficient evidence that a genuine issue of material fact remains. Id. at 324-25, 106 S.Ct. at 2553-54. “The non-movant may not rest on its conclusory pleadings but, under Rule 56, must set out, usually in an affidavit by one with knowledge of specific facts, what specific evidence could be offered at trial.” Sweats Fashions, Inc. v. Pannill Knitting Co., 833 F.2d 1560, 1562-63 (Fed.Cir.1987). In considering motions for summary judgment, we view evidence and draw inferences in a light most favorable to the non-moving party. Litton Indus. Products, Inc. v. Solid State Systems Corp., 755 F.2d 158, 163 (Fed.Cir.1985).

[3]*3III

Defendant alternately argues either that plaintiff volunteered to remove the tops of the piles and perform the additional testing or that plaintiff cannot prove that a government agent with contracting authority directed or approved any work beyond the scope of the original contract. With respect to the second alternative, the government asserts that absent a showing of authority, an agreement with the government cannot be enforced. Defendant cites extensive precedent requiring plaintiff to prove authority on the part of the government agent with whom it claims to have contracted.

Defendant asserts that there is no genuine issue of material fact related to the issue of authority because plaintiff has identified the NASA agents who directed the additional work as the Contracting Officer’s Technical Representative (COTR), Donald Minderman, and project engineer, James O’Malley, neither of whom, defendant contends, had contracting authority. Def.’s Mot.Summ.J., App. at 152. Thus, defendant argues, as a matter of law, plaintiff cannot recover based on “unauthorized” modifications.

As defendant contends, contracting authority is a necessary element of a binding contract with the government. See, e.g., City of El Centro v. United States, 922 F.2d 816, 820 (Fed.Cir.1990), cert. denied, 501 U.S. 1230, 111 S.Ct. 2851, 115 L.Ed.2d 1019 (1991); H.F. Allen Orchards v. United States, 749 F.2d 1571, 1575 (Fed.Cir.1984), cert. denied, 474 U.S. 818, 106 S.Ct. 64, 88 L.Ed.2d 52 (1985); Shearin v. United States, 25 Cl.Ct. 294, 297 (1992), aff'd, 983 F.2d 1085 (Fed.Cir.1992). However, under certain circumstances, a plaintiff may be able to establish the formation of a contract with the government even when the contracting agent lacked prior express actual authority. In these rare situations, it must be established either that the agent with whom the claimant negotiated had implied actual authority to make the agreement, H. Landau & Co. v. United States, 886 F.2d 322 (Fed.Cir.1989); Branch Banking & Trust Co. v. United States, 120 Ct.C1. 72, 87, 98 F.Supp. 757, cert. denied, 342 U.S. 893, 72 S.Ct. 200, 96 L.Ed. 669 (1951); Garza v. United States, 34 Fed. Cl. 1, 20 (1995); Miller Elevator Co. v. United States, 30 Fed.Cl. 662, 693 (1994), appeal dismissed, 36 F.3d 1111 (Fed.Cir.1994), or that an agent with authority ratified the agreement after it was made, United States v. Beebe, 180 U.S. 343, 354, 21 S.Ct. 371, 375-76, 45 L.Ed. 563 (1901); Garza, 34 Fed.Cl. at 21; California Sand and Gravel, Inc. v. United States, 22 Cl.Ct. 19, 27-28 (1990), aff'd, 937 F.2d 624 (Fed.Cir.1991), cert. denied, 502 U.S. 1057, 112 S.Ct. 934, 117 L.Ed.2d 105 (1992).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Magnus Pacific Corporation v. United States
133 Fed. Cl. 640 (Federal Claims, 2017)
Dolmatch Group, Ltd. v. United States
42 Cont. Cas. Fed. 77,266 (Federal Claims, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
36 Fed. Cl. 1, 1996 WL 325923, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dan-rice-construction-co-v-united-states-uscfc-1996.