Whitman v. United States

110 F. Supp. 444, 124 Ct. Cl. 464
CourtUnited States Court of Claims
DecidedMarch 3, 1953
Docket48725
StatusPublished
Cited by5 cases

This text of 110 F. Supp. 444 (Whitman v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whitman v. United States, 110 F. Supp. 444, 124 Ct. Cl. 464 (cc 1953).

Opinion

HOWELL, Judge.

This is an action for an increase in fixed fee in the amount of $126,216.60, under a cost-plus-a-fixed-fee contract. By order of the court dated October ll, 1948, the proceedings in this case were, on defendant’s motion pursuant to old Rule 39(b), limited to the preliminary question of the validity of certain releases furnished by plaintiffs to defendant.

It is plaintiffs’ position that the releases are invalid, and that even if valid, they do not bar the claim here asserted. Defendant contends that the releases are valid, and that they preclude recovery of any increase in plaintiffs’ fixed fee.

On August 6, 1940, plaintiffs and defendant entered into a contract whereby defendant engaged the services of plaintiffs as Architect-Engineer in the construction of a large 'Chemical Warfare Service project at Edgewood, Maryland. The contract provided that plaintiffs would receive as compensation for their services a fixed fee of $60,-400. This amount was based on defendant’s estimate of cost of the project as $5,559,273, with an estimated completion time as provided for in the contract of 10 months.

This contract was the second one covering work of the nature here involved awarded by the Army, and it was plaintiffs’ initial contract of the kind. The information furnished plaintiffs prior to the signing of the contract was insufficient for plaintiffs to formulate an estimate of their own as to the probable cost and completion time of the work, and indicated that the work to be performed was novel and complicated. Plaintiffs relied on defendant’s estimate of the cost of and time for the project as being as reasonably accurate and determinative of the scope of the work as could be made at the then existing stage of the plans. Actually, however, defendant at that time had insufficient information to enable it to determine the amount or extent of the work required under the contract.

Within a month after the execution of the contract, plaintiffs realized that the cost of the work to be done would exceed defendant’s original estimate of cost. In November 1940, three months after the signing of the contract, an estimate by defendant placed the cost at $11,740,000. Later information available to plaintiffs indicated that even this estimate was too low, and on February 24, 1941, defendant made a new estimate of the cost of the project in an amount exceeding $19,000,000. Both prior to and after the defendant’s estimate of February 24, 1941, plaintiffs made several attempts in writing to secure an increase in their fixed fee. These are summarized in findings 6-and 7. Defendant made no re *446 sponse in writing to these and other requests by plaintiffs for an increase in fee.

During the course of the contract work, increases in the scope of the work were ordered by defendant, although these were never formally characterized as changes in the scope of the work. While the contract work was under way, defendant added other work by change orders, the estimated cost of which was $6,636,437,. and the actual cost of which exceeded $9,000,000. Plaintiffs have been paid additional compensation for the change order work, and it is not involved in this suit.

The extent of the change in the scope of the work not covered by change orders could not have been fully and accurately determined prior to the completion of the contract. 1 Although defendant made no response in writing to plaintiffs’ written requests for an increase in their fixed fee, defendant’s officers orally urged plaintiffs to proceed with the contract work and to,postpone determination of the exact scope of the work and the consideration of additional compensation until the conclusion of the contract. Except for the requests for readjustment,previously referred to, plaintiffs acceded to these promptings and completed the project.

Work under the original contract, exclusive of change order work, was substantially completed in June 1942. It had extended over a, period of 22 months, and had cost in excess of $17,000,000. The work covered ,by change orders was completed on March 6, 1943. The total cost of the project was approximately $26,500,000.

In the early summer of 1941, plaintiffs were .asked by defendant to make an inspection of sites for another project similar to the one under way at Edgewood. Following plaintiffs’ recommendation of -Huntsville, Alabama, this site was selected by defendant as the location of the new project, and plaintiffs were advised that they had been selected as Architect-Engineer of ' the Huntsville work. Plaintiffs promptly began preparations to move some, of their men from Edgewood to Huntsville, and to recruit other personnel.

Subsequently, on July 8, 1941, plaintiffs were advised for the first time that they could not obtain the Huntsville contract unless and until a release of claims for an increase in fixed fee on the Edgewood contract was executed.. On July 10, 1941, plaintiffs executed and delivered to defendant the required release, which is quoted in finding 13. At the time this release was entered into, the only claim which plaintiffs had arising out of the Edgewood contract was the claim for increase in fixed fee, and they believed that it was being held in abeyance pending the completion of 'the Edge-wood contract.

In August 1941 the parties began negotiations for another project, hereinafter referred to as the Redstone project or contract. This contract was entered into on August 23, 1941, but before its execution plaintiffs were confronted with and required to sign a release identical in terms with the one referred to above. In May 1942 negotiations were begun for another project, hereinafter referred to as the Denver project or contract. Work on this project was begun immediately, before any formal contract was submitted to plaintiffs. The Denver contract was executed by plaintiffs and defendant’s contracting officer on June 2, 1942. ■ On July 1, 1942, plaintiffs executed and delivered -to defendant a third release pertaining to the Edgewood contract. This release is quoted in finding 19.

As heretofore indicated, the Edgewood project was completed on March 6, 1943. On September 7, 1943, defendant forwarded to plaintiffs a “Final Release” 2 on the Edge-wood work, to be executed and returned. By letter dated September 16, 1943, plaintiffs returned duly executed (as of September 13, 1943) the release quoted in finding 21. In this so-called “Final Release,” plaintiffs excepted from the release a “claim for estimated fixed fee of $50,000:” The re *447 maining fixed fee due plaintiffs under the Edgewood contract was paid on November 30, 1943.

On March 16, 1944, plaintiffs submitted to the Contracting Officer their claim in writing “for an equitable adjustment of fee * * On August 29, 1944, the Contracting Officer denied the claim. His decision is quoted in part in finding 23. The denial of the claim was based on the releases which are here in issue.

Plaintiffs, on September 28, 1944, appealed the ruling of the Contracting Officer, asserting that there was no valid release which precluded consideration of plaintiffs’ claim. On October 26, 1944, plaintiffs were furnished a copy of the Contracting Officer’s findings of fact in connection with plaintiffs’ appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Thomas Creek Lumber & Log Co. v. United States
41 Cont. Cas. Fed. 76,971 (Federal Claims, 1996)
Martin J. Simko Construction, Inc. v. United States
33 Cont. Cas. Fed. 74,888 (Court of Claims, 1986)
Arthur Venneri Company v. The United States
381 F.2d 748 (Court of Claims, 1967)
Moran Bros., Inc. v. The United States
346 F.2d 590 (Court of Claims, 1965)
Copco Steel & Engineering Co. v. The United States
341 F.2d 590 (Court of Claims, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
110 F. Supp. 444, 124 Ct. Cl. 464, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whitman-v-united-states-cc-1953.