W. H. Armstrong & Co. v. United States

98 Ct. Cl. 519, 1943 U.S. Ct. Cl. LEXIS 100, 1943 WL 4254
CourtUnited States Court of Claims
DecidedMarch 1, 1943
DocketNo. 44583
StatusPublished
Cited by16 cases

This text of 98 Ct. Cl. 519 (W. H. Armstrong & Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
W. H. Armstrong & Co. v. United States, 98 Ct. Cl. 519, 1943 U.S. Ct. Cl. LEXIS 100, 1943 WL 4254 (cc 1943).

Opinions

Madden, Judge,

delivered the opinion of the.court:

Plaintiff contracted with the defendant to build some thirteen officers’ quarters at Bolling Field in the District of Columbia for $142,046.00. Plaintiff was to furnish all labor and materials to complete the job, except common bricks, which were to he furnished by the defendant. According to the specifications, the basement walls were to be constructed of common bricks, and the walls above the basement were to have a facing of facing bricks backed with common bricks. Before plaintiff submitted its bid, its representatives visited the site and asked to see the common bricks which the defendant intended to furnish for the job. The defendant’s Constructing Quartermaster, who was to be the defendant’s representative in dealing with the contractor, [526]*526showed plaintiff’s representatives a stock pile of more than a million salvaged common red shale bricks of good quality. Plaintiff took samples of these bricks and in computing the amount of its bid estimated the amount of labor and mortar to be used in laying the bricks under the contract on the assumption that common bricks such as were in the stock pile would be furnished.

Plaintiff subcontracted the labor of laying the bricks for $11,400. The bricklaying began September 12, 1932, and bricks from the stock pile were used for about a month. Then the defendant’s agents directed plaintiff to use no more bricks from the stock pile, but to use bricks salvaged from a dismantled steel plant near the site and cleaned. Plaintiff asked for and obtained the contract to clean these bricks. The steel plant bricks were irregular in size and shape, many of them being fire bricks, which are considerably larger than common bricks, and are pemus and absorb the water from the mortar and thus create difficulties in laying them. The larger size of the steel plant bricks made the walls thicker and thus required the use of more mortar.

Plaintiff’s subcontractor protested to plaintiff at the change in the kinds of bricks, and plaintiff agreed to pay him extra compensation for his extra labor: Plaintiff protested orally to the defendant’s representative, the Constructing Quartermaster, who entered into an oral agreement with plaintiff that plaintiff would continue to use the steel plant bricks and would later present its extra costs to the Constructing Quartermaster for audit.

September 25, 1933, after the completion of the contract, plaintiff submitted a claim to the then Constructing Quartermaster for its additional costs, but nothing has been paid plaintiff in that regard. Plaintiff’s increased cost of mortar was $1,649.26, and plaintiff paid its bricklaying subcontractor $4,000.00 to settle a law suit brought against plaintiff by the subcontractor for the increased cost of laying the irregular bricks.

Plaintiff, no doubt for the purpose of by-passing obstacles in the shape of non-compliance with formal requirements of the contract, plants its case upon the theory that the defendant breached the contract as written, when it ordered the [527]*527use of the steel plant bricks, and thereby excused plaintiff from strict performance of the contract and laid itself liable to compensate plaintiff for the losses caused by its breach.

We think that plaintiff’s theory is not supportable. We think that the Contracting Quartermaster’s direction to plaintiff was, except for the form in which it was given, a modification which the defendant had the power'to make, under the terms of the contract. It was either an order for extra work or material within the provisions of Article 5 of the contract and Section 27 of the specifications, or a change order under Article 3 of the contract, which provisions are quoted in finding 15. We are therefore obliged to determine whether the obstacles to recovery which plaintiff by its theory sought to avoid are insuperable, as the defendant urges.

We think that Article 5 of the contract is the applicable article. The Constructing Quartermaster’s direction to use the steel plant bricks was, in effect, an order to use whatever extra labor and extra mortar it 'would take to make walls out of such bricks. So Article 5 fits the situation quite precisely. If neither Article 5 of the contract nor Section 27 of the specifications were present, Article 3 might be made to apply, but that is not necessary with these other provisions present.

When one party writes a contract in its own language, as the Government did here, and inserts in it two separate provisions, either of which might apply to a given state of facts, but different legal consequences would result if one, rather than the other, of the two provisions was applied, the other party to the contract is, in the absence of evidence of a contrary intent, entitled to have applied the provision which would be least burdensome to him.

The defendant urges that, even though Article 5 is the applicable article, and it contains no requirement of approval by the head of the department of an order for extra work or material, yet such a requirement should be read into Article 5 by implication. The defendant argues that the contract is not very rational unless these two articles are read as being consistent with each other. We are inclined to agree. But it was the defendant’s writing, its standard [528]*528form of contract prepared with great care, used by it thousands of times, and we are not willing to read into it important provisions which are not there, in order to enable the defendant to escape from pajdng'for what its officer ordered, and the defendant has received and is, presumably, .now enjoying.' We conclude therefore that under a proper interpretation of the contract, the order of the Constructing Quartermaster- was given under Article 5 of the contract, and the approval of the head of. the department, written or otherwise, was not necessary to the validity of the order.

•We coiné now to the question whether the• Constructing Quartermaster's failure to write his order for the extra work and materials prevents plaintiff from recovering for them.

It would have been impracticable for either plaintiff or the Government to have followed strictly the injunction of Article 5 in this case. The right price for the extra work and mortar could only have been guessed at when the order was first given. Ordinary prudence on the part of each •would have required what was done here, viz, the deferment of consideration of the cost to a later time. Our observation of cases litigated here tells us that this kind of prudence is frequently practiced in such situations. If the Constructing Quartermaster had done here what was agreed to be done, and had given plaintiff a written order after the extra cost had been determined, the bill would quite certainly have been paid, though Article 5 would not have been strictly complied with. If the Constructing Quartermaster had, at the time he gave his order, said in writing what he said orally, that would not have been a compliance with Article 5, which requires that the “price (be) stated in such order.” Strictly, plaintiff could not have protected itself against what has here happened to it except by refusing to obey the order and demanding that the Constructing Quartermaster do, in writing, what was impossible to do at all, viz, fix a price which could not prudently be fixed at that time. Perhaps that would have been correct practice.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Miller Elevator Co. v. United States
39 Cont. Cas. Fed. 76,635 (Federal Claims, 1994)
Calfon Construction Inc. v. United States
35 Cont. Cas. Fed. 75,738 (Court of Claims, 1989)
Martin J. Simko Construction, Inc. v. United States
33 Cont. Cas. Fed. 74,888 (Court of Claims, 1986)
United States v. Cottrell
287 F. Supp. 877 (E.D. California, 1968)
The Len Company and Associates v. The United States
385 F.2d 438 (Court of Claims, 1967)
General Bronze Corporation v. The United States
338 F.2d 117 (Court of Claims, 1964)
Williams v. United States
127 F. Supp. 617 (Court of Claims, 1955)
Whitman v. United States
110 F. Supp. 444 (Court of Claims, 1953)
Stiers v. United States
121 Ct. Cl. 157 (Court of Claims, 1951)
Branch Banking & Trust Co. v. United States
98 F. Supp. 757 (Court of Claims, 1951)
Moorman v. United States
82 F. Supp. 1010 (Court of Claims, 1949)
Globe Indemnity Co. v. United States
102 Ct. Cl. 21 (Court of Claims, 1944)

Cite This Page — Counsel Stack

Bluebook (online)
98 Ct. Cl. 519, 1943 U.S. Ct. Cl. LEXIS 100, 1943 WL 4254, Counsel Stack Legal Research, https://law.counselstack.com/opinion/w-h-armstrong-co-v-united-states-cc-1943.