Gleason v. United States

33 Ct. Cl. 65, 1897 U.S. Ct. Cl. LEXIS 6
CourtUnited States Court of Claims
DecidedDecember 6, 1897
DocketNos. 17782 and 17783
StatusPublished

This text of 33 Ct. Cl. 65 (Gleason v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Gleason v. United States, 33 Ct. Cl. 65, 1897 U.S. Ct. Cl. LEXIS 6 (cc 1897).

Opinion

Peelle, J.,

delivered the opinion of the court:

These actions grow out of alleged breaches by the defendants of two separate contracts entered into by them with the claimants, the first of which, dated August 4,1885, was for the excavation of 110,000 cubic yards, more or less, of rock excavation “in the enlargement of the Louisville and Portland Canal” in Kentucky, the work thereunder to be completed on or before December 31,1886.

The second contract, dated January 13,1887, was for the excavation of 124,000 cubic yards, more or less, of earth, and 13,000 cubic yards, more or less, of solid rock excavation, “for enlarging the basin of the Louisville and Portland Canal at the head of the locks,” which work was to be completed bn or before December 31, 1887.

Both contracts were extended, the first twice and the second three times, the last extension of the first contract being to December 31, 1888, and the last of the second contract to December 1,1888.

During the season of 1888, the period of the last extensions, the condition of the Ohio River “was unusual and unprecedented for repeated and continued freshets of high water,” -in consequence of which the working season in the Ohio Eiver at Louisville, Ky., was limited to about thirty-five days, and by reason of which the claimants, without any fault on their part, were prevented from completing the work within the time agreed upon in the contracts as last extended.

At and after the expiration of the contracts so extended, the claimants, through the personal solicitations of their attorneys, [84]*84applied to the engineer in charge for an allowance of additional time for the completion of the work agreed upon, for the reason that they had been, by freshets, high water, or other force of the elements, and by no fault of their own, prevented from completing the work within the time agreed upon, bnt the engineer officer in charge refused to allow any additional time, basing his refusal on the claimants’ failure to complete the work within the times agreed upon prior to the last extensions.

Before the first contract was entered into, the engineer in charge prepared specifications for the information of bidders, which the claimants examined, and on the faith of which they entered into the contract. These specifications provided, among other things, that their contract would provide‘‘that additional time may be allowed to a contractor for beginning or completing his work in cases of delay from freshets, ice, or other force or violence of the elements, and by no fault of his or their own.”

There was no such provision iu the specifications exhibited for the information of bidders before the second contract was entered into, but both contracts contained the following provision :

“If, in any event, the party of the second part shall delay or fail to commence with the delivery of the material or the performance of the work on the day specified herein, or shall, in the judgment of the engineer in charge, fail to prosecute faithfully and diligently the work in accordance with the specifications and requirements of this contract, then, in either case, the party of the first part, or his successor legally appointed, shall have power, with the sanction of the Chief of Engineers, to annul this contract by giving notice in writing to that effect to the party or parties (or either of them) of the-second part, and upon the giving of such notice all money or reserved percentage due or to become due to the party or parties of the second part by reason of this contract shall be and become forfeited to the United States; and the party of the first part shall be thereupon authorized, if an immediate performance of the work or delivery of the material be in his opinion required by the public exigency, to proceed to provide for the same by open purchase or contract, as prescribed in section 3709 of the Revised Statutes of the United States; provided, however, that if the party or parties of the second part shall, by freshets, ice, or other force or violence of the elements, and by no fault of his or their own, be prevented either from commencing or completing the work or delivering the materials at the time agreed upon in this contract, such additional time may in writing be allowed him or them for such commencement [85]*85or completion as, in the judgment of the party of the first part or his successor, shall be just and reasonable; but such allowance and extension shall in no.manner affect the rights or obligations of the parties under this contract, but the same shall subsist, take effect, aud be enforceable precisely as if the new date for such commencement or completion had been the date originally herein agreed upon.”

By reason of the proviso to the paragraph of the contract just quoted, the claimants contend that, notwithstanding' the extensions theretofore granted, they were entitled, by reason of the delay caused by the freshets aforesaid, to an allowance of additional time within which to complete the work agreed upon in the contract last extended, and that the refusal of the engineer officer in charge to allow additional time was a breach of the contracts on the part of the defendants, resulting in great damage to the claimants in the loss of profits which would have accrued to them had such additional time been allowed.

The defendants contend that, in the absence of fraud, actual or constructive, the decision of the engineer officer in charge in refusing an extension of time for the completion of the work under the contract is final and conclusive and can not be reviewed by this court.

As to whether the extensions or allowances of additional time prior to December, 1888, were or were not granted on sufficient grounds, we are not called upon to decido. Nor is it necessary for us to consider the question as to -whether the defendants’ officers had the right, except in the manner provided by Bevised Statutes, section 3709, to impose new conditions as the basis of an extension, as appears to have been done in the case of the first contract.'

Both parties treat the extensions as having been made on sufficient grounds, and once consummated, the contract provides that “ such allowance and extension shall in no manner affect the rights or obligations of the parties under this contract, but the same shall subsist, take effect, and be enforceable precisely as if the new date for such commencement or completion had been the date originally herein agreed upon.”

So that, for the purpose of these cases, we have only to do with the contracts as last extended; and in this respect we will consider the several dates for the completion of the work in December, 1888, as though they were the dates originally' agreed upon in the contracts.

[86]*86Whatever delays or defaults on the part of the claimants . may have occurred prior to the last extensions of the contracts were waived by the defendants when the extensions thereof were granted; no forfeitures were declared at the time, and by the several extensions were waived, and once waived, can not be revived. (Pigeon’s Case, 27 C. Cls. R., 167, 176.) So that the delay or diligence of the claimants in respect of the prosecution of the work could only be looked to by the officer in charge during the period of the last extensions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Buren v. Digges Ex Rel. Libbey
52 U.S. 461 (Supreme Court, 1851)
Dermott v. Jones
69 U.S. 1 (Supreme Court, 1865)
Gordon v. United States
74 U.S. 188 (Supreme Court, 1868)
United States v. Speed
75 U.S. 77 (Supreme Court, 1869)
Smoot's Case
82 U.S. 36 (Supreme Court, 1873)
Canal Co. v. Hill
82 U.S. 94 (Supreme Court, 1872)
Utley v. Donaldson
94 U.S. 29 (Supreme Court, 1877)
United States v. Smith
94 U.S. 214 (Supreme Court, 1877)
Kihlberg v. United States
97 U.S. 398 (Supreme Court, 1878)
Chicago & Northwestern Railway Co. v. United States
104 U.S. 680 (Supreme Court, 1882)
Merriam v. United States
107 U.S. 437 (Supreme Court, 1883)
United States v. Gibbons
109 U.S. 200 (Supreme Court, 1883)
Sweeney v. United States
109 U.S. 618 (Supreme Court, 1884)
United States v. Behan
110 U.S. 338 (Supreme Court, 1884)
Mobile & Montgomery Railway Co. v. Jurey
111 U.S. 584 (Supreme Court, 1884)
Martinsburg & Potomac Railroad v. March
114 U.S. 549 (Supreme Court, 1885)
Wheeler v. New Brunswick & Canada Railroad
115 U.S. 29 (Supreme Court, 1885)
Chicago, Santa Fé & California Railroad v. Price
138 U.S. 185 (Supreme Court, 1891)
Gilmore v. Courtney
41 N.E. 1023 (Illinois Supreme Court, 1895)
Kennedy v. United States
24 Ct. Cl. 122 (Court of Claims, 1889)

Cite This Page — Counsel Stack

Bluebook (online)
33 Ct. Cl. 65, 1897 U.S. Ct. Cl. LEXIS 6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/gleason-v-united-states-cc-1897.