Griffiths v. United States

77 Ct. Cl. 542, 1933 U.S. Ct. Cl. LEXIS 279, 1933 WL 1783
CourtUnited States Court of Claims
DecidedMay 8, 1933
DocketNo. L-196
StatusPublished
Cited by9 cases

This text of 77 Ct. Cl. 542 (Griffiths v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Griffiths v. United States, 77 Ct. Cl. 542, 1933 U.S. Ct. Cl. LEXIS 279, 1933 WL 1783 (cc 1933).

Opinion

Williams, Judge,

delivered the opinion of the court:

This case grows out of a contract entered into between the plaintiff and the War Department for the construction of ten lavatory buildings at Fort Sheridan, Illinois.

The plaintiff seeks recovery on three items, viz:

(1) The sum of $2,440, imposed and deducted as liquidated damages because of 122 days’ delay in completing the work under the contract.

(2) The sum of $7,778.00, alleged loss and damage because of defendant’s requirement that plumbing fixtures manufactured by J. L. Mott Company, Inc., be installed instead of Armco plumbing fixtures which plaintiff claims met the requirements of the contract.

(3) The sum of $492.00 for fill for the interior of the buildings because of the change in the axes of the buildings from a north and south direction to an east and west direction.

The three items of the claim will be considered in the order of their statement.

1. Liquidated damage claim, $2,440

The contract was executed by the parties on December 21, 1927. It provides that work shall be commenced on or before December 27, 1927, and shall be completed on or before April 25, 1928.

[550]*550It further provides that the contract shall be subject to the written approval of the Quartermaster General, Washington, D.C., or such officer as he may designate and shall not be binding until approved. The contract was approved by an officer designated for that purpose by the Quartermaster General, on January 27, 1928, the plaintiff receiving notice of this fact on February 1, 1928, 31 days and 35 days, respectively, after the date fixed in the contract for commencement of the work.

Work under the contract was completed on August 25, 1928, or 122 days after the completion date in the contract. On settlement the defendant imposed liquidated damages at $20 per day for each of the 122 days of delay in completing the work, and withheld from the amount otherwise due plaintiff under the contract the sum of $2,440.

The plaintiff contends that by reason of the failure of the Quartermaster General to approve the contract in the manner provided therein, until a date subsequent to the date fixed in the contract for beginning the work, the time limit provision of the contract was waived, and that plaintiff became charged with a liability only of performing within a reasonable time, and that this is so without regard to whether the delay of the Quartermaster General in approving the contract was in fact the cause of, or contributed to, the delay in completion of the work. Cathell et al., v. United States, 46 C.Cls. 368; Snare & Triest Co. v. United States, 43 C.Cls. 364; Ittner v. United States, 43 C.Cls. 336; Little Falls Knitting Mills Co. v. United States, 44 C.Cls. 1, are cited as supporting this contention.

It is well settled that where a contract contains a clause which makes its final execution dependent upon the approval of the head of a department or some supervising official of the Government, it is not a binding obligation until such approval is had. Monroe v. United States, 184 U.S. 524. It is likewise well settled that where time is an essence of a contract and the Government by its delay prevents performance within the contract time, such delay will operate as a waiver of the time limit and give the contractor a reasonable time in which to perform. The effect of the [551]*551decisions relied upon by plaintiff is an affirmation of these well-settled rules.

While the contract in this case was not approved by the designated agent of the Quartermaster General until January 27, 1928, and did not become binding until that date, plaintiff, without waiting for such approval, immediately started to perform. On December 27, the date fixed in the contract for beginning the work, ground upon which the buildings were to be erected was broken. It is true this work was comparatively unimportant, and was performed by defendant upon authorization of plaintiff to prevent the lapsing of the funds available for the contract, but it was nevertheless the beginning of the work. Plaintiff’s foreman arrived on the premises not later than the middle of January, bringing with him the necessary tools and equipment. He proceeded immediately to provide adequate working quarters, prepare the ground, run lines, set stakes, and make all necessary preliminary preparations for the work. While the evidence is conflicting as to what extent the work was prosecuted prior to the receipt of notice of the approval of the contract, the conclusion is justified that the work of excavation was begun on or about January 18. Plaintiff stated that when he visited the site about the middle of February, foundations for four or five of the buildings were in, and that excavations for all but two of them had been made, and that the work up to that time had progressed very satisfactorily. The evidence shows that prior to that date plaintiff had been delayed approximately 15 days in pouring concrete for the foundations because of excessive cold weather, making it physically impossible for the work to have progressed to the point stated by plaintiff, if the work of excavation had not started prior to January 27. It is clear, therefore, that plaintiff commenced work and proceeded with it without waiting for the approval of the contract, and that he was not delayed in performance by the failure of the Quartermaster General to approve the contract prior to December 27, 1927, when work under it was to begin. His failure to perform within the time specified was due to his own delay in procuring the plumbing [552]*552fixtures called for in the specifications, which were not ordered until May 24, 1928, one month subsequent to the date named in the contract for completion of the work, and also one month after all work, except the installation of these fixtures, had been practically finished.

Had the failure of the Quartermaster General to approve the contract, until a day subsequent to the time designated for beginning the work, been the cause of the plaintiff’s delay in completing the work within the time stipulated, such failure, under the authorities cited by plaintiff, would have operated as a waiver of the time limit provision of the contract, and imposed upon the plaintiff an obligation to complete the work within a reasonable time. But, as we have seen, such was not the case. He went immediately upon the premises and started operations under the contract without waiting for its approval. In these circumstances the delay of the Quartermaster General in approving the contract cannot be construed as a waiver of the time provision. It did operate, however, by implication to extend the time for performance a corresponding length of time, continuing in force as applicable to the extended time the liquidated damage clause of the contract. Laidlow-Dunn-Gordon Co. v. United States, 47 C.Cls. 271; McGowen v. American Pressed Tan Bark Co., 121. U.S. 575; Hinkley & Powers v. United States, 49 C.Cls. 148. Plaintiff was therefore entitled to an extension of 35 days from April 25,1928, in which to complete the contract — -the length of time between December 27, 1927, when work was to begin, and February 1,1928, the date on which he received notice of the approval of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Len Company and Associates v. The United States
385 F.2d 438 (Court of Claims, 1967)
Stiers v. United States
121 Ct. Cl. 157 (Court of Claims, 1951)
Alamo Construction Co. v. United States
86 F. Supp. 845 (Court of Claims, 1949)
W. H. Armstrong & Co. v. United States
98 Ct. Cl. 519 (Court of Claims, 1943)
Hirsch v. United States
94 Ct. Cl. 602 (Court of Claims, 1941)
Holmberg v. United States
91 Ct. Cl. 501 (Court of Claims, 1940)
Mueller v. United States
90 Ct. Cl. 401 (Court of Claims, 1940)
Triest & Earle, Inc. v. United States
89 Ct. Cl. 5 (Court of Claims, 1939)
Karno-Smith Co. v. United States
84 Ct. Cl. 110 (Court of Claims, 1936)

Cite This Page — Counsel Stack

Bluebook (online)
77 Ct. Cl. 542, 1933 U.S. Ct. Cl. LEXIS 279, 1933 WL 1783, Counsel Stack Legal Research, https://law.counselstack.com/opinion/griffiths-v-united-states-cc-1933.